B09_SOW_Septic_-_Vault_Pumping_(Revised_8_28_25)(amend_0001)_0001.doc

DOC document 51 KB Posted

Attached to
MOJA SEPTIC AND VAULT PUMPING 32 UNITS
Solicitation number
140P8125Q0069
Issued by

About this file

This is a Statement of Work (SOW) for septic and vault toilet pumping services at Mojave National Preserve. The contract requires removing and disposing of human waste from 32 septic and vault toilets across 7 locations within the park, with an expected annual pumping schedule. The work involves pumping toilets with capacities ranging from 500 to 4,500 gallons, located in areas such as Kelso Dunes, Hole in the Wall, Rock House, Zzyzx, and other park locations, with a 24-48 hour response time for service calls.

The contract is structured with a base year from September 17, 2025, to September 16, 2026, and four optional extension years through September 16, 2030. The contractor must have appropriate credentials to transport and dispose of human waste in San Bernardino County, California, and maintain a clean pumping vehicle to prevent introducing non-native seeds into the preserve. A water truck will be provided by the park, and the contractor is expected to fully utilize pumping truck capacity and remove any additional trash during the pumping process. The solicitation is issued by the Department of the Interior National Park Service Pacific West Region under solicitation number 140P8125Q0069.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work

Pumping of Vault Toilets at MOJA Part 1: Scope/Background/Objective

1.1 Scope of Work

Removal and disposal of human waste from 32 septic and/or vault toilets located throughout Mojave National Preserve.

1.2 Background

Due to the visitation usage of the 32 septic and/ or vaults (capacity of a vault is approximately 500- 4500 gallons), all the 7 varying locations within the park, need to be pumped on a regular basis for the health and safety of the visitors, park employees, and wildlife.

1.3 Objective

To enhance the park visitor experience, and address health and safety issues of the visitors, park employees, and wildlife.

Part 2:

Contractor Tasks & Supplies To remove the human waste and dispose of the waste properly, complying with all county, state, and federal regulations. A water truck will be provided by Mojave National Preserve, to follow the pumper truck and provide additional water as needed.

Pumping is on an “as needed” basis and the vendor will be called for service, with an expected 24-48 hour response time. Any trash is to be removed during the pumping process. It is requested to fully utilize the capacity of the pumping truck while in the park, pumping more than one vault or septic at a time, if possible. Septic and/or Vault toilets are located off both dirt and paved roads.

The approximate pumping schedule is once a year per septic/vault. If visitor usage is higher, some locations may need additional pumping.

Kelso Dunes Area: (Approximate area: 34.892493, -115.698850)

· KD vaults (approx. 1500 gallons each) There are 4 vaults in this area. Pumping will be done approximately once per year, depending on visitor use.

Hole in the Wall (HITW) Camping Area: (Approximate area: 35.047933, -115.393567)

· HITW campground vaults (approx. 1500 gallons each). There are 4 vaults in this area. Pumping will be done approximately once per year, depending on visitor use.

· Rock House vaults (approx. 1500 gallons each) There are 2 vaults in this area. Pumping will be done approximately once per year, depending on visitor use.

· OX Ranch septic (approx. 1500 gallons) one septic tank pumped approximately once per year

· Midhills campground vaults (approx. 1500 gallons each) There are 4 vaults in this area. Pumping will be done approximately once per year, depending on visitor use.

· Rocking L House septic (approx. 1500 gallons each) one septic tank pumped approximately once per year.

· Equestrian camp site group site vaults (approx. 1500 gallons each) There are 2 vaults in this area. Pumping will be done approximately once per year, depending on visitor use.

Hole in the Wall Visitor Center (VC) and Fire Center (FC):

(Approximate area: 35.047933, -115.393567)

· VC primary septic (approx. 1500 gallons) one septic tank pumped approximately once per year.

· FC primary septic (approx. 2500 gallons) one septic tank pumped approximately once per year.

· FC kitchen septic (approx. 550 gallons) one septic tank pumped approximately once per year.

· Rings Loop trail vault (approx. 1500 gallons) There is one vault in this area. Pumping will be done approximately once per year, depending on visitor use.

Kelso Area: (Approximate area: 35.011802, -115.654318)

· Kelso Dorms septic (approx. 3000 gallons) one septic tank pumped approximately once per year.

· Kelso RV septic (approx. 2000 gallons) one septic tank pumped approximately once per year.

· Schoolhouse septic (approx. 1500 gallons) one septic tank pumped approximately once per year.

· Kelso Depot VC septic (approx. 4500 gallons) one septic tank pumped approximately once per year.

Zzyzx Area: (Approximate area: 35.143646, -116.106792)

· Main building septic (approx. 1000 gallons). one septic tank pumped approximately once per year.

· Zzyzx vault (approx. 1500 gallons each) There are 2 vaults in this area. Pumping will be done approximately once per year, depending on visitor use.

Kessler springs Area: (Approximate area: 35.296110, -115.533656)

· Dorm Housing septic (approx. 1500 gallons) one septic tank pumped approximately once per year.

· Valley View housing septic (approx. 1500 gallons) one septic tank pumped approximately once per year.

Morning star area: (Approximate Area: 35.451513, -115.390368

· Tortoise Facility septic (approx. 1500 gallons) one septic tank pumped approximately once per year.

*Includes the pumping of all waste from the vault of the vault toilets and transport of the waste for offsite disposal in compliance will all applicable state and local laws and best management practices. Toilets may contain other than human waste and will also need to be removed by the contractor; Not the government’s responsibility to remove before contractor is on site.

The pumping vehicle shall be kept clean, free of vegetation, and in good mechanical condition. Please note, it is extremely important that the pumping vehicle is free of dirt and debris, which can transport non-native seeds into the Mojave National Preserve.

Option Performance Period Base Year: September 17, 2025 – September 16, 2026

Option Year 1: September 17, 2026 – September 16, 2027

Option Year 2: September 17, 2027 – September 16, 2028

Option Year 3: September 17, 2028 – September 16, 2029

Option Year 4: September 17, 2029 – September 16, 2030

CONTRACTOR PERSONNEL

The pumping and services will be performed by a contractor with the appropriate credentials and licensure to transport and dispose of human waste in San Bernardino County, California.

Contract Superintendence:

A superintendent needs to have 5 years of experience with direct superintendence similar to this scope of work (SOW). If prime contractor is self-performing the work, then daily direct onsite superintendence is not required. If the prime contractor is subcontracting the work out, the prime contractor must have a superintendent physically available to be onsite, within two (2) hours of COR call out, during every service day when they are in the park. The contractor shall submit a letter to the Contracting Officer (CO) and Contracting Officers Representative on quoter’s experience that is related to the SOW.

Part 3:

Contract End Items MOJA personnel inspect that the waste is removed from the Preserve and any spills are to be cleaned up by the contractor.

File details come from the government source that posted it. Updated .