Questions_and_Answers_0001.pdf
PDF 187 KB Posted
- Attached to
- Hazardous Tree Removal Federal contract opportunity
- Solicitation number
- 140P6426Q0104
About this file
This is a Questions and Answers document (Amendment 0001) for federal contract solicitation 140P6426Q0104 regarding Hazardous Tree Removal services at an Integrated Advanced Tree Removal (IATR) location.
The document addresses ten clarifications to the Statement of Work and procurement requirements. Key specifications include: stump grinding to 12 feet below surface with certified weed-free topsoil coverage for all 15 identified trees; no equipment restrictions for limited-accessibility areas, though operators must mitigate rutting and fill any ruts with clean topsoil prior to completion; contractor responsibility for coordinating utility locating through Diggers Hotline for electrical utilities, fiber optic cabling, and septic systems, with NPS staff to pre-flag the septic mound and related infrastructure; contractor responsibility for identifying and arranging disposal of all vegetative waste outside the park; non-compensable Period of Performance extension via formal contract modification if documented adverse weather exceeds the 10-day allowance within the 45-calendar-day performance period; Item 12 limited to limb removal only due to red-headed woodpecker habitat with required bird protection measures; public site accessibility for vendor inspections outside the scheduled site visit on 7/24/26 at 11:00 a.m. (with parking in Dane County lot); no reservation requirement for site visit attendance; Statement of Work descriptions as the controlling document over discrepancies in the Price Schedule; and submission of all quotes and inquiries to ryan_begany@ios.doi.gov. An updated Statement of Work, Price Schedule, and Clause Package have been attached to the amendment.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P6426Q0104_Amd_0002.pdf | ||
| Questions_and_Answers_0002.pdf | ||
| Statement_of_Work_-_Revised_0002.pdf | ||
| Price_Schedule_-_Revised_0001.pdf | ||
| Price_Schedule_-_Revised_0001.xlsx | XLSX spreadsheet | |
| Clause_Package_-_Revised_0001.pdf | ||
| Statement_of_Work_-_Revised_0001.pdf | ||
| Sol_140P6426Q0104_Amd_0001.pdf | ||
| Wage_Determination.pdf | ||
| Sol_140P6426Q0104.pdf | ||
| Statement_of_Work.pdf | ||
| Price_Schedule.pdf | ||
| Price_Schedule.xlsx | XLSX spreadsheet |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation #: 140P6426Q0104
Amendment #: 0001
Hazardous Tree Removal – IATR
Questions and Answers listed below:
QUESTIONS:
Question # Question Answer/Response
1. Stump Grinding Specifications: The
Statement of Work (SOW) requires stump grinding for all 15 identified trees but does not specify a mandated depth.
Could the Government clarify if stumps must be ground to a specific depth below grade (e.g., 6 or 12 inches) and if the resulting holes must be backfilled with topsoil and seeded?
Stumps should be ground to 12’ below surface, covered with clean topsoil (certified weed free). An updated Statement of Work has been attached to the Amendment.
2. Equipment Restrictions and Site Access:
Appendix A identifies two trees with "limited accessibility" directly adjacent to the office building and garage. Given the requirement to use "low-impact methods" to minimize soil and vegetation disturbance, are there specific weight restrictions or prohibited equipment types (e.g., cranes or large bucket trucks) for the turf areas surrounding these structures?
There are no equipment limitations.
Accessibility is limited only based on elevation changes; therefore, large equipment might be difficult to stage.
Preserving the integrity of the turf is not necessary. However, operators would be asked to mitigate rutting as much as possible. If this occurs, operators would be asked to fill the ruts (with clean topsoil) prior to project completion. An updated Statement of Work has been attached to the Amendment.
3. Utility Locating Responsibilities: SOW Section 3.2 states the vendor is responsible for "locating and preventing damage to known utilities," specifically mentioning a septic mound. To ensure the safety of on-site personnel and infrastructure, will the Government provide recent as-built drawings for these systems, or is the contractor expected to procure private utility locating services?
Operators would need to work with diggers hotline to locate below ground electrical utilities, including fiber optic cabling and septic pipes/exterior plumbing. The septic mound and related infrastructure can be flagged in advance of project start date by NPS staff. Septic mound and known utilities are illustrated on map below. An updated Statement of Work has been attached to the Amendment.
4. Debris Disposal Parameters: The SOW requires all vegetative waste to be disposed of legally "outside the park".
To allow for accurate pricing of hauling and tipping fees, could the Government confirm if there is a preferred local disposal site or if the contractor is entirely responsible for identifying a facility?
The contractor is entirely responsible for identifying a facility and making arrangements for disposal of all vegetative waste. An updated Statement of Work has been attached to the Amendment.
5. Adverse Weather Procedures: The 45-calendar-day Period of Performance (PoP) explicitly includes an allowance for 10 weather days. In the event that documented adverse weather exceeds this 10-day threshold, will the Government grant a non-compensable extension to the PoP via a formal contract modification?
If adverse weather exceeds the 10 day threshold, the Government will grant a non-compensable extension to the PoP via a formal contract modification upon confirmation with the park that adverse weather conditions exist.
6. Is Item 12 for limb removal only?
Item 12 is for limb removal only since it is heavily occupied by red headed woodpeckers and other later successional tree dwelling species. All necessary mitigation measures should be taken not to harm any birds/active nests. An updated Statement of Work has been attached to the Amendment.
7. Is the site accessible if vendors are unable to attend the Site Visit?
If vendors are unable to attend the Site Visit, they are encouraged to inspect the site. All trees that need to be removed are on property that is accessible to the public. The designated trees will be marked by COB of 7/21/26. Park staff are unavailable to provide any guidance regarding this requirement, outside of the designated POC during the scheduled Site Visit 7/24/26 at 11am.
Please park in Dane County parking lot for any inspection outside of the scheduled Site Visit, not the staff parking lot. Park offices and facilities are unavailable to the public.
8. Is a reservation required to attend the Site Visit?
No reservation is required to attend the Site Visit. Interested parties must simply be present at the appropriate place and time. No additional Site Visits will be conducted.
9. There are discrepancies between the descriptions of several items in the Statement of Work and Price Schedule.
Which description is correct?
The descriptions in the Statement of Work are correct. A corrected Price Schedule reflecting what is in the Statement of Work has been attached to the Amendment.
10. Which email address should the quote be sent to?
All quotes and inquiries should be sent to ryan_begany@ios.doi.gov. The Clause Package has been corrected to show the appropriate email address and attached to the Amendment.