DEPARTMENT OF THE INTERIOR

NATIONAL PARK SERVICE

GOLDEN GATE NATIONAL RECREATION AREA

FORT POINT NATIONAL HISTORIC SITE

201 MARINE DRIVE, SAN FRANCISCO, CA 94129

SCOPE OF WORK FOR A SCULPTOR TO

MODEL, MOLD, CAST, FINISH, AND INSTALL TWO BRONZE MODELS, A STYLIZED CIVIL

WAR SOLDIER, AND A SECTION OF FAUX BRICK MASKING THE EMBRASURE OF

CASEMATE 10 AT FORT POINT NATIONAL HISTORIC SITE

PART 1 - GENERAL

Performance Period: The work of this contract shall be provided from approximately April 1, 2022* through December 1, 2022. (*the date might change before the contract award).

Project Identification: The project is located at the FORT POINT NATIONAL HISTORIC SITE, 201 Marine Drive, San Francisco, CA 94129. Fort Point is a unit of the Golden Gate National

Recreation Area.

The work of this contract shall consist of the fabrication and installation of 4 sculptural elements as components to a larger installation of new exhibits (by others), said tasks described below for the referenced project.

Reference numbers of this project: Request For Quotation (RFQ) 140P8622Q0029

Park/PMIS Number: GOGA 234917

Purchase Order/Contract Number: TBD

Contracting Officer: The Contracting Officer (CO) is responsible for all aspects of the project, except as the CO designates the Contracting Officers Representative. The CO is responsible for all contractual and financial details.

The CO for this project is Michael Gabriel, michael_gabriel@nps.gov

Contracting Officer’s Representative: The Contracting Officer’s Representative (COR) is designated by the Contracting Officer (CO) and shall serve as the primary POC for all technical matters. The COR is also responsible for the approval of submittals, progress payments, and acceptance and rejection of work. The COR for this project is Michael Faw, Fort Mason

Building 201, San Francisco, CA 94123, (415) 272-1449, michael_faw@nps.gov.

1.1 BACKGROUND:

Fort Point stands at the south side of the Golden Gate Strait, forming a substantial landmark at the entrance to San Francisco Bay. Built at the site of an old Spanish gun battery, Fort Point was one of the first major U.S. Army installations in the Bay Area. It guarded the San Francisco Bay and Harbor from the Gold Rush-era in the 1850s until World War II. Although no shots were ever fired in anger from Fort Point, it is the most tangible legacy of the Civil War in California, and represents California’s little known, yet significant, political and social involvement in the

Civil War. Built to hold four tiers of cannons, the fort is also an outstanding example of masonry mailto:michael_gabriel@nps.gov fort construction and is the only fort of its style on the West Coast of the United States. As a testimonial to the fort’s historic significance, the southern anchorage of the Golden Gate Bridge was designed to gracefully arch over it.

Fort Point became a National Historic Site in 1970 and is today managed as a district park unit within the larger Golden Gate National Recreation Area. The fort’s scenic location under the south end of the Golden Gate Bridge attracts visitors throughout the year, many of whom accidentally happen on the fort and have no idea of its significance. Over 300,000 people visited

Fort Point in 2017, with a significant number of those being international and national vacationers, particularly during the summer months.

The exhibits to be fabricated under this contract will be installed at Fort Point National Historic

Site (FOPO), at the northwest corner of San Francisco, CA. The contractor shall coordinate with

Capitol Exhibit Services, the fabricator of the rest of the exhibit components.

1.2 SCOPE:

A. Contractor shall furnish all necessary supervision, labor, tools, parts, material, equipment, appurtenances and transportation for the four exhibit components detailed below.

B. Contract documents provided by the Government will include design drawings, renderings, dimensions, material specifications, site photographs and details of the exhibit cabinetry (by others) the sculptural components are to be mounted on. This information will be made available from Michael Faw, Accessibility and Exhibit Specialist, Project Manager and

Contracting Officer’s Representative (COR), Building 201 Fort Mason, (415) 2721449, E-mail:

michael_faw@nps.gov.

1.3 PROJECT DESCRIPTION

The Contractor shall provide all supervision, labor, tools, parts, material, equipment and transportation to complete the following project work items:

CE-01.01-100- Full Three Dimensional Bronze Model of Fort Point exterior, with bronze city bus for scale. See attached drawings for details. Bronze models to be lost wax cast using a

Nickel Silver Bronze alloy, ASTM B149-973, B149-976 or similar. The male model for molding may be hand sculpted, CNC cut, or 3D printed from detailed CAD drawings (available upon request). See attached drawings for details.

CE-02.03-000 Figure of Soldier on Guard Duty- Realistic figure with accurate uniform and firearm, but stylized finish. See attached drawings for details.

CE-04.07-100 Bronze Model of Fort Point Site- Exploring the Grounds. Note revisions for both extents and braille detail on page 16 of the drawing set “Sculptural Elements

2020_02_21_FOPO_FINAL.pdf”. Bronze models to be lost wax cast using a Nickel Silver

Bronze alloy, ASTM B149-973, B149-976 or similar. Male model may be hand sculpted, CNC cut, or 3D printed.

-Note: rather than a separate braille and tactile lettered plaque as show in the Exhibit Drawing package, the braille and tactile lettering is to be cast with the rest of the topographic model. The mailto:michael_faw@nps.gov forward label area will tilt down to the table mount (by others) from the crest of the highest point of the topo model.

The numbers, braille dots, and tactile letters are to be applied on a separately manufactured (as opposed to cast) plaque by Matthews Bronze or similar. Lost wax casting has not historically been of sufficiently consistent detail to meet NPS braille dot standards. See also the attached

NPS “Tactile and Braille Map Guidelines2014.pdf” for detailed braille dot specifications. The

NPS COR will use the MAD Lab (Media And Design) at San Francisco Lighthouse for the Blind to review and approve all braille text layouts.

Casemates 9-11 AV Theater- Faux painted brick panel for a projection surface inside

Casemate 10 in the West Bastion (facing north) less than 48” by 48”, Contractor and COR to confirm final size on site, with confirmation from the AV contractor Monadnock Media. Faux paint detail to be applied to Wonderboard fiberglass mesh-reinforced cement backerboard or similar coarse textured commercially available waterproof sheet stock. Paint details to be applied on site to match existing brick color, size, spacing, and texture detail. Sheet stock to be applied to inset framing (already installed by others).

Attached drawings include:

Sculptural Elements 2020_02_21_FOPO_FINAL.pdf

Sculptural Elements 2020_02_21 FOPO FINAL - DRAWINGS Package.pdf

Tactile and Braille Map Guidelines2014.pdf

A. GENERAL NOTES AND SPECIFICATIONS:

The quality of workmanship, quality and the type of materials, and the details of construction shall conform to all applicable portions of the highest standards except where requirements of the drawings and specifications are in excess thereto, in which case the drawings and specifications shall take precedence. Shop drawings, catalog cuts, etc., shall be submitted for approval by the COR.

Note that Fort Point will remain open to visitors at the hours posted, and at other hours as may be necessary for the operation of the historic site.

The contractor shall not close or obstruct walkways, or passages unnecessarily, and will not place, nor store, material in walkways, in the courtyard general or in passageways.

The contractor shall take precautions to protect all park visitors and park staff members from injury and safety hazard, as well as protect all of those portions of the structure which are not being worked on from any sort of damage. Any damage which does occur will be repaired by the Government and billed to the Contractor.

1.4 WORK SEQUENCE

A. The Work will be conducted in such a manner to provide the least possible interference to occupant access in the area and that causes no damage to historic cultural or natural resources.

1.5 PUBLIC ACCESS AND SAFETY

1.5.1 During the course of this project, the Contractor shall at all times:

A. Conduct operations to ensure public safety and the least inconvenience to the public.

B. Maintain access for National Park Service administrative and other official business throughout the construction phase.

C. During working hours, secure areas that are under construction from visitors.

D. Leave construction area in a condition that is safe for visitors on weekends, holidays, and other times when contract work is not in progress.

1.6 CONTRACTOR USE OF PREMISES

A. Emergencies: Emergency telephone numbers must be posted at the job site.

B. Site & Features Protection: The Fort Point National Historic Site is included on the National

Historic Register. Because of its significance, all parties are to take all measures necessary during the performance of the work to maintain and protect the historic fabric of the site. Plan and perform all work with extreme care to ensure that no building or site features are damaged. Note that all features to remain in place, whether historic or non-historic, should be protected during construction. All work must meet the

Secretary of the Interior’s Standards for the Treatment of Historic Properties.

Consider every aspect of the project from mobilization to demobilization with an expectation for protection of historic features. Immediately report to the COR any unforeseen site conditions.

C. Occupied Sites & Structures: This surrounding site will be open to visitation throughout construction. Contractor should conduct installation work during hours the Fort is closed to the public, which varies by season and staff availability. A firm schedule will be provided at the time of contract award. If work must occur during open hours, Contractor must provide temporary enclosures, barricades, signage, etc. as required to protect adjacent occupied spaces and public areas such as building facilities and materials, etc. from dust, noise and debris associated with performing the work.

D. Hours of Work: On site work must be performed between 7:00 am and 5:00 pm, Monday through Friday. Requests to work outside designated hours must be given in writing a minimum of two (2) working days prior to scheduling, and must be approved in writing by Contracting Officer’s Representative.

E. Stop Work Orders. GGNRA reserves the right to stop work at any time for emergencies/safety violations, and NEPA and NHPA violations. Emergency and safety stop work orders may be issued directly by GGNRA Safety Officer and/or GGNRA Public Safety personnel (law enforcement/fire). All other stop work orders will be issued through the project POCs (CO or COR).

F. Preservation of Natural Features - Vegetation: Confine all operations to work limits of the project. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government. Provide temporary barriers to protect existing trees and plants and root zones. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with COR and remove agreed-on roots and branches that interfere with construction. Do not fasten ropes, cables, or guys to existing trees.

G. Preservation of Natural Features - Wildlife: Do not approach, disturb, harass or feed wildlife.

H. Environmental Protection: Properly clean up, mitigate and remedy, if necessary, all spills of petroleum products, hazardous materials, or other chemical or biological products released from the construction from construction vehicles or stationary sources. Immediately report to the COR any spill of petroleum products or a hazardous material. Report the spill to the appropriate federal, state and local authorities, if the spill is of a reportable quantity. Separate work area, including material sources, by the use of a dike or other suitable barrier that prevents petroleum products, chemicals or other liquid or solid material from entering the waters of the U.S.

1.7 GOVERNMENT FURNISHED MATERIALS.

A. The Government will not furnish any materials or equipment to the Contractor for the

Project.

1.8 CONTRACTOR ACCESS AND USE OF THE SITE

A. All Contractor employees and subcontractor employees shall be advised of the rules and regulations of the National Park Service.

1.9 CLEANUP

A. The Contractor shall at all times keep the work area including the storage areas to be used from unnecessary accumulation of waste material and rubbish. All

Contractor generated waste material and rubbish shall be removed upon completion of the work from the premises and disposed of properly in accordance with all Local, Municipal, State and Federal regulations.

B. Upon completion of work, the Contractor shall ensure that the Project area is in a clean, neat and orderly condition satisfactory to the Project Manager.

1.10 PARKING

A. Parking for Contractor’s vehicles shall be in designated spaces as directed by the COR.

1.11 UTILITIES

A. The Contractor is advised that there no water available in the general area of the work site. Public bathrooms with cold water only are app. 200’ from the entrance to the Fort.

1.12 OPERATING HOURS

A. Regular work hours shall be between 7:00 AM and 5:00 PM, Monday through

Friday, excluding Saturdays, Sundays, and Official Government holidays.

B. If the Contractor intends on working outside of the regular work hours noted prior approval in writing 2 days in advance from COR is required.

1.13 FIELD VERIFICATION

A. Contractor shall perform field verification of all existing conditions affecting the work associated with this contract before ordering of parts, materials and equipment.

1.14 KEY CONTRACTOR PERSONNEL.

A. For the duration of this contract, the Contractor shall appoint a Supervisor and/or Point of Contact and provide the contact information to the COR.

1.15 GOVERNMENT POINTS OF CONTACT

1.15.1 The following are the Government Points of Contact for this contract:

Contracting Officer: Michael Gabriel, michael_gabriel@nps.gov

Contracting Officer’s Representative: Michael Faw, Fort Mason Building 201, San Francisco, CA 94123, (415) 272-1449, michael_faw@nps.gov.

2.0 SAFETY AND ACCIDENT PREVENTION:

2.1. The Contractor shall formulate and submit a written site specific health and safety plan for acceptance by the Government. The written plan shall include the details of the contractor's safety organization, responsibilities, method of program implementation, and how site specific job hazards and deficiencies shall be identified and corrected. It shall detail employee's responsibilities for: protection of Government property and safety of others, employee's responsibilities for reporting all mishaps, and establish procedures for reporting or correcting unsafe conditions, hazards, or practices. The plan shall also contain mishap notification and reporting procedures. The Contractor shall have a central POC for safety and health related issues and the POC shall be identified in writing.

2.2. The Contractor shall ensure employees have safety education when engaged in activities involving Government facilities, personnel, or equipment.

2.3 The Contractor shall immediately notify COR and/or NPS Safety Officer of all accidents/incidents involving employee use of and/or damage/injury to facilities, equipment, or personnel.

2.4 The Contractor shall provide all required personal protection equipment, (e.g.

respirators, hearing protection, eye protection, gloves, steel-toed boots, aprons, masks, face shields, reflective vests, etc. IAW OSHA Standards.)

3.0. ENVIRONMENTAL REQUIREMENTS

3.1 The Contractor shall comply with all federal, state, and local environmental laws, and

NPS policies and regulations to include but not limited to Resource Conservation, Safe

Water Drinking Act (SWDA), the Clean Air Act (CAA), and Federal Facilities

Compliance Act (FFCA).

mailto:michael_gabriel@nps.gov mailto:michael_faw@nps.gov

3.2 The use, handling, storage, and disposal of all toxic, hazardous, special or radiological wastes/materials shall be in accordance with all local, State, Federal, and

NPS Environmental Regulations and procedures; and coordinated with the NPS

Environmental Safety Programs Office and as directed by the COR. Lead based paint is presumed to be present in all historic painted finishes.

3.3 Environmental Management Plan. Not Used

3.4 Vehicles and equipment. All vehicles, tools, equipment and boots entering the project area must be clean of noxious weeds and free from oil leaks and are subject to inspection.

Wash all construction vehicles, tools and equipment thoroughly remove all dirt, plant, and other foreign material prior to entering the project.

4.0 QUALITY CONTROL PLAN

Contractor shall submit to the COR a “Quality Control Plan” for review and approval.

The Quality Control Plan shall include:

1. A list of personnel responsible for quality control and assigned duties, and include each person's qualifications and training certificates,

2. A copy of a letter of direction to the Contractor's Quality Control Supervisor outlining assigned duties,

3. Methods of performing, documenting, and enforcing quality control of all work, including examples of construction progress and quality control reports,

4. Methods of monitoring and controlling environmental pollution and contamination as required by regulations and laws.

4.1 CONTRACTOR PRODUCTION AND QUALITY CONTROL REPORTS

Contractor shall complete standard format daily construction progress reports and weekly quality control reports. Contractor shall submit the reports electronically in a timely manner to the COR.

5.0 SUBMITTAL AND APPROVAL PROCEDURES

A. All submittals must be transmitted using National Park Service form DSC-1(CS), dated 11/95. No action will be taken on a submittal item unless accompanied by the transmittal form. As specified in the individual sections, forward submittals to

Contracting Officer’s Representative at least 30 days before need for approval.

Unless a different number is specified, submit 1 reproducible original and 2 copies of each shop drawing, 2 copies of manufacturer's catalog sheets (product data sheets), 1 specimen of each sample, and 2 copies of all other submittals requested.

B. Shop Drawings: Include the following information with each copy of shop drawings: Date; Date of revisions (when applicable); Details of fabrication, assembly and erection including connections and engagement to contiguous work;

Materials used; All required dimensions. The term "by others" must not be used.

All work to be performed by others must be identified by Contractor or subcontractor name, discipline, or trade.

C. Samples: Samples must be large enough to illustrate clearly the functional characteristics and full range of color, texture, or pattern.

D. Manufacturers' Catalog Sheets: Not used.

E. Manufacturer's Installation Instructions: Not used.

F. COR reserves the right to require submittals in addition to those called for in individual sections, specifically studio progress visits or digital photographic “in process” images.

G. Approved Equals: For each item proposed as an "approved equal," submit supporting data, including the following: Samples as appropriate; Comparison of the characteristics of the proposed item with that specified; Changes required in other elements of the work because of the substitution; Name, address, and telephone number of vendor; Manufacturer's literature regarding installation, operation, and maintenance.

H. A request for approval constitutes a representation that Contractor: Has investigated the proposed item and determined that it is equal or superior in all respects to that specified; Will provide the same warranties for the proposed item as for the item specified; Has determined that the proposed item is compatible with interfacing items; Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution; Waives all claims for additional expenses that may be incurred as a result of the substitution.

I. Construction Materials: The Contractor is encouraged to submit for approval products made out of recycled or environmentally responsible material. Every effort will be made by the National Park Service to approve these materials.

Coordinate all submittals and review them for legibility, accuracy, completeness, and compliance with contract requirements. Forward submittals that are related to or affect one another as a package to facilitate coordinated review. Each transmittal must contain only data specific to that individual submittal.

J. Submittal Identification: Contracting Officer may provide a project identification stamp which must be applied by the Contractor. Identification must include the park name-package number, project title, contract number, and transmittal number. All sets of shop drawings, manufacturer's catalog sheets, samples, and other documents submitted to the Contracting Officer’s Representative must have the identification information stamped on the submittal. Identification information must be applied to the bottom right margin on each page. Identification information on samples must be applied to the most readily visible area on the sample or on tags attached to sample.

K. Submittal Numbering: Number each submittal consecutively. For re-submittals use the original submittal number, plus a letter suffix beginning with A.

Additional re-submittals of the same item must contain the original number with the next consecutive letter.

L. Contracting Officer’s Representative's Review: Submittals will be returned disapproved without technical review if identification information is missing, not filled in, or if placed on the back of the submittal; an incorrect number or format of submittals is provided; the transmittal form is incorrectly filled out; submittals are not coordinated; or submittals do not show evidence of Contractor's approval.

Any work done or orders for materials or services placed before approval must be at the Contractor's own risk.

After reviewing submittals, the Contracting Officer’s Representative will return one copy of form DSC-1(CS) and one copy of applicable (marked up) submittal sheets to the Contractor. Shop drawing review notations will be returned on the reproducible original shop drawing. All other submitted items will be retained.

The Contractor is responsible for producing additional copies for his/her own use.

The returned submittal will be marked in one of three ways as defined below:

APPROVED: Acceptable with no corrections.

APPROVED WITH NOTATIONS: Minor corrections or clarifications required. All comments are clear and no further review is required. The

Contractor must address all review comments when proceeding with the work.

DISAPPROVED - RESUBMIT: Rejected as not in accordance with the contract or as requiring major corrections or clarifications. The

Contracting Officer’s Representative will identify the reasons for disapproval. The Contractor must revise and resubmit with changes clearly identified.

4.0 INVOICING

Vendor shall submit invoices via www.ipp.gov.

END OF SECTION