Atch_4_FAR_Clause_52_211-10_Revised_0001.pdf

PDF 64 KB Posted

Attached to
MORU-Energy Plant HVAC Upgrade
Solicitation number
140P6321B0011
Issued by

About this file

This document contains a federal contract clause specifying performance requirements and a related federal contract opportunity notice. The contract clause sets a project completion date of May 30th, 2022 for work to commence within 10 days of notice and be prosecuted diligently. The related solicitation is for an Energy Plant HVAC Upgrade at Mount Rushmore National Memorial for the Department of the Interior National Park Service Midwest Region. The opportunity type is a solicitation and the requirement is to upgrade the HVAC system at the Mount Rushmore energy plant.

View the file

Other files

File Type Posted
Atch_2_Drawing_M1_Update_0001.pdf PDF
Atch_3_Questions_Answers_0001.pdf PDF
Atch_1_POP_Phased_Approach_0001.pdf PDF
Sol_140P6321B0011_Amd_0001.pdf PDF
Drawings.pdf PDF
Specifications.pdf PDF
Sol_140P6321B0011.pdf PDF
5_13_21_COVID-19_Mask_Policy.pdf PDF
DOL_Wage_Determination.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984) Alternate I (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 5/30/2022. The time stated for completion shall include final cleanup of the premises.

The completion date is based on the assumption that the successful offeror will receive the notice to proceed by 9/13/2021. The completion date will be extended by the number of calendar days after the above date that the Contractor receives the notice to proceed, except to the extent that the delay in issuance of the notice to proceed results from the failure of the Contractor to execute the contract and give the required performance and payment bonds within the time specified in the offer.

(End of clause)