B08_Section_B_Price_Schedule.docx

DOCX document 26 KB Posted

Attached to
BIHO - REPLACE WINDOWS UNIT #5 Federal contract opportunity
Solicitation number
140P8318Q0123
Issued by
Department of the Interior National Park Service

About this file

Section B

View the file

Other files for this federal contract opportunity

Other files attached to BIHO - REPLACE WINDOWS UNIT #5, newest first.
File Type Posted
B09_Amendment_WINDOW_SCHEDULE.docx DOCX document
5c.zip ZIP file
5a.zip ZIP file
Sol_140P8318Q0123_Amd_0001.pdf PDF
5b.zip ZIP file
B09_Amendment_Drawings_Windows_BIHO_341_3009C_emp_apartment.pdf PDF
B09_SF-30_Amendment_140P8318Q0123.pdf PDF
5d.zip ZIP file
B09_Amendment_to_Solicitation_140P8318@0123.docx DOCX document
B09_SOW_Amendment_BIHO_146594_Spec_04042017.docx DOCX document
B08_SF-25A_PAYMENT_BOND_FORM.pdf PDF
B08_Section_C-M_Terms_and_Conditions_9-12-2018.docx DOCX document
B08_Attachment_1_READ_ME_FIRST.docx DOCX document
B08_Wage_Detrmination_MT180026_Beaverhead_County,Montana.pdf PDF
B08_SOW_Replace_Windows.doc DOC document
B08_SF-1442_RFQ_140P8318Q0123.pdf PDF
Sol_140P8318Q0123.pdf PDF
B08_Experience_and_Past_Performance.docx DOCX document
B08_NPS_CM-16_Transmittal_Form_Use_for_Contract_Submittals.docx DOCX document
Show all 19

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation 140P8318Q0123 – Attachment 1, READ ME FIRST Replace Windows in Quad-Plex Housing Unit 5 A,B,C,D - BIHO

SECTION B - SUPPLIES OR SERVICES AND PRICES

CONTRACT PRICE SCHEDULE

All work shall be performed in accordance with contract specifications.

This document serves as a general template. The contractor shall factor the lump sum price to include all labor, tools, equipment, materials, mobilization-in, mobilization-out, payment bond, overhead and profit (applicable to prime contractor subcontractor) necessary for completing all work. All work shall be performed in accordance with these terms and conditions, including the attached Specifications, Plans (drawings), and Davis-Bacon Act wage rates. In accordance with FAR 36.204, the estimated magnitude of this construction project is between $25,000.00 and $100,000.00.

The Offeror shall submit a price for all line items below. Failure to do so may render the quote non-responsive. The Government anticipates being able to evaluate solely based upon lump sum prices quoted for each line item. However, the Government reserves the right to request breakdowns of any quoted lump sum prices, such as mobilization in and out, materials, labor, bonding, overhead, or profit. On lump sum line items, provide total price only. If no line item exists for a portion of the work, include the cost in a relative line item. In case of error in summation, the total of the corrected line item amount governs. Round totals and extended prices to the nearest whole dollar (no cents).

NPS has limited funds to perform this project. In addition to providing a proposal that complies with the plans and specifications and Section B, Price Schedule, offerors are encouraged to submit alternative priced proposals that achieve the Government’s overall objectives of improving energy efficiency and building functionality. All alternatives must include replacement of windows [and other components]. Each alternative should briefly yet clearly state the differences between it and the Statement of Work, as well as any general impacts the alternative would have on energy efficiency. [R factor] Include a firm fixed price for each alternative.

Language not used: Because of this, NPS recognizes a wide price range may exist based upon level of effort and quality of materials used. Contractors may submit alternate quotations proposing different level of quality and materials on a line item basis from which NPS may select their preferred choice(s) based on price and other factors as outlined in the solicitation. Alternate quotations should provide sufficient detail so as to be clear and permit a meaningful evaluation.

ITEM NO. 1: Window A This bid item consists of providing all labor, material and equipment to remove and install window A

Line ItemUnit ofUnitExtended
No.DescriptionQtyMeasurePriceTotal

Window A Total 4 each $ $ ITEM NO. 2: Window B This bid item consists of providing all labor, material and equipment to remove and install window B

Line ItemUnit ofUnitExtended
No.DescriptionQtyMeasurePriceTotal

Window B Total 18 each $ $ ITEM NO. 1: Window C This bid item consists of providing all labor, material and equipment to remove and install window C

Line ItemUnit ofUnitExtended
No.DescriptionQtyMeasurePriceTotal

Window C Total 1 each $ $ ITEM NO. 1: Window D This bid item consists of providing all labor, material and equipment to remove and install window D

Line ItemUnit ofUnitExtended
No.DescriptionQtyMeasurePriceTotal

Window D Total 12 each $ $

PROJECT TOTAL$____________________
B.2ADDITIONAL INFORMATION. Offerors submitting quotes in response to this solicitation must have an active registration in the System for Award Management (SAM) and a DUNS number. Additional information can be found at:

https://sam.gov http://www.dnb.com/get-a-duns-number.html

(a) Insert your business name:

_______________________________________________________________________ and, DUNS number: _______________________________________ and, Complete contact information (e-mail address and phone number)

(b) My business is registered in SAM yes_______ no_______ (check one);

(c) We have completed the online representations and certifications (part of SAM) yes______ no______ (check one);

(d) We are currently a small business concern* yes_________ no____________ (check one).

Name and Title

Signature

Date