STATEMENT OF WORK
Replace Windows, Doors and Skylights North Cascades Visitor Center
North Cascades National Park Service Complex
Newhalem, Washington
National Park Service October 2017
RFP 140P8318R0001 North Cascades NPS Complex Attachment 1: Statement of Work
TABLE OF CONTENTS
DIVISION 1 - GENERAL REQUIREMENTS
011100 Summary of Work 012700 Definition of Line Items 013300 Submittals 013523 Safety Requirements 015300 Barriers 015100 Temporary Services 015700 Temporary Controls 017000 Project Closeout 017419 Waste Management 018000 Technical Specifications
SECTION 011100
SUMMARY OF WORK
PART 1: GENERAL
1-1 DESCRIPTION:
A. The work of this contract consists of the Replacement of Windows, Doors and Skylights in the North Cascades National Park (NOCA) Visitor Center (VC) in Newhalem, Wash-ington. When completed, this project will have removed and replaced all skylights, exte-rior windows, and exterior doors at the visitor center.
B. Location: Visitor Center is 0.7 mile South of mile post 119.9 on US Highway 20 in the town of Newhalem, WA
C. The roof of the North Cascades Visitor Center is made of copper and Contractor must take special care not to damage or alter its appearance. The roof is susceptible to damage from direct impacts and exposure to certain chemicals, which can alter the natural patina of the surface.
D. Target work dates are March 1 – May 4, 2018. The Visitor Center (VC) is occupied and actively serving the public mid-May to late October annually.
E. Period of performance: Final construction must be substantially complete by May 4, 2018.
F. Work hours are between 7:00 a.m. and 5:30 p.m., Monday through Thursday, and no work may occur on Fridays or Federal Holidays. Any changes to these days and timeframes must be pre-approved by the COR.
G. Within 20 calendar days of award the Contractor shall provide a detailed construction schedule identifying all major and minor features of work including all closeout docu-mentation required in Section 017000 of this SOW. The schedule shall be updated and submitted with each progress payment request.
H. Maps and park information may be viewed at www.nps.gov/noca
I. All work is to be performed under a single fixed-price contract.
1-2 CONTRACTOR’S USE OF PREMISES:
A. Construction Camp: Establishment of a camp within the park will not be permitted. RV parks are available in Marblemount and there are additional lodging opportunities west of Marblemount on Highway 20.
B. Contractor shall at all times conduct their operations to ensure the least inconvenience to the public. Contractor must minimize disruption to occupants and ensure safe access to and from entrances if on-site work occurs while the VC is open.
C. Materials storage: Storage of construction materials is allowed on-site at a location des-ignated by the Contracting Officer's Representative. Storage of hazardous materials must meet all federal, state, and local guidelines and regulations. On-site storage of the Con-tractor’s materials does not imply acceptance or protection of them by the Government.
D. Preservation of natural features: Confine all operations to work limits of the project.
Prevent damage to natural surroundings. Provide temporary barriers to protect existing trees and plants and root zones. Restore damaged areas, by repairing or replacing dam-aged trees and plants, at no additional expense to the Government.
1. Provide temporary barriers to protect existing trees and root zones.
2. Do not remove, injure, or destroy trees or other plants without prior approval.
Consult with Contracting Officer and only remove agreed upon roots and branches that interfere with construction.
3. Do not fasten ropes, cables, or guys to existing trees.
E. Existing Utilities: Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Govern-ment. Overhead power to buildings must be protected or removed and reinstalled as needed to facilitate work.
F. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials.
G. Contractor must not display signs or advertisements (except those specified herein) on the construction site except with prior approval of the Contracting Officer.
1-3 FIELD VERIFICATION: Field-verify all new and existing dimensions affecting the work of this contract before ordering products.
1-5 PROJECT MEETINGS
A. Preconstruction Conference Before the start of the project, the Contracting Officer will arrange a meeting with the Contractor to be held at NPS offices in Sedro-Woolley, WA or by teleconference.
B. Progress Meetings
Contractor will convene weekly progress meetings with COR and prepare written docu-mentation of topics discussed and decisions reached.
END
SECTION 012700
DEFINITION OF CONTRACT LINE ITEMS
PART 1 GENERAL
1.1 DESCRIPTION
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another be-gins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
1.2 CONTRACT LINE ITEMS
CONTRACT LINE ITEMS 1, 2, and 3 – Remove and replace windows, doors, and skylights in the NOCA Visitor Center; Original Construction drawings have been provided and should be used as a reference for all work on the visitor center. A site visit is highly recommended, as con-tractor is responsible for verifying all of the door, window and skylight sizes as well as assuring the color of the frame (if needed #28 Kawneer Medium Bronze) matches the existing framework.
1. Remove and replace all external windows in the visitor center with gas filled thermal windows with a minimum R-5 rating. All windows will need to be field verified prior to ordering to assure proper sizing as they are all different with many sizes and angles.
Starting at the front and moving clockwise around building:
• 13 windows at the South front main entrance
• 3 windows with one of those being a pop out to the left or West of the main en-trance
• 9 windows on the Northwest rear corner of the visitor center by the West rear patio exit
• 6 windows to the West of the fireplace on North side of building
• 6 windows to the East of the fireplace on North side of building
• 9 windows on the Northeast rear corner of the visitor center by the East rear patio exit door
• 2 second story windows on the East side of the visitor center one is in the inner staircase and the other is in the Library
• 1 window just above the East Side main service entrance
• 3 windows one of those being a pop out on the East side of the building just to the
North of the East side entrance
• 3 windows just to the East or to the right of the main entrance door on the South side of the visitor center the middle window is a pop out
• Re-install security system contacts after installation
• Contractors shall furnish and apply sealants to provide a good weathertight installa-tion on all joints and intersections and at opening perimeters
2. Replace exterior doors at the visitor center to include all hardware and hinges and use gas filled thermal windows with a minimum R-5 rating.
• Replace the South Main front entrance doors as these are thermal glass with panic bars and have the automatic accessible door opener that will need to be replaced (complete opener mechanism and wiring with switch)
• Replace the East side service entrance doors these are thermal glass with panic bars and have the automatic accessible door opener that will need to be replaced (com-plete opener mechanism and wiring with switch)
• Replace the Northwest patio entrance door this is thermal glass with panic bars and has the automatic accessible door opener that will need to be replaced (complete opener mechanism and wiring with switch)
• Replace the Northeast patio entrance door with thermal glass and a panic bar
• Re-install security system contacts after installation
• Replace threshold-new threshold must not exceed ½” in height and be ADA com-pliant
• Install all doors with a brush sweep and narrow body, heavy duty closer
• All doors open to the outside
• Install perimeter (weather) seals and gaskets to ensure a tight seal around the door
• All installation to be plumb and square and door must be free from rack and twist
• Body of doors as well as all related hardware needs to match the current color of doors (#28 Kawneer Medium Bronze)and related framework
3. Replace all skylights in the roof of the visitor center with gas filled thermal skylight panels with a minimum R-5 rating. Please Note: Skylights have leaked on the rare occa-sion in the past and we would like to see if we can get a diagnosis or confirmation of a leaking skylight on this issue.
• Replace 8 skylight panels on the North roof section with thermal glass skylight pan-els
• Replace 12 frosted skylight panels on the center North roof sections with thermal glass skylights
• Replace 12 frosted skylight panels on the center South roof sections with thermal glass skylights
• Replace 8 skylight panels on the South roof section with thermal glass skylight pan-els
• Body of skylights as well as all related hardware should match the current color of skylights (#28 Kawneer Medium Bronze) and related framework
• Contractors shall furnish and apply sealants to provide a good weathertight installa-tion on all joints and intersections and at opening perimeters
SECTION 013300
SUBMITTALS
1-1 DESCRIPTION: The work of this section consists of submittal requirements before and during construction.
1-2 RELATED REQUIREMENTS: Closeout submittals – 01700.
1-3 REQUIRED SUBMITTALS:
A. No on-site work may occur before the COR approves all submittals.
B. All submittals become the property of the Government.
C. Contractor must submit the following to COR at least seven calendar days before the pre-construction meeting.
1. List of proposed subcontractors.
2. List of proposed products showing manufacturers’ recommendations.
3. Initial Progress Schedule (see construction project schedule below).
4. Accident Prevention Plan.
5. Waste Management Plan.
6. Before beginning work, report to Contracting Officer if any specification require-ments conflict with product manufacturer's warranty requirements.
D. Construction Project Schedule Development and Updates
1. General: The schedule shall include important milestones for achieving completion of the project and shall be in Adobe PDF file. The project schedule shall include sub-mission dates, mock-ups and review periods, through the period of performance.
Fully develop the anticipated schedule and submit to the Contracting Officer within 10 days of the Preconstruction meeting.
2. Purpose: The purpose of the project schedule is to ensure coordination, scheduling, and adjustments to scheduling during the period of performance. The project schedule will assist the Contractor and the Contracting Officer in monitoring the progress of the work, evaluating proposed changes, and processing the Contractor’s monthly pro-gress payment requests
3. Schedule Development: The project schedule shall cover the entire contract period including showing work at the visitor center over time. In developing the project schedule, the Contractor shall be responsible for ensuring that subcontractor work at all tiers, as well as its own work, is included in the project schedule.
4. The project schedule shall show the sequence and interdependence of activities re-quired for complete performance of the work. Proposed durations assigned to each activity shall be the Contractor's best estimate of time required to complete the activ-ity.
5. Seasonal weather conditions shall be considered and included as best as possible in planning and scheduling the work. The project work is expected to progress in a logi-cal manner; preparation and painting work should progress by building in accordance with the scope of work and agreed upon schedule.
6. At the end of any period of work, or if awaiting proper climatic conditions, the build-ing shall be either finished or covered and protected from the elements.
7. Project Schedule Updates: The Contractor shall update the project schedule monthly, coordinating with the COR for adjustments and local logistics/access.
8. Time Extensions: Weather delays shall not automatically mean that an extension of the contract time is warranted or due the Contractor. For time extension considera-tions, the Contractor and COR shall document conditions and causes, and the CO will determine the extent of equitable time adjustments if necessary. Refer to Section F of the contract clauses.
SECTION 013523
SAFETY REQUIREMENTS
1-1 DESCRIPTION: The work of this section consists of establishing an effective accident prevention program and providing a safe environment for all personnel and visitors.
1-2 REQUIRED SUBMITTALS
Accident Prevention Plan: Before the pre-construction conference, the Contractor must submit for approval of the Contracting Officer a written safety plan demonstrating com-pliance with all applicable federal and state safety regulations.
PART 2: PRODUCTS
2-1 ACCIDENT PREVENTION PLAN
The Plan shall be written to comply with OSHA and project requirements (a generic plan is not acceptable).
2-2 FIRST AID FACILITIES
Provide adequate facilities for the number of employees and the hazards associated with the types of ongoing construction work at the site.
2-3 PERSONNEL PROTECTIVE EQUIPMENT
Meet requirements of applicable ANSI standards.
PART 3: EXECUTION
3-1 The Contractor must comply with all OSHA federal regulations (29 CFR 1910) and
Washington state regulations governing the safety of workers performing the type of work described in this contract.
SECTION 015300
BARRIERS
1-1 DESCRIPTION: The work of this section consists of furnishing, installing, and main-taining barriers to protect existing facilities and the public from construction operations.
PART 2: PRODUCTS
2-1 GENERAL: Material may be new or used, but shall be suitable for intended purpose.
Fences and barriers shall be structurally adequate and neat in appearance.
2-2 BARRICADES AND SIGNS: ANSI D6. 1-78, “Manual if Uniform Traffic Control De-vice: (MUTCD), Part VI.
2-3 LUMBER: Free of nails, large knot holes, and splinters.
2-4 BARRIER TAPE: Banner Guard, imprinted with “CAUTION: CONSTRUCTION
AREA,” manufactured by Reef Industries, Inc., Houston, Texas, or approved equal.
3-1 PROTECTION OF PUBLIC:
A. Fence, barricade, or otherwise block off the immediate work area to prevent unauthor-ized entry to the work area.
B. Erect, and maintain barricades, lights, danger signals, and warning signs in accordance the ANSI D6. 1-78.
C. Cover pipes, hoses, and power lines crossing sidewalks and walkways with troughs using beveled edge boards.
3-2 BARRIER TAPE: Install where directed by COR.
3-3 REMOVAL: Completely remove barriers no longer needed and when approved by COR.
SECTION 015100
TEMPORARY SERVICES
PART 1: GENERAL
1-1 DESCRIPTION: The work in this section consists of providing temporary services for
Contractor’s performance of the work of this Contract.
PART 2: PRODUCTS
2-1 GENERAL: Temporary material may be new or used, but must be adequate in capacity for the usage, must not create unsafe conditions, and must not violate requirements of ap-plicable codes and standards.
2-2 SANITARY FACILITIES: Contractor shall furnish adequate portable toilet.
2-3 FIRE PROTECTION EQUIPMENT: UL Class2A, 2-1/2 gallon water type, stored-pres-sure extinguisher and UL Class 10, Type I, 15-pound B:C carbon dioxide extinguisher.
3-1 ELECTRICAL AND TELEPHONE:
A. NPS will provide electrical service via 20-amp duplex outlet at building included in this contract, as designated by the COR. The Contractor must use distribution materials pro-vided at Contractor’s expense and installed/removed in a professional and safe manner.
The Contractor and employees are expected to conserve energy.
B. Telephone: A public telephone is available at this site. Cellular service varies.
3-2 WATER: Potable water is available at the Visitor Center May through October; after 31
October water is non-potable until 1 May 2018.
3-3 SANITARY FACILITIES: Contractor shall locate portable toilet in an area near each work site acceptable to the COR.
3-4 FIRE PREVENTION AND PROTECTION:
A. Hazard Control: The contractor must take all necessary precautions to prevent fire during construction. The Contractor must provide all equipment and procedures for fire protec-tion on site. The Contractor must assign a capable and qualified person on site in charge of fire protection at all times. The responsibilities include locating and maintaining fire protective equipment and establishing and maintaining safe working procedures.
B. Smoking: No smoking allowed inside federal buildings or within 25 feet of windows or doors.
SECTION 015700
TEMPORARY CONTROLS
1-1 DESCRIPTION: The work in this section consists of providing temporary controls.
PART 2: PRODUCTS – Not used.
3-1 HOUSEKEEPING:
A. Keep project neat, orderly, and in a safe condition at all times.
B. Provide enough refuse containers for collecting construction materials and other con-struction debris.
C. Wet-down dry material and rubbish to prevent blowing dust.
D. Keep volatile wastes in covered containers.
3-2 DISPOSAL:
A. Waste Management: Unless otherwise specified, all salvaged materials become property of the Contractor and shall be separated and recycled outside of the park.
B. Immediately remove hazardous rubbish from project site. Strictly adhere to all hazmat management, collection, storage, disposal and documentation requirements. Place other construction debris in refuse containers at least daily. Dispose of refuse at least weekly, in a legal manner, at public or private dumping area outside the park.
SECTION 017000
PROJECT CLOSEOUT
1-1 DESCRIPTION: The work in this section consists of final cleanup, closeout submittals, and final inspection procedures.
PART 2: PRODUCTS
2-1 CLEANING MATERIALS: As recommended by the manufacturer of surface to be cleaned.
PART 3: EXECUTION
3-1 CLEANING: Remove all tools, equipment, surplus materials, and rubbish. Restore or refinish surfaces of existing facilities that are marred, scratched, or damaged due to the work of this contract to match original condition. Remove paint chips, grease, dirt, stains, foreign mate-rials, and labels from interior and exterior finished surfaces. Sweep paved areas; rake grounds.
At time of final inspection, project shall be thoroughly clean and ready for use.
3-2 CLOSEOUT SUBMITTALS: Submit before final inspection request.
A. Guarantees: As specified in individual sections.
B. Spare Materials: As specified in individual sections.
3-3 SUBSTANTIAL COMPLETION AND FINAL INSPECTION: Submit written certifica-tion that project, or designated portion of project, is substantially complete, and request in writ-ing, a final inspection. Contracting Officer will make an inspection within 10 days of receipt of request.
A. When Contracting Officer determines that the work is substantially complete, they will prepare a list of deficiencies that need to be corrected before final acceptance and issue a Letter of Substantial Completion.
B. If Contracting Officer determines that the work is not substantially complete, they will immediately notify Contractor in writing, stating reasons. After completing work, Con-tractor shall resubmit certification and request a new final inspection.
3-4 ACCEPTANCE OF WORK: After all deficiencies have been corrected, a Letter of Ac-ceptance will be issued.
3-5 POST-CONSTRUCTION INSPECTION: Before expiration of warranty period, Con-tracting Officer will inspect project and notify Contractor in writing of all deficiencies.
SECTION 017419
WASTE MANAGEMENT
PART 1 - GENERAL
1.1 SUMMARY
This Section includes administrative and procedural requirements for the following:
Salvaging nonhazardous demolition waste.
Recycling nonhazardous construction waste.
Disposing of nonhazardous demolition and construction waste.
DEFINITIONS
Construction Waste: Building and site improvement materials and other solid waste resulting from construction, remodeling, renovation, or repair operations. Construction waste includes packaging.
Demolition Waste: Building and site improvement materials resulting from demolition or selective demolition operations.
Solid Waste: Garbage, debris, sludge, or other discharged material (except hazardous waste) including solid, liquid, semisolid, or contained gaseous materials resulting from domestic, industrial, commercial, mining, or agricultural operations.
Debris: Non-hazardous solid waste generated during the construction, demolition, or renovation of a structure which exceeds 2.5 inch (60 mm) particle size that is: a manufactured object; plant or animal matter; or natural geologic material (e.g. cobbles and boulders). A mixture of debris and other material such as soil or sludge is also subject to regulation as debris if the mixture is comprised primarily of debris by volume, based on visual inspection.
Disposal: Removal off-site of demolition and construction waste and subsequent sale, recycling, reuse, or deposit in landfill or incinerator acceptable to authorities having jurisdiction.
Environmental Pollution and Damage: The presence of chemical, physical, or biological elements or agents which adversely affect human health or welfare; unfavorably alter ecological balances; or degrade the utility of the environment for aesthetic, cultural, or historical purposes.
Garbage: Refuse and scraps resulting from preparation, cooking, dispensing, and consumption of food.
Hazardous Materials: Any material that is regulated as a hazardous material in accordance with 49 CFR 173, requires a Material Safety Data Sheet (MSDS) in accordance with 29 CFR 1910.1200, or which during end use, treatment, handling, storage, transportation or disposal meets or has components which meet or have the potential to meet the definition of a Hazardous Waste in accordance with 40 CFR 261.
Recycle: Recovery of demolition or construction waste for subsequent processing in preparation for reuse.
Salvage: Recovery of demolition or construction waste for reuse in another facility.
PERFORMANCE REQUIREMENTS
General: Project shall minimize creation of construction, deconstruction, and demolition waste to protect and restore natural resources. Factors that contribute to waste such as over packaging, improper storage, ordering error, poor planning, breakage, mishandling, and contamination shall be minimized. A Waste Management Plan shall be developed to ensure that existing site and building materials are reused, salvaged, or recycled. Waste disposal in landfills shall be minimized.
Salvage /Recycle Requirements: Develop waste management plan that results in end-of- Project rates for salvage/recycling of 75 percent by weight of total waste generated by the Work. The following waste categories, at a minimum, shall be diverted from a landfill:
Clean dimensional wood, palettes Plywood, OSB, and particle board Cardboard, paper, packaging, newsprint Metals (from banding, stud trim, piping, rebar, roofing, other trim, steel, iron, galvanized sheet steel, stainless steel, aluminum, copper, zinc, lead, brass, and bronze)
Gypsum drywall—unpainted Non-hazardous paint and paint cans Beverage containers: Aluminum, glass, and plastic containers Insulation Wiring Other mixed construction and demolition waste as appropriate
If any waste materials encountered during the deconstruction/demolition or construction phase are found to contain lead, asbestos, PCBs, (such as fluorescent lamp ballasts), or other harmful substances, they are to be handled and removed in accordance with local, state, and federal laws and requirements concerning hazardous waste.
Existing items and material to be removed during the deconstruction/demolition phase shall be reused in the construction phase of the Project. Items that cannot be reused shall be salvaged or recycled. Items considered for reuse must be in refurbishable condition and must meet the quality standards set forth in these specifications. Contractor shall ensure that the quality of the item(s) in question will meet or exceed accepted industry or trade standards for first quality commercial grade application. During construction, deconstruction, or demolition the Contracting Officer may designate other objects or materials for reuse.
Salvage/Recycle Requirements: Government goal is to salvage and recycle as much nonhazardous demolition and construction waste as possible specifically including the following materials:
Temporary R-19 fiberglass batt insulation (to be placed in attic space over existing insulation without blocking ventilation openings) Temporary 1/2” plywood window opening closures (to be provided to the Government for reuse upon project completion)
SUBMITTALS
Waste Management Plan: After award of contract and prior to the scheduled Pre- Construction Conference, Contractor shall submit a draft Waste Management Plan to the Contracting Officer for approval. Submit electronic copies of plan. Revise and resubmit Plan as required by the Contracting Officer. Approval of Contractor’s Plan will not relieve Contractor of responsibility for compliance with applicable environmental regulations.
Progress Documentation: Supplemental to the Waste Management Plan, document solid waste disposal, diversion, and cost/revenue analysis and submit completed worksheet on a monthly basis.
Recycling and Processing Facility Records: Indicate receipt and acceptance of recyclable waste by recycling and processing facilities licensed to accept them. Include manifests, weight tickets, receipts, and invoices.
Landfill and Incinerator Disposal Records: Indicate receipt and acceptance of waste by landfills and incinerator facilities licensed to accept them. Include manifests, weight tickets, receipts, and invoices.
Qualification Data: For Waste Management Coordinator.
Progress payment requirements:
With each Application for payment, submit updated Project Waste Management Plan worksheet for solid waste disposal and diversion.
With each Application for Payment, submit manifests, weight tickets, receipts, and invoices specifically identifying the Project and waste material.
Closeout Submittals
With Closeout Submittals, submit a summary of the Project Waste Management Plan worksheet for solid waste disposal and diversion.
QUALITY ASSURANCE
Regulatory Requirements: Comply with hauling and disposal regulations of authorities having jurisdiction.
Waste Management Meeting: Conduct separate meeting or cover in the Pre-Construction Conference and comply with requirements in Division 01 Section "Project Management and Coordination." Review methods and procedures related to waste management including, but not limited to, the following:
Review and discuss waste management plan including responsibilities of Waste Management Coordinator.
Review requirements for documenting quantities of each type of waste and its disposition.
Review and finalize procedures for materials separation and verify availability of containers and bins needed to avoid delays.
Review procedures for periodic waste collection and transportation to recycling and disposal facilities.
Review waste management requirements for each trade.
PRODUCTS
1.1 WASTE MANAGEMENT PLAN
General: Develop plan consisting of waste identification and waste reduction work plan.
Indicate quantities by weight or volume, but use same units of measure throughout waste management plan.
Waste Identification: Indicate anticipated types and quantities of demolition and construction waste generated by the Work. Include estimated quantities and assumptions for estimates.
Waste Reduction Work Plan: List each type of waste and whether it will be salvaged, recycled, or disposed of in landfill or incinerator. Include points of waste generation, total quantity of each type of waste, quantity for each means of recovery, and handling and transportation procedures.
Salvaged Materials for Reuse: For materials that will be salvaged and reused in this Project, describe methods for preparing salvaged materials before incorporation into the Work.
Recycled Materials: Include list of local receivers and processors and type of recycled materials each will accept. Include names, addresses, and telephone numbers.
Disposed Materials: Indicate how and where materials will be disposed of. Include name, address, and telephone number of each landfill and incinerator facility.
Handling and Transportation Procedures: Include method used for separating recyclable waste including sizes of containers, container labeling, and designated location on Project site where materials separation will be located.
EXECUTION
1.1 PLAN IMPLEMENTATION
General: Implement waste management plan as approved by the Contracting Officer. Provide handling, containers, storage, signage, transportation, and other items as required to implement waste management plan during the entire duration of the Contract.
Waste Management Coordinator: Engage a waste management coordinator responsible for implementing, monitoring, and reporting status of waste management work plan.
Contractor shall establish contacts with local recycling and reuse companies to set up lines of responsibility. Contractor shall be responsible for coordination in terms of identifying materials, pickup schedules, and standard quality for recycled materials.
Training: Train workers, subcontractors, and suppliers on proper waste management procedures, as appropriate for the Work occurring at Project site.
Distribute waste management plan to everyone concerned within three days of submittal return.
Distribute waste management plan to entities when they first begin work on-site.
Review plan procedures and locations established for salvage, recycling, and disposal.
Site Access and Temporary Controls: Conduct waste management operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.
Separation facilities:
Contractor shall designate and Contracting Officer shall approve a specific area or areas to facilitate separation of materials for potential reuse, salvage, recycling, and return.
Waste and recycling bins are to be placed near each other, and close to the point of waste generation but out of the traffic pattern.
Recycling and waste bin areas are to be kept neat and clean and clearly marked in order to avoid co-mingling of materials.
Bins shall be protected during non-working hours from off-site contamination.
Garbage dumpsters should be checked periodically to monitor recyclables being thrown away or if there are undocumented materials that could be recycled.
Materials handling procedures: Materials to be recycled shall be protected from contamination and shall be handled, stored, and transported in a manner that meets the requirements set by the designated facilities for acceptance. Establish a defined area for the operations of each trade, especially woodcutting so that off-cuts will be kept in one area and can be sorted by dimension for future reuse.
SALVAGING DEMOLITION WASTE
Salvaged Items for Reuse in the Work:
Clean salvaged items.
Pack or crate items after cleaning. Identify contents of containers.
Store items in a secure area until installation.
Protect items from damage during transport and storage.
Install salvaged items to comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make items functional for use indicated.
Salvaged Items for Sale and Donation: Not permitted on Project site.
Salvaged Items for Governments Use:
Clean salvaged items.
Pack or crate items after cleaning. Identify contents of containers.
Allow for inspection if necessary.
Store items in a secure area until delivery to Government.
Transport items to storage area on-site designated by Government.
Protect items from damage during transport and storage.
RECYCLING CONSTRUCTION WASTE, GENERAL
General: Recycle paper and beverage containers used by on-site workers.
Recycling Receivers and Processors: List below is provided for information only; available recycling receivers and processors include, but are not limited to, the following:
Skagit River Steel & Recycling 1265 S Anacortes St · Burlington · 360-757-6096 · skagitriversteel.com
Procedures: Separate recyclable waste from other waste materials, trash, and debris. Separate recyclable waste by type at Project site to the maximum extent practical.
Provide appropriately marked containers or bins for controlling recyclable waste until they are removed from Project site. Include list of acceptable and unacceptable materials at each container and bin. Inspect containers and bins for contamination and remove contaminated materials if found.
Stockpile processed materials on-site without intermixing with other materials. Place, grade, and shape stockpiles to drain surface water. Cover to prevent windblown dust.
Stockpile materials away from construction area. Do not store within drip line of trees.
Store components off the ground and protect from the weather.
Remove recyclable waste off Governments property and transport to recycling receiver or processor.
RECYCLING DEMOLITION WASTE
Wood Materials: Sort and stack members according to size, type, and length. Separate lumber, engineered wood products, panel products, and treated wood materials.
Metals: Separate metals by type.
Gypsum Board: Stack large clean pieces on wood pallets and store in a dry location. Remove edge trim and sort with other metals. Remove and dispose of fasteners.
Electrical Devices: Separate switches, receptacles, switchgear, transformers, meters, panelboards, circuit breakers, and other devices by type.
Conduit: Reduce conduit to straight lengths and store by type and size.
Electronic Products: Ensure that all non-usable electronic products are reused, donated, sold, or recycled using environmentally sound management practices at end of life.
RECYCLING CONSTRUCTION WASTE
Packaging:
Cardboard and Boxes: Break down packaging into flat sheets. Bundle and store in a dry location.
Polystyrene Packaging: Separate and bag materials.
Pallets: As much as possible, require deliveries using pallets to remove pallets from
Project site. For pallets that remain on-site, break down pallets into component wood pieces and comply with requirements for recycling wood.
Crates: Break down crates into component wood pieces and comply with requirements for recycling wood.
Wood Materials:
Clean Cut-Offs of Lumber:
Clean Sawdust: Bag sawdust that does not contain painted or treated wood.
Gypsum Board: Stack large clean pieces on wood pallets and store in a dry location.
Clean Gypsum Board: Grind scraps of clean gypsum board using small mobile chipper or hammer mill. Screen out paper after grinding.
DISPOSAL OF WASTE
General: Except for items or materials to be salvaged, recycled, or otherwise reused, remove waste materials from Project site and legally dispose of them in a landfill or incinerator acceptable to authorities having jurisdiction.
Except as otherwise specified, do not allow waste materials that are to be disposed of accumulate on-site.
Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.
Burning: Do not burn waste materials.
Disposal: Transport waste materials off Governments property and legally dispose of them.
https://www.skagitcounty.net/departments/publicworkssolidwaste/cdl.htm
END OF SECTION
SECTION 018000 TECHNICAL SPECIFICATIONS
INSULATING GLASS WINDOWS
1.1 SUMMARY:
A. Furnishing and installing insulated, tempered glass.
B. Glazing compounds and accessories.
1.2 REFERENCES:
A. American National Standards Institute, Inc.:
ANSI Z97.1-84 Safety Glazing Material Used in Buildings – Safety Performance Specifications and Methods of Test
B. Architectural Aluminum Manufactures Association:
AAMA SG-1-76 Dense Rubber – like Compression Gasket Materials
C. Code of Federal Regulations:
16 CFR Part 1201 Safety Standard for Architectural Glazing Materials
D. Glass Association of North America:
GANA – 1992 Fabrication, Erection & Glazing Hours Manual GANA – 1990 Sealant Manual
E. Insulating Glass Manufacturers Alliance:
IGMA 70-7-1 Glazing Recommendations for ‘Sealed Insulating Glass Units
1.3 PERFORMANCE REQUIREMENTS
A. Provide glass and glazing materials for continuity of building enclosure vapor re-tarder and air barrier:
1. In conjunction with vapor retarder and joint sealer materials described in other sections.
2. To utilize the inner pane of multiple pane sealed units for the continuity of the air barrier and vapor retarder seal.
3. To maintain a continuous air barrier and vapor retarder throughout the glazed as-sembly from glass pane to heel bead of glazing sealant.
B. Select type and thickness of exterior glass to withstand dead loads and wind loads acting normal to plane of glass at design pressures calculated in accordance with State Structural Specialty code.
1. Use the procedure specified in ASTM E 1300 to determine glass type and thick-ness.
2. Limit glass deflection to 1/200 or flexure limit of glass, whichever is less, with full recovery of glazing materials.
3. Thicknesses listed are minimum.
C. Passes positive pressure test standards UBC 7-2 and UBC 7-4.
1.4 SUBMITTALS:
A. General: Submittals shall be according to Section 013300.
B. Manufacturer’s Literature: Submit PDF files of the manufacturer’s descriptive data for insulated, tempered glass units to be used on this project. Provide structural, physical and environmental characteristics, size limitations, and special handling or installation requirements.
C. Installation Instructions: Submit PDF files of manufacturer’s installation instructions for the insulating glass to be used on this project.
D. Samples: Provide samples of sealed insulated glass panel for each window replacement location to ensure that the replacement window color tint/shade installed matches the existing adjacent windows. Obtain COR approval of samples prior to installation.
1.5 QUALITY CONTROL:
A. Perform Work in accordance with GANA Glazing Manual and FGMA Sealant Manual for glazing installation methods.
B. Installer Qualifications: Company specializing in performing the work of this section with minimum three years documented experience.
C. Failure Criteria: Not limited to the following:
1. Glass Cracking, Scratching or breakage.
2. Visible vapor or moisture forming on inner surfaces.
3. Inadequate or defective window sealing/setting.
4. Incorrect window tint, color, or shade.
1.6 DELIVERY, STORAGE, AND HANDLING:
A. Delivery: Schedule glass delivery to coincide with installation schedules.
B. Storage: Store glass and setting materials in safe, dry locations and do not unpack until needed for installation. Handle and install materials in a manner that will protect them from damage.
1.7 PROTECTION/SITE CONDITIONS:
A. Employees may be present Monday through Thursday from 7:00 AM to 5:30 PM.
B. Protection of building exterior, interior contents and finishes:
1. The interior of the building shall be protected from exterior environment elements during the work process. If the replacement window cannot be installed by the close of the workday, adequate protection shall be placed over the opening to protect the building’s interior finishes and contents from any weather event. Any damage caused by the contractor, contractor’s forces, tools and mechanical equipment shall be re-paired or replaced to at least its prior existing conditions.
2. The exterior of the building, landscaped areas including plants and planting beds, irri-gation materials, lighting, sidewalks, signage, curbs and parking surfaces shall be pro-tected from all Contractor’s processes during the move-in, contracted work and close-out. Any damage caused by the contractor, contractor’s forces, tools and mechanical equipment shall be repaired or replaced to at least its prior existing conditions.
C. Do not install glazing when ambient temperature is less than 50 degrees F.
D. Maintain minimum ambient temperature before, during and 24 hours after installation of glazing compounds.
PART 2: PRODUCTS
2.1 MATERIALS:
A. Safety Insulating Glass: Windows shall be formed of two pieces of tempered, ¼ inch thick, clear glass separated by a ½ inch-thick dehydrated air space, hermetically sealed, each pane bearing a permanent label. Windows shall conform to 16 CFR Part 1201.
B. Sealed Insulated Glass Materials:
a. Insulated Glass Units (Type I-1): Double pane with glass to elastomer edge seal.
1. Outer pane of float type, annealed, bronze color, inner pane of clear Low-E glass.
2. Use fully tempered panes where required by code for impact safety.
3. Place low E coating on 2 surface within the unit.
4. Durability: Certified by an independent testing agency to comply with ASTM E 2190.
5. Comply with ASTM E 774 and E 773, Class CBA.
6. Purge interpane space with dry hermetic air.
7. Total unit thickness of 1 inch minimum.
The replacement Insulated glass units shall match adjacent windows in terms of tint/shade. The contractor shall provide samples for COR approval to ensure color match and to confirm the following characteristics:
8. Visible light transmittance: 44 percent.
9. Total solar energy transmittance: 33 percent.
10. Summer U-value: 0.35
11. Winter U-value: 0.35
12. Solar heat gain coefficient: 0.46
13. Shading coefficient: 0.53
C. Setting Materials: Shall be the types required for the applicable setting method specified in the GANA Sealant Manual, unless specified otherwise. Do not use metals sash putty, nonskinning compounds, non-resilient preformed sealers or impregnated preformed gas-kets. Materials must be completely clean and dry. Check sealant manufacturer’s recom-mendations for proper cleaning procedures.
1. Setting Blocks: Neoprene, 80 to 90 Shore A durometer hardness, ASTM C 864
Option I. Length of 0.1 inch for each square foot of glazing or minimum 4 inch x width of glazing rabbet space minus 1/16 inch x height to suit glazing method and pane weight and area.
2. Spacer Shims: Neoprene, 50 to 60 Shore A durometer hardness, ASTM C 864 Option I. Minimum 3 inch long x one half the height of the glazing stop x thick-ness to suit application, self-adhesive on one face.
3. Glazing Tape: Preformed butyl compound with integral resilient tube spacing de-vice; 10 to 15 Shore A durometer hardness; coiled on release paper; size; black color.
4. Glazing Tape: Closed cell polyvinyl chloride foam, coiled on release paper over adhesive on two sides, maximum water absorption by volume of 2 percent, de-signed for compression of 25 percent to effect an air barrier and vapor retarder seal.
5. Glazing Gaskets: Resilient silicone extruded shape to suit glazing channel retain-ing slot; ASTM C 864 Option I; bronze color.
3.1 EXAMINATION:
A. Verify that openings for glazing are correctly sized and within tolerance.
B. Verify that surfaces of glazing channels or recesses are clean, free of obstructions that may impede moisture movement, weeps are clear, and ready to receive glazing.
3.2 PREPARATION:
A. Clean contact surfaces with solvent and wipe dry.
B. Prime surfaces scheduled to receive sealant.
C. Install sealants in accordance with ASTM C 1193 and FGMA Sealant Manual.
D. Install sealant in accordance with manufacturer's instructions.
3.3 INSTALLATION - EXTERIOR/INTERIOR DRY METHOD (GASKET GLAZING)
A. Place setting blocks at 1/4 points with edge block no more than 6 inches from corners.
B. Rest glazing on setting blocks and push against fixed stop with sufficient pressure on gas-ket to attain full contact.
C. Install removable stops without displacing glazing gasket; exert pressure for full continu-ous contact.
3.4 INSTALLATION - EXTERIOR WET METHOD (SEALANT AND SEALANT)
A. Place setting blocks at 1/4 points and install glazing pane or unit.
B. Install removable stops with glazing centered in space by inserting spacer shims both sides at 24 inch intervals, 1/4 inch below sight line.
C. Fill gaps between glazing and stops with Type 4 sealant to depth of bite on glazing, but not more than 3/8 inch below sight line to ensure full contact with glazing and continue the air and vapor seal.
D. Apply sealant to uniform line, flush with sight line. Tool or wipe sealant surface smooth.
3.5 INSTALLATION - INTERIOR DRY METHOD (TAPE AND TAPE)
A. Cut glazing tape to length and set against permanent stops, projecting 1/16 inch (1.6
mm) above sight line.
B. Place setting blocks at 1/4 points with edge block no more than 6 inches from corners.
C. Rest glazing on setting blocks and push against tape for full contact at perimeter of pane or unit.
D. Place glazing tape on free perimeter of glazing in same manner described above.
E. Install removable stop without displacement of tape. Exert pressure on tape for full con-tinuous contact.
F. Knife trim protruding tape.
3.6 CLEANING
A. Remove glazing materials from finish surfaces.
B. Remove labels after Work is complete.
C. Clean glass and adjacent surfaces.
3.7 PROTECTION OF FINISHED WORK
After installation, mark pane with an 'X' by using removable plastic tape or paste; do not mark heat absorbing or reflective glass units.
ALUMINUM ENTRANCES
1.1 SUMMARY
A. Section Includes: Exterior-swinging entrance doors.
1.2 ACTION SUBMITTALS
A. Product Data: For each type of product indicated.
B. Samples: For each type of exposed finish required.
1.3 OTHER ACTION SUBMITTALS:
A. Entrance Door Hardware Schedule: Prepared by or under the supervision of supplier, detailing fabrication and assembly of entrance door hardware, as well as procedures and diagrams. Note any conflicts in door hardware schedule to be resolved.
1.4 INFORMATIONAL SUBMITTALS
A. Warranties: Sample of special warranties.
1.5 CLOSEOUT SUBMITTALS
A. Maintenance data.
1.6 QUALITY ASSURANCE
A. Product Options: Information on Drawings and in Specifications establishes require-ments for systems' aesthetic effects and performance characteristics. Aesthetic effects are indicated by dimensions, arrangements, alignment, and profiles of components and assemblies as they relate to sightlines, to one another, and to adjoining con-struction. Performance characteristics are indicated by criteria subject to verification by one or more methods including preconstruction testing, field testing, and in-service performance.
B. Accessible Entrances: Comply with applicable provisions in the U.S. Architectural & Transportation Barriers Compliance Board's ADA-ABA Accessibility Guidelines.
1.7 WARRANTY
A. Special Warranty: Manufacturer's standard form in which manufacturer agrees to repair or replace components of aluminum-framed systems that do not comply with requirements or that fail in materials or workmanship within specified warranty period.
1. Warranty Period: The Contractor shall provide a written one (1) year warranty for all general work and workmanship, as well as manufacturer’s written war-ranty.
B. Special Finish Warranty: Manufacturer's standard form in which manufacturer agrees to repair or replace components on which finishes do not comply with requirements or that fail in materials or workmanship within specified warranty period. Warranty does not include normal weathering.
1. Warranty Period: The Contractor shall provide a written one (1) year warranty
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:
B. Basis-of-Design Product: Subject to compliance with requirements, provide custom size, Kawneer 360 Insulclad or comparable product by one of the following:
1. Arcadia, Inc.
2. CMI Architectural.
3. Commercial Architectural Products, Inc.
4. EFCO Corporation.
5. TRACO.
6. Tubelite.
7. United States Aluminum.
8. Vistawall Architectural Products; The Vistawall Group; a Bluescope Steel com-pany.
2.2 MATERIALS
A. Aluminum: Alloy and temper recommended by manufacturer for type of use and finish indicated.
1. Sheet and Plate: ASTM B 209.
2. Extruded Bars, Rods, Profiles, and Tubes: ASTM B 221.
3. Extruded Structural Pipe and Tubes: ASTM B 429.
4. Structural Profiles: ASTM B 308/B 308M.
5. Welding Rods and Bare Electrodes: AWS A5.10/A5.10M.
2.3 GLAZING SYSTEMS
A. Glazing: As specified in Division 08 Section "Glazing."
B. Glazing Gaskets: Manufacturer's standard compression types; replaceable, molded or extruded, of profile and hardness required to maintain watertight seal.
C. Spacers and Setting Blocks: Manufacturer's standard elastomeric type.
2.4 ENTRANCE DOOR
A. Entrance Doors: Manufacturer's standard glazed entrance doors for manual-swing op-eration.
1. Door Construction: 1-3/4-inch overall thickness, with minimum 0.125-inch-thick, extruded-aluminum tubular rail and stile members. Mechanically fasten corners with reinforcing brackets that are deeply penetrated and fillet welded or that incorporate concealed tie rods.
a. Thermal Construction: High-performance plastic connectors separate alu-minum members exposed to the exterior from members exposed to the in-terior.
2. Door Design: As indicated medium stile; 4-1/16-inch nominal width.
a. Accessible Doors: Smooth surfaced for width of door in area within 10 inches above floor or ground plane.
3. Glazing Stops and Gaskets: Beveled, snap-on, extruded-aluminum stops and preformed gaskets.
a. Provide non-removable glazing stops on outside of door.
B. Entrance Door Hardware: As specified in Division 08 Section "Door Hardware."
2.5 ENTRANCE DOOR HARDWARE
A. General: General Guidance is here, but more detailed information is included in Spec Section 087100 and 087113. Provide entrance door hardware and entrance door hard-ware sets indicated in door and frame schedule for each entrance door to comply with requirements in this Section.
1. Entrance Door Hardware Sets: Provide quantity, item, size, finish or color indi-cated, and products equivalent in function and comparable in quality to named products.
2. Sequence of Operation: Provide electrified door hardware function, sequence of operation, and interface with other building control systems indicated.
3. Opening-Force Requirements:
a. Egress Doors: Not more than 15 lbf to release the latch and not more than 30…