Statement of Work Summary
This Statement of Work (SOW) describes the replacement of HVAC system components at the Visitor Center (Building 213) at Fort San Cristóbal, San Juan National Historic Site, located at 501 Calle Norzagaray, San Juan, Puerto Rico. The project requires removal and replacement of eight complete HVAC systems, consisting of six 5-ton units and two 4-ton units from manufacturers Trane and Gree. The contractor must provide all labor, materials, equipment, supervision, and services to remove existing aging systems and install new high-efficiency, factory-matched condensing units and interior air handling units designed for EPA-approved low-GWP refrigerants (R-454B, R-32, or manufacturer-approved alternatives). The project addresses salt air corrosion issues and the industry transition away from R-410A refrigerant, requiring complete system replacement to ensure manufacturer-approved compatibility.
All new HVAC equipment must be U.S.-manufactured with minimum SEER2 ratings of 22 or greater, 208/230-volt electrical systems, seven-year compressor warranties, and five-year parts warranties. Specific corrosion protection requirements include anti-corrosion condenser coil coating, saltwater-rated components, and corrosion-resistant cabinet construction. Installation work encompasses replacement of copper refrigerant piping, receiver-drier filters, thermostatic/electronic expansion valves, condensate drain systems, air filters, and electrical connections compliant with the National Electrical Code. Disconnect switches must be non-metallic, NEMA 4X-rated Mennekes brand enclosures. Exterior units require corrosion-resistant wind anchoring systems, rooftop pedestals, and stainless steel tie-down hardware without roof penetrations. The contractor must recover all refrigerants per EPA regulations, remove and properly dispose of existing equipment, provide an on-site superintendent during active work, perform system startup and commissioning, and deliver operation and maintenance manuals, warranty documentation, and training records prior to contract closeout.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work
Replace HVAC System Components
Visitor Center – Building 213
Fort San Cristóbal – San Juan National Historic Site 501 Calle Norzagaray San Juan, Puerto Rico
1. Project Title
Replace HVAC System Components – Visitor Center (Building 213)
2. Project Location
Fort San Cristóbal San Juan National Historic Site Visitor Center – Building 213
3. Background
The Visitor Center at Building 213 currently operates multiple aging HVAC systems that have experienced declining efficiency and reliability. Due to the coastal marine environment, the existing equipment is exposed to salt air corrosion, reducing its service life.
In addition, HVAC manufacturers have transitioned from R-410A refrigerant to new lower Global Warming Potential (GWP) refrigerants, such as R-454B and R-32, to comply with current environmental regulations. Because these new refrigerants require compatible system components, the existing interior air handling units (evaporator units) are not suitable for reuse with new condensing units. This project therefore includes replacement of both the exterior condensing units and the associated interior air handling units to provide complete, manufacturer-approved matched HVAC systems.
The new systems will improve energy efficiency, reliability, humidity control, and occupant comfort while ensuring compliance with current industry standards and manufacturer requirements.
4. Scope of Work
The Contractor shall provide all labor, materials, equipment, supervision, and services necessary to remove the existing HVAC systems and install complete new high-efficiency HVAC systems at the Visitor Center (Building 213).
Work shall include, but is not be limited to:
• Removal and replacement of all exterior condensing units.
• Removal and replacement of all interior air handling units (evaporator units).
• Replacement of all refrigerant piping.
• Replacement of refrigerant accessories required by the manufacturer.
• Replacement of electrical connections and controls as necessary.
• Startup, testing, balancing, commissioning, and operational verification of each complete HVAC system.
All equipment shall be furnished as factory-approved matched systems designed to operate with the manufacturer's specified refrigerant.
All work shall comply with manufacturer specifications, industry standards, and applicable Federal, State, and local codes.
The Contractor shall provide an on-site superintendent or foreman present at all times during active work.
5. Existing Condensing Units to be Replaced
Location Tonnage Manufacturer Model Number
Location #1 5 Ton Trane 4TTR3060E1000NA
Location #2 5 Ton Trane 4TTR6061C1000AA
Location #3 5 Ton Trane 4TTV0048A1000CD
Location #4 5 Ton Gree FLEXX60AC230V1A0
Location #5 5 Ton Gree FLEXX60AC230V1A0
Location #6 4 Ton Trane 4TTR3048E1000PB
Location Tonnage Manufacturer Model Number
Location #7 4 Ton Trane 4TTR3048E1000PB
Location #8 4 Ton Trane 4TTR3048E1000PB
Total HVAC systems to replace: 8
Each HVAC system shall include replacement of both the exterior condensing unit and the associated interior air handling unit.
6. Equipment Requirements
All new HVAC equipment shall meet the following requirements:
• Factory-matched condensing unit and indoor air handling unit.
• Compatible with current EPA-approved refrigerants (R-454B, R-32, or manufacturer's current approved refrigerant).
• Units shall be manufactured in the United States.
• Minimum SEER2 rating of 22 or greater, where commercially available for the equipment size.
• Electrical system: 208/230 Volt.
Minimum Warranty
• Seven (7) Year Compressor Warranty
• Five (5) Year Parts Warranty
Corrosion Protection
Due to the coastal environment, all exterior condensing units shall include:
• Anti-corrosion condenser coil coating.
• Components rated for saltwater environments.
• Corrosion-resistant cabinet construction.
Indoor air handling units shall be compatible with the selected condensing units and furnished with factory-approved evaporator coils designed for the specified refrigerant.
7. Installation Requirements
Condensing Units
• Install new exterior condensing units at existing locations.
• Replace all copper tubing with new copper tubing to accommodate new R-32 or R454B refrigerant.
• Replace all inline HVAC Receiver Drier Filter
• Each unit shall include breaker panel circuit labeling identifying the corresponding HVAC system.
• Each unit shall include a disconnect switch located in the immediate vicinity.
Disconnect switches shall be:
• Non-metallic
• NEMA 4X rated enclosure
• Mennekes brand or approved equal
Interior Air Handling Units
The Contractor shall remove and replace all existing interior air handling units.
Installation shall include:
• New factory-approved evaporator coils.
• New thermostatic expansion valve (TXV) or electronic expansion valve (EEV), as required by the manufacturer.
• New condensate drain connections and traps where required.
• New auxiliary drain pans and overflow safety switches where applicable.
• New condensate float safety switches.
• New air filters.
• New insulation as required.
• Reconnection to existing ductwork with modifications as necessary to provide proper fit and airflow.
Refrigerant Piping
All existing refrigerant piping shall be removed and replaced.
New piping requirements:
• New ACR Type L copper tubing.
• Tubing sizes shall be verified and matched to manufacturer requirements.
• Suction lines shall include all-weather insulation.
• Liquid lines shall be properly sized.
• Installation shall comply with manufacturer requirements for new refrigerants.
Piping Protection
• Refrigerant lines passing through floors or concrete walls shall be installed inside PVC conduit.
Electrical Work
• Remove existing electrical connections.
• Install new wiring between breaker panels, condensing units, and air handling units as required.
• Replace control wiring as necessary.
• All electrical work shall comply with the National Electrical Code (NEC).
Equipment Anchoring
Exterior condensing units exposed to open-air environments shall include:
• Corrosion-resistant wind anchoring systems.
• Rooftop equipment pedestals.
• Stainless steel tie-down hardware.
Units shall be mounted without roof penetrations.
8. Removal and Disposal
The Contractor shall:
• Remove all existing condensing units.
• Remove all existing interior air handling units.
• Remove existing refrigerant piping.
• Recover all refrigerants in accordance with EPA regulations.
• Dispose of equipment and refrigerants in accordance with all applicable Federal, State, and local regulations.
13. Deliverables
Prior to Notice to Proceed
The Contractor shall submit:
• Equipment product submittals for COR approval.
• Condensing unit and air handling unit specifications.
• Equipment dimensions and weights.
• Manufacturer documentation verifying matched-system compatibility.
Prior to Contract Closeout
The Contractor shall provide:
• Two (2) hard-bound Operation and Maintenance Manuals.
• One (1) hard-bound warranty manual.
• Equipment model and serial number list for all condensing units and air handling units.
• Documentation of system startup and commissioning.
• Documentation of training completion.