About this file
This document is a Contract Bid Schedule for a federal solicitation to install a Stinson Beach Lifeguard Locker Room Trailer and renew/reconfigure the Stinson Beach Maintenance Building. The solicitation number is 140P8624R0011 and the agency is the Department of the Interior National Park Service Pacific West Region.
The bid schedule includes two base line items: 1) Shower Trailer Supply and Installation and 2) Renew and Reconfigure Maintenance Building. Offerors must submit a conforming offer with pricing for these base line items. The government reserves the right to award any or no options at or after the time of award, and pricing will be evaluated to determine best value. Offerors are encouraged to submit alternate proposals that could result in cost savings to the government.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P8624R0011_Amd_0002.pdf | ||
| B08_Attachment_9_Maintenance_Building_Dimensions_0002.pdf | ||
| Sol_140P8624R0011_Amd_0001.pdf | ||
| B08_Attachment_4_Limitations_on_Subcontracting_Report.xlsx | XLSX spreadsheet | |
| Sol_140P8624R0011.pdf | ||
| B08_Attachment_1_Specifications_Stinson_Beach_.pdf | ||
| B08_Attachment_3_Davis-Bacon_Wage_Rates_CA20240007.pdf | ||
| B08_Attachment_5_Past_Performance_Questionnaire.docx | DOCX document | |
| B08_Attachment_6_General_References.docx | DOCX document | |
| B08_Attachment_7_Relevant_Experience_Questionnaire.pdf | ||
| B08_Attachment_8__VIOLATION_OF_ARMS_CONTROL_TREATIES_OR_AGREEMENTS-CERTIFICATION.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Price Schedule
| CONTRACT BID SCHEDULE | |||||
| SOLICITATION NUMBER: 140P8624R0011 | |||||
| PARK PMIS: 319666 & 319456 | |||||
| DEVELOPED AREA: Golden Gate National Recreation Area | |||||
| PROJECT TITLE: : Install Stinson Beach Lifeguard Locker Room Trailer + Renew and Reconfigure Stinson Beach Maintenance Building | |||||
| Notice: Offerors are required to submit, a minimum, an offer that conforms to the solicitation documents with pricing for Base line items. Failure to do so may render the proposal unacceptable. On lump-sum line items, provide the total price only. For all unit-priced line items, provide the unit price and the extended total price. If no specific line item exists for a portion of the work, include the costs in a related item. In case of error in calculation of extended prices, the unit price governs. In case of error in summation, the total of the corrected amounts govern. Round totals and extended prices to whole dollars. The Government reserves the right to award any or no options at or after the time of award. At the option of the Government, the period for exercise of options at the proposed prices shall extend 180 calendar days from the date of award. Pricing will be evaluated based on what is determined to be the best value to the Government. Options may be exercised in any combination, order, or grouping deemed in the judgment of the Contracting Officer to offer the best value to the Government. | |||||
| In addition to the offer that conforms to the solicitation documents, offerors are encouraged to submit alternate proposals that will result in cost savings to the Government. Such proposals shall clearly identity why the acceptance of the alternate proposal would be advantageous to the Government, see FAR Clause 52.215-1, Instructions to Offerors - Competitive Acquisition-Alternate II and DSC-36 Clause (Instructions for Submission of Offers and Other Information) in Section L of the Solicitation. | |||||
| CONTRACT LINE ITEM NUMBER (CLIN) | CONTRACT LINE ITEM (CLI) TITLE | QUANTITY | UNIT OF MEASURE | UNIT PRICE | TOTAL PRICE |
| BASE | |||||
| 1 | Shower Trailer Supply and Installation | 1 | LS | $0.00 | |
| 2 | Renew and Reconfigure Maintenance Building | 1 | LS | $0.00 | |
| TOTAL PROPOSED BASE PRICE + Options -------------- CLIN 1 thru CLIN 2 | $0.00 |