This is Amendment #1 to a federal solicitation (140P8126Q0020) issued by the National Park Service (NPS) for Lake Mead wet well relining work. The amendment addresses five vendor questions with clarifications regarding project specifications and does not extend the original proposal closing date, which remains April 28, 2026. The period of performance runs from July 1, 2026 through December 28, 2026.

The amendment provides technical clarifications for three lift stations requiring wet well relining: Katherine Landing Main (105-inch diameter, 180-inch depth), Katherine Landing Back Bay (80-inch diameter, 126-inch depth), and Temple Bar (75-inch diameter, 213-inch depth). Historic maximum sewage flow rates are 15,129 gallons per day for Katherine Main, 7,000 gallons per day for Temple Bar, and 1,700 gallons per day for Katherine Landing Back Bay. Surface preparation must comply with ICRI Technical Guidelines No. 03732, with 200 mils dry film thickness per coat and additional coats applied as needed. For Temple Bar, the exact square footage of failing fiberglass liner requiring removal is unknown, but operators can visually assess the failing liner from the top hatch; no prior inspection reports are available. Contractors must provide all temporary bypass piping with the ability to tie into the force main within a 100-foot radius at all locations, as no existing tie-in points are available on the force main.

View the file

Other files

File Type Posted
Sol_140P8126Q0020_Amd_0004.pdf PDF
Sol_140P8126Q0020_Amd_0003.pdf PDF
Sol_140P8126Q0020_Amd_0002.pdf PDF
B08_ATTACHMENT_A_SOW.pdf PDF
Sol_140P8126Q0020.pdf PDF
B08_ATTACHMENT_B_SCA_Wage_Rates_NV.pdf PDF
B08_ATTACHMENT_C_SCA_Wage_Rates_AZ.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: is not is required copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7.ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

PAGESOF

Contractor

The hour and date specified for receipt of Offers to sign this document and return

Bradley Metler

See continuation page

NPS, PWR - LAKE MABO

601 Nevada Way Boulder City NV 89005-2426

PPL

140P8126Q0020

04/28/2026

04/28/2026

1 4

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

NSN 7540-01-152-8067

140P8126Q0020/0001

Amendment #1 addresses vendor questions. No extension to the closing date.

Period of Performance: 07/01/2026 to

12/28/2026

140P8126Q0020 LAKE MEAD WET WELL RELINING

AMENDMENT #1 4-29-26

Amendment #1 addresses vendor questions. Answers are in ORANGE, below.

Q1. WET WELL DIMENSIONS AND SURFACE AREA

Please provide the interior dimensions (diameter or length x width, and depth) and total surface area to be coated for each of the three wet wells (Temple Bar, Katherine Landing Main, and Katherine Landing Back Bay).

A1: KL Main LS has a diameter of 105 inches with a depth of 180 inches, Back bay dia. 80" and depth of 126", Temple Bar dia. 75", depth of 213"

Q2. SEWAGE FLOW RATES FOR BYPASS PUMPING

Can NPS provide expected average and peak sewage flow rates (gpm) for each of the three lift stations so that bypass pumping equipment can be sized appropriately?

A2: Historic flow rate maximums for Temple Bar= 7,000 gpd, Katherine Main= 15,129 gpd, KL Back bay= 1,700 gpd

Q3. TEMPLE BAR LINER REMOVAL AND SUBSTRATE CONDITION

For the Temple Bar wet well, can NPS provide the approximate square footage of failing fiberglass liner that must be removed, along with the estimated condition and depth of any spalling or structural damage to the underlying concrete substrate? Has any prior condition assessment, inspection report, or as-built drawing been completed that can be shared with offerors?

A3: Unknown, Operators can see the failing liner from the hatch on top of the wet well. No further inspection has been conducted.

Q4. SURFACE PREPARATION STANDARD AND COATING THICKNESS

What is the required minimum dry film thickness (DFT) for the protective coating, and is surface preparation specified to a particular NACE or SSPC standard (e.g., SSPC-SP 6, SSPC-SP 10) with a defined blast profile?

A4: Surface must be cleaned of all grease , oil, rust, scale and other contaminants in accordance with ICRI Technical Guidelines No. 03732. 200 mils thickness per coat, additional coats may be needed in certain instances.

140P8126Q0020 LAKE MEAD WET WELL RELINING

AMENDMENT #1 4-29-26

Q5. BYPASS ROUTING DISTANCE AND DISCHARGE TIE-IN POINTS

What is the approximate distance and elevation change for the bypass routing (Back Bay to Main at Katherine Landing, and Main lift to the sewage lagoons via force main at both sites)? Are there existing force main connection points or manholes that the contractor can tie into for bypass discharge, or must the contractor provide all temporary piping?

A5: No existing tie in points on force main. Depending on tech approach to project the distances can vary. The force main should be able to be tied in to within a 100' radius at all locations.

Amendment of solicitation/modification of contract
Contract ID code
Amendment/modification number
Effective date
Requisition/purchase requisition number
Project number
Issued by
Code
Administered by
Code
Name and address of contractor
Code
Facility code
Amendment of solicitation number
Dated
Modification of contract/order number
Dated
This item only applies to amendments of solicitations
Accounting and appropriation data
This item applies only to modifications of contracts/orders.
This change order is issued pursuant to:
The above numbered contract/order is modified to reflect the administrative changes
This supplemental agreement is entered into pursuant to authority of:
Other
Important:
Description of amendment/modification
Name and title of signer
Contractor/offeror
Date signed
Name and title of contracting officer
Signature of Contracting Officer
Date signed
Previous edition unusable
Standard form 30 (rev. 11/2016)
Continuation sheet
Reference Number
Name of Offeror or Contractor
OPTIONAL FORM 336 (4-86))

Sponsored by GSA FAR (48 CFR) 53.110

File details come from the government source that posted it. Updated .