This document is a Scope of Work (SOW) for replacing doors at various locations within Death Valley National Park. The main objectives are to remove and replace failing exterior doors on operational buildings, as well as install new interior doors in an office building. The SOW includes details on the locations, specifications for the new doors, installation requirements, contractor responsibilities, submittal procedures, quality control, safety, and project management. Key details include:
The project locations are Furnace Creek Visitor Center, Scotty's Castle Gas Tank House, water utility sites at Mesquite Spring, Stovepipe Wells, Grapevine, and Emigrant Campground, and the Hacienda at Scotty's Castle. The new exterior doors must meet Architectural Barriers Act Accessibility Standards and have automated opening, emergency exit functionality, and corrosion-resistant materials. The government will provide lock cores. There is an option to install 10 interior doors at the Hacienda. The period of performance is estimated from September 2024 to January 2025. Contractor submittals, inspections, safety requirements, and quality control procedures are also specified.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B09_Q_A_0001.pdf | ||
| Sol_140P8124Q0050_Amd_0001.pdf | ||
| Sol_140P8124Q0050.pdf | ||
| B08_ATTACHMENT_D_Area_Location_Maps.pdf | ||
| B08_ATTACHMENT_A_SOW.pdf | ||
| B08_ATTACHMENT_F_OPTION__1_Water_Building_Doors.pdf | ||
| B08_ATTACHMENT_G_OPTION__2_Hacienda_Interior_Doors.pdf | ||
| B08_ATTACHMENT_B_Inyo_County_Wage_Rates.pdf | ||
| B08_ATTACHMENT_H_Construction_Contract_Administration_Notice.pdf | ||
| B08_ATTACHMENT_C_Furnace_Creek_Visitor_Center_As_Built_2013.pdf | ||
| B08_ATTACHMENT_E_Scottys_Castle_Gas_Tank_House.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE OF WORK (Updated 7-22-24)
Replace Doors at Death Valley National Park 1
1.1 SUMMARY
A. The goal of this project is to replace failing exterior doors on several operational buildings and hang interior doors in an office building at Furnace Creek, Cow Creek, Stovepipe
Wells/Emigrant, Grapevine/Mesquite Springs Campground, and Scotty’s Castle at Death Valley
National Park.
B. The scope of this project includes providing all labor, materials, equipment, transportation, supervision, and all other contractor-related services to rehabilitate and improve interior and exterior doors including jambs, thresholds, actuators, handles, hinges and other hardware required to complete installation at each location.
1. Removal: The contractor shall remove existing doors and appurtenances and dispose of debris at appropriate facilities outside the park.
2. Installation: The contractor shall install new doors and appurtenances.
3. Adjacent infrastructure, both Government and tenant owned, shall be protected.
4. Government will provide lock cores for each door, for contractor to install.
C. A pre-bid site visit will be scheduled for prospective offerors. Prospective offerors will meet at
Furnace Creek Visitor Center at 11AM (PST) on Wednesday July 17, 2024. NPS will provide time at
Furnace Creek to answer questions and then leading a caravan of offerors to each site. Please allow the entire day for this site visit, in order to see each building. High Clearance 4x4 vehicles are suggested for offerors to visit most sites, especially during wet conditions, at the offeror’s leisure. Please RSVP to brian_aillaud@nps.gov
1.2 SCOPE
A. All buildings shall remain operational during contractor work.
B. No local permits are required for this work.
C. Contractor shall coordinate laydown area(s) with COR prior to beginning work at each site.
D. All contractor furnished products shall be new and undamaged. COR will inspect all deliveries before contractor is to remove existing doors and begin installation.
E. Location and Contractor’s Use of Premises: The project work is in Death Valley National Park.
See attached location maps for comparative locations and distances to nearest areas.
Contractor shall always conduct operations to ensure the least inconvenience to the public.
1. FURNACE CREEK VISITOR CENTER: Four (4) sets of double doors and adjoining sidelite windows shall be replaced in-kind. A description of each door is provided for illustrative purposes, below. The doors must be similar in appearance and operation to existing doors. See Attached FCVC Rehab Plans (A2.0, A2.7, A2.8 A2.9, A8.6) for window and door locations; schedules; head, jamb and mullion details. NOTE: doors and/or hardware may have been updated since this asbuilt. Contractor to confirm.
Replace Doors at Death Valley National Park 2
Figure 1 Location of doors 101A, 102A and windows 101A, 101B and 102G.
Figure 2 Location of doors 116B and 120B.
a. Two (2) pairs of anodized aluminum glass main entrance double doors (101A, 102A) with four (4) fixed side windows and two (2) fixed transom windows. Doors and windows shall meet Architectural Barriers Act Accessibility Standard (ABAAS)
Replace Doors at Death Valley National Park 3 and have automated opening with push-button or sensor actuation. Doors must meet emergency exit requirements, swing outwards, and have push-pull bars and deadlatch. A push-button locking mechanism shall be installed at the front desk to allow NPS personnel to lock the door in the event of an active shooter. The emergency locking mechanism shall be expandable to include other doors in the complex and integrate into alarm systems during future projects.
Figure 3: Storefront elevations showing inner and outter double doors, sidelites and transoms.
Figure 4 Furnace Creek Visitor Center Entry door 101A and windows 101A and 101B (exterior). Red check marks indicated sections to be replaced, frames and glass.
Replace Doors at Death Valley National Park 4
Figure 5 Furnace Creek Visitor Center Entry Door 102A and windows 102G (interior). Red check marks indicated sections to be replaced, frames and glass.
b. Two (2) Sets of Flush exterior painted steel double-doors on Furnace Creek Visitor
Center Theater Room (120B) and multipurpose room (116B), meeting ABAAS.
Doors shall meet emergency exit requirements, swing outwards, and have an interior lockable push-bar type interior actuator and exterior handle with key lock or approved equal. Secondary door shall have integrated astragal. See Photos Below.
Figure 6 Furnace Creek VC Auditorium door
Replace Doors at Death Valley National Park 5
Figure 7 Furnace Creek VC Multipurpose Room door
2. SCOTTY’S CASTLE GAS TANK HOUSE: Replace two (2) exterior doors at the Gas
Tank House at Scotty’s Castle. Replace east entrance door with a glass storefront single-door, including transoms and sidelites, if necessary. The door shall meet ABAAS, and have automated opening with push-button or sensor actuation. Doors must meet emergency exit requirements, swing outwards, and have push-pull bars and deadlatch. A push-button locking mechanism shall be installed at the front desk to allow NPS personnel to lock the door in the event of an active shooter. The emergency locking mechanism shall be expandable to include other doors in the complex and integrate into alarm systems during future projects. South Entrance door to be replaced in kind to meet historic nature and presentation of building. All aesthetic components to be replicated. This door does not need to meet ABAAS. See below.
Figure 8 Scotty's Castle Floor Plan. East entrance door and sidelites to be replaced to meet ABAAS .
South entrance door to be replaced in kind.
Replace Doors at Death Valley National Park 6
Figure 9 Scotty's Castle East and South Elevation
Figure 10 East entrance door
Figure 11 South Entrance Door
Replace Doors at Death Valley National Park 7
3. OPTION #1: Replace four (4) Exterior doors at water utility sites.
a. MESQUITE SPRING: One (1) exterior steel outswing door rated for mechanical rooms (corrosion resistance). Door must be lockable from both interior and exterior and have new actuator installed. The door must be of a material or coating to resist corrosion from chlorine storage. See below.
Figure 12 Mesquite Spring Treatment Plant Door
b. STOVEPIPE WELLS REVERSE OSMOSIS PLANT: One (1) exterior steel outswing door rated for mechanical rooms (corrosion resistance). Door must be lockable from both interior and exterior and have new actuator installed. The door must be of a material or coating to resist corrosion from chlorine storage. See below.
Figure 10 Stovepipe Wells Treatment Plant Door
Replace Doors at Death Valley National Park 8
Figure 11 Stovepipe Wells Door
c. GRAPEVINE WATER PLANT: One (1) exterior steel outswing door rated for mechanical rooms (corrosion resistance). Door must be lockable from both interior and exterior and have new actuator installed. The door must be of a material or coating to resist corrosion from chlorine storage. See below.
Figure 12 Grapevine Water Plant Door
d. EMIGRANT CAMPGROUND COMFORT STATION: One (1) exterior steel outswing door rated for mechanical rooms (corrosion resistance). Door must be lockable from both interior and exterior and have new actuator installed. The door must be of a material or coating to resist corrosion from chlorine storage. See below.
Figure 13 Emigrant Campground Comfort Station Mechanical Room Door
Replace Doors at Death Valley National Park 9
4. OPTION #2: Install ten (10) Government-furnished interior doors in the Hacienda at
Scotty’s Castle.
Figure 13 Scotty's Castle Hacienda interior doors (location of doors is approximate and will be final-ized after inventorying government furnished doors with contractor)
Figure 14 Hacienda Interior Doors
Replace Doors at Death Valley National Park 10
Figure 15 Hacienda Interior Doors
Figure 16 Hacienda Interior Doors
Figure 17 Hacienda Interior Doors
Figure 18 Hacienda Interior Doors
Replace Doors at Death Valley National Park 11
The Government, at its sole discretion, may determine the order that work is completed.
C. The Contractor shall provide a method to secure facilities during removal and installation, allow emergency egress, operational access, and adequate signage so that visitors and employees can easily navigate detours. New exterior doors shall be fully installed, including lock cores, before leaving the building(s) for the night. Significant directional aids will be required at the visitor center when the front door is replaced. This may include, but is not limited to, signs in multiple languages, pictograms, non-permanent floor markings, illuminated or auditory beacons, temporary tactile guides, and docents to answer questions about work and physically guide visitors to an open door.
D. Period of Performance
1. Period of performance to begin 8/12/2024. Contracting officer shall issue the Notice to
Proceed (NTP) #1 once bonds and liability insurance are submitted and accepted. Upon acceptance of Division 1 submittals and at the conclusion of the preconstruction meeting, CO shall issue NTP #2 for contractor to mobilize and begin onsite work. ALL ONSITE
WORK IS ESTIMATED TO BE PERFORMED September 2024 to January 2025.
E. Field Verification
1. Contractor shall field verify all new and existing dimensions affecting the work in this contract before ordering materials.
1.3 GENERAL SUBMITTAL PROCEDURES
A. Processing Time: Allow 14 days for all submittals. When the submittal review is completed, an e-mail notification will be sent to the Contractor. Government will make every effort to process submittals expeditiously. Government will provide a CM-16 transmittal form to be a cover page for submittals.
B. Submittal Requirements
1. Prior to Issuance of NTP #1 (to begin Division 1 work) the Contractor shall submit:
a. Certificate of Liability Insurance. Ensure the certificate holder box on the ACORD form shows:
National Park Service and the United States of America
P.O. Box 579
Death Valley, CA 92328
b. Payment and Performance Bonds
2. Prior to Preconstruction Meeting and NTP #2 (to begin onsite work)
a. Letter designating Prime Contractor’s On Site Superintendent
b. Schedule of Values (to match Bid Schedule)
c. Project Schedule d Accident Prevention Plan
e. SF1413 Subcontractor Form (if applicable)
f. Product Submittals
g. Temporary Access Plan: A plan detailing NPS operational access, emergency egress, placement and examples of signage and other markings or personnel that guide visitors and employees to open doors, especially the visitor center front door.
3. Electronic Submittals: Transmit all submittals electronically in .pdf format attached to form
CM-16.
Replace Doors at Death Valley National Park 12
4. Identification: Submittal number or other unique identifier, including revision identifier.
5. Submittal number shall use a sequential number (e.g., .001). Re-submittals shall include an alphabetic suffix after another decimal point (e.g., .001.A).
1.3 REQUESTS FOR INFORMATION AND REQUESTS FOR PROPOSAL
A. The Contractor shall provide Requests for Information (RFI) in writing.
B. RFIs shall be provided following a standard format that includes, at a minimum, the request for information number (numbered sequentially by submission date), project name, contract number, date of submission, a brief descriptive title or subject of the RFI, to whom the RFI is directed, whom the RFI is from, the distribution list (e.g., carbon copy), a narrative that provides the question and any supporting information, the date a response is requested by, and any supporting documents such as catalog cutsheets. The Government will provide a template upon request.
C. The Government make every effort to respond to RFIs in a timely manner.
D. The Government may issue a Request for Proposal based on change orders, contract modifications, changing site conditions, changing mission requirements, or in response to an RFI.
1.4 MEETINGS
A. Pre-Construction Conference
1. The Government will provide an agenda for the conference prior to the conference.
a. The conference agenda will generally cover the following.
i. Project and personnel introductions
ii. A review of all pre-work documents
iii. Emergency response and health and safety
iv. A line-by-line review of the contract, scope of work, and all supporting documents.
E. Progress Meetings
1. Progress meetings are not anticipated at this time but may be required by the CO should work progress warrant the need.
F. Substantial Completion and Final Inspection
1. When the project, or a designated portion of the project, is substantially complete, the
Contractor shall request a pre-final inspection in writing at least 14 calendar days in advance of the inspection date.
2. If the work is determined to be substantially complete at the pre-final inspection, the
Contracting Officer will prepare a Letter of Substantial Completion with a Punch List of deficiencies to be corrected before final inspection / acceptance. The Contractor shall complete the work described in the Punch List within 30 calendar days, as weather permits.
Once all Punch List work is complete, the Contractor shall request a final inspection in writing to arrange for the confirmation of Punch List completion.
3. If the Contractor fails to complete the Punch List work within this timeframe, the
Contracting Officer may either replace or correct the work with an appropriate reduction in the contract price or charge for re-inspection costs in accordance with the Inspection of
Construction clause of the contract.
4. If the work is determined to be not substantially complete at the time of the pre-final inspection, the Contracting Officer will notify the Contractor in writing. The Contractor may request a new pre-final inspection; however, all re-inspection costs may be charged against the Contractor in accordance with the Inspection of Construction clause of the contract.
Replace Doors at Death Valley National Park 13
5. After all deficiencies have been corrected and the project is complete, a Letter of Final
Acceptance will be issued by the Contracting Officer. Contractor shall submit Release of
Claims along with Final invoice and 1-year Warranty Letter, after final acceptance is issued.
1.2 CONTRACTING OFFICER’S ACTION
A. General: Submittals will be disapproved without technical review if identification information is missing, not filled in, or if placed on the back of the submittal; an incorrect format of submittals is provided; the transmittal form is incorrectly filled out; submittals are not coordinated; or submittals do not show evidence of Contractor’s approval.
1. Any work done or orders for materials or services placed before approval shall be at the
Contractor’s own risk.
B. ACTION SUBMITTALS: Contracting Officer will review each submittal, generate comments on corrections or modifications required, and indicate the appropriate action on the CM-16E
Transmittal Form. The submittal will be marked in one of three ways as defined below:
1. APPROVED: Acceptable with no corrections.
2. APPROVED WITH NOTATIONS: Minor corrections or clarifications required. All comments are clear and no further review is required. The Contractor shall address all review comments when proceeding with the work.
3. DISAPPROVED - RESUBMIT: Rejected as not in accordance with the contract or as requiring major corrections or clarifications. The Contracting Officer will identify the reasons for disapproval. The Contractor shall revise and resubmit with changes clearly identified.
1.5 ACCIDENT PREVENTION
A. General. Contractor must submit certification that contractor possesses a current, OSHA compliant safety program to which the Contractor shall require all employees, subcontractors, and visitors to adhere to.
1. Equipment or tools not meeting OSHA requirements will not be allowed on the project.
2. Comply with contract clause entitled "Accident Prevention."
3. In case of conflicts between Federal, State, and local safety and health requirements, the most stringent shall apply.
4. Failure to comply with the requirements of this section and related sections may result in suspension of work.
B. ACCIDENT REPORTING: A project reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, fires, and property damage by accident in excess of $100. Notify Contracting Officer immediately in the event of a reportable accident.
Within 7 days of a reportable accident, fill out and forward to Contracting Officer an
Accident/Property Damage Report (Form CM-22). Form may be obtained from the Contracting
Officer.
C. SAFETY MEETINGS: Prior to beginning work, have a safety meeting with all personnel and the COR to review the jobsite safety requirements. As a minimum, Contractor shall also conduct daily 15-minute "toolbox" safety meetings at the beginning of each workday.
D. ASBESTOS AND HAZARDOUS MATERIALS
Replace Doors at Death Valley National Park 14
a. A good-faith survey of asbestos is provided as part of the contract documents.
b. The Contractor shall conduct all work that impacts asbestos or hazardous materials, including lead-based or lead-containing paint and animal droppings or carcasses according to applicable laws, regulations, and policies, and by adhering to industry best practices.
c. Impacts to known asbestos containing material, known hazardous materials, or materials reasonably expected to contain hazardous materials or animal waste shall be conducted at no additional cost to the Government.
d. Asbestos or hazardous materials not reasonably expected to be encountered will be treated as a differing site condition.
E. FIRE AND LIFE SAFETY: Comply with the requirements of NFPA 241 (Standard for
Safeguarding Construction, Alteration, and Demolition Operations). No smoking is permitted on jobsites.
F. SITE ACCESS: The Contracting Officer’s Representative will be at the Cow Creek
Maintenance/Administrative area of Death Valley National Park, approximately 3 miles North of the Furnace Creek Visitor Center on CA-190. Project sites are throughout Death Valley
National Park and site access will vary from paved roads to high-clearance 4x4 dirt roads.
G. ACCESS RESTRICTIONS: Work is in areas of a National Park that are open to the Public.
a. The facilities and National Park will remain in operation during the entire performance period.
b. The Contractor shall conduct their operations so as to cause the least possible interference with the normal operation of the Park.
c. The regular working hours of the Division of Maintenance is 06:00-16:30 Monday through
Thursday, except holidays. All meetings, inspections, and similar, shall be scheduled during
Division of Maintenance normal business hours.
d. The regular business hours of the Park are 08:00-17:00 Monday through Friday, except holidays.
e. No work shall be conducted within the Park outside the hours of 06:00-17:00 Monday through Friday. No work shall be conducted within the Park on federal Holidays.
f. After-Hours Work Requests must be submitted to the COR a minimum of 2 business days in advance. After-Hours Work Requests may disapprove requests and will not provide a reason for disapproval. Disapproval of After-Hours Work Requests shall not be the basis for a period of performance extension.
g. The Government may require work outside normal business hours to meet mission needs.
A request for equitable adjustment may be made through the RFI process.
h. Soundscape / Noise: The Contractor shall minimize noise levels at the project site to protect the soundscape of the Park. Perform noise-producing work in less sensitive hours or day or week or as directed by the Contracting Officer.
1.6 QUALITY REQUIREMENTS
A. General. This Section includes administrative and procedural requirements for quality assurance and quality control. Testing and inspecting services are required to verify compliance with requirements specified or indicated. These services do not relieve Contractor of responsibility
Replace Doors at Death Valley National Park 15 for compliance with the Contract Document requirements. The quality of all work shall be the responsibility of the Contractor.
B. Standards: If compliance with two or more standards is specified and the standards establish different or conflicting requirements for minimum quality levels, comply with the most stringent requirement. Refer uncertainties and requirements that are different, but apparently equal, to
Contracting Officer for a decision before proceeding.
C. Off-Site Inspection: Items that are fabricated or assembled off-site shall be inspected for quality control at the place of fabrication.
D. CO shall stop work on any item or feature pending satisfactory correction of any deficiency noted by the COR.
1.7 QUALIFICATIONS OF EMPLOYEES:
1. All employees must be physically qualified and able to perform their assigned duties in a safe manner.
1. Do not allow employees to perform work whose ability or alertness is impaired because of prescription or illegal drug use, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.
2. Operators of vehicles, manlifts, etc. shall be able to understand signs, signals, and operating instructions, and be fully capable of operating such equipment. Provide operating instructions for all equipment. Newly hired operators shall be individually tested by an experienced operator or supervisor to determine if they are capable of safely operating equipment.
END OF GENERAL SPECIFICATIONS
Replace Doors at Death Valley National Park 16
PART 2 - MATERIALS
2.1 DOORS
A. Replace all doors in-kind or with approved equals.
B. Glass shall be low-e, or similar, insulated, and bird friendly.
C. All materials shall be suitable for saline soils, corrosive environments, high winds, blowing sand and dust, and extremes of heat, cold, and humidity/lack-thereof.
D. All materials shall be finished according to law, regulation, policy, and industry best practices.
END OF MATERIALS
Replace Doors at Death Valley National Park 17
EXECUTION
2.2 SAFETY
A. The Contractor, subcontractors, and their employees shall be familiar with and comply with
Occupational Safety and Health Administration requirements set forth in 29 CFR Parts 1910 and
1926, and all federal, state, and local regulations, as applicable.
B. The Contractor shall bear sole responsibility for any penalties and downtime charges imposed for noncompliance.
C. The Contractor shall maintain a copy of the approved Accident Prevention Plan on-site during all phases of the project and shall ensure that all on-site personnel have reviewed and are familiar with the plan. All safety equipment referenced in the Accident Prevention Plan shall be at the work site and calibrated (if applicable) before work begins.
D. The Contractor shall, at all times, maintain safe and continuous access to the work site for the
Contracting Officer’s Representative, federal, state, and local authorities. The Contractor shall provide all necessary safety measures including, but not limited to, fencing, barricades, warning signs, and flags, to ensure the safety of the employees, tenants, and the public. Required barricades, warning signs, etc. shall be placed around the work zone prior to initiation of work and kept in place until all work is complete.
E. The Contractor shall store or handle gasoline or other flammable liquids in strict accordance with
NFPA 30 and all state and local fire marshal requirements.
F. The Contractor shall have a minimum of one 10-pound class ABC fire extinguisher at each work site and two 20-pound class ABC fire extinguishers in any location where spark-producing or hot work is conducted. Where materials warrant, other fire extinguisher sizes and classes shall be at the work site according to law, regulation, policy, or industry best practice.
G. The Contractor shall be responsible for directing the use of personal protective clothing and equipment to minimize employee exposure in accordance with the OSHA.
H. The Contractor shall eliminate all unnecessary sources of ignition, including smoking materials, form the work area.
I. All work shall be completed in a manner that minimizes the possibility of any threat to human health and safety or the environment.
END OF EXECUTION
Replace Doors at Death Valley National Park 1
PART 3 - Sample Forms
CONTRACTOR'S QUALITY CONTROL DAILY REPORT
REPORT NO. _________ SHEET 1 OF _________
PROJECT
CONTRACT NO.
DATE
PARK
CONTRACTOR'S REPRESENTATIVE ON THE JOB
WEATHER (Rain, Snow, Cloudy, Windy, etc.)
RAINFALL
Inches
TEMPERATURE GROUND CONDITIONS (Dry, Damp, Wet, Frozen, etc.)
MAX.
MIN.
1. PRIME CONTRACTOR
NO. EMPLOYEES BY JOB CATEGORIES Hours HEAVY EQUIPMENT ON
JOB
NO.
UNITS
HRS. WORKING
YES NO Comments
WORK PERFORMED BY PRIME CONTRACTOR:
MATERIALS DELIVERED OFFICIAL VISITORS TO SITE
2A. SUBCONTRACTOR, _____________________________________________: (If more than one subcontractor use copies of following page.)
NO. EMPLOYEES BY JOB CATEGORIES Hours HEAVY EQUIPMENT ON
JOB
NO.
UNITS
WORK PERFORMED BY SUBCONTRACTOR:
3. SPECIFIC INSPECTIONS: (Inspections performed, results, and corrective actions)
4. TESTING: 1 Check if any testing was performed today. (Complete and attach Test Report Information Sheets.)
Type and Location of Testing: ____________________________________________________________________________________
5. VERBAL INSTRUCTION RECEIVED FROM GOVERNMENT ON CONSTRUCTION DEFICIENCIES OR RE-TESTING
REQUIRED:
6. REMARKS:
7. CERTIFICATION:
I certify that the above report is complete and correct and that I, or my authorized representative, have inspected all work performed this day by the prime contractor and each subcontractor and determined that all materials, equipment, and workmanship are in strict compliance with the plans and specifications except as may be noted above. ____________________________________________________________
Contractor's Quality Control Representative
Replace Doors at Death Valley National Park 2
SUBCONTRACTOR WORK CONTINUED:
CONTRACT NO. REPORT NO. _______
SHEET ____ OF ____
2 SUBCONTRACTOR,
NO. EMPLOYEES BY JOB CATEGORIES Hours HEAVY EQUIPMENT ON
JOB
NO.
UNITS
2 SUBCONTRACTOR,
JOB
NO.
UNITS
JOB
NO.
UNITS
JOB
NO.
UNITS
YES NO COMMENTS
File details come from the government source that posted it. Updated .