Questions_and_Answers_0002.pdf

PDF 85 KB Posted

Attached to
REPLACE HVAC AT ERNEST COE VC Federal contract opportunity
Solicitation number
140P5425R0010
Issued by
Department of the Interior National Park Service Southeast Region

About this file

This document is a Pre Award Site Visit Questions and Answers (Q&A) for the Earnest Coe Visitor Center HVAC Replacement project. The Q&A addresses six key technical considerations for the HVAC system replacement, including installation logistics, refrigerant line routing, electrical configuration, and equipment compatibility. Critical details include confirming the feasibility of using a chain hoist for condenser placement, verifying refrigerant line routing options to minimize interior disruption, determining fresh air intake requirements, and resolving electrical system complexities with the 4-ton and 7.5-ton HVAC systems. The contractors will need to carefully navigate existing infrastructure constraints, ensure code compliance, and potentially involve an electrician to address wiring and phase requirements for the new HVAC equipment.

The document highlights specific technical challenges, such as the inability to find a two-condenser to one air handler option with A2L refrigerant, potential needs for rewiring, and the requirement to replace the HVAC system to current code standards. The project involves the National Park Service and will require precise planning to minimize operational disruption at the Everglades National Park's Ernest Coe Visitor Center.

View the file

Other files for this federal contract opportunity

Other files attached to REPLACE HVAC AT ERNEST COE VC, newest first.
File Type Posted
160-127398A_As_Built_Coe_HVAC_0002.pdf PDF
Sol_140P5425R0010_Amd_0002.pdf PDF
Pages_from_1996_EVER-246_Plans_0002.pdf PDF
Sol_140P5425R0010_Amd_0001.pdf PDF
Sol_140P5425R0010.pdf PDF
Wage_Determination.pdf PDF
Past_Performance_Questionnaire.pdf PDF
Statement_of_Work.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Earnest Coe VC HVAC Replacement

Pre Award Site Visit Q&A

1.Can we use a chain hoist to lift the condenser over the pedestrian bridge railing? I'm confident the structure is strong enough. We would like to avoid disassembly of the units to prevent unnecessary contamination. See photo with yellow area indicating where the chain host would be used. We would use high capacity cloth straps to hold the chain hoist to prevent any damage to the paint of the structure and use this to hoist the new condensers over the railing. Hoist shall not be used to lift HVAC condensers over rail.

2. Can we avoid cutting the interior floor for the refrigerant lines on the main unit to avoid the huge mess it would make and interfere with operations. We would prefer to go directly out the exterior wall and need to confirm that going out the wall and under the sidewalk outside will comply with the accessibility officer. See Photo. The cover for the new line location will stick out onto the sidewalk by about 7 inches before going under the slab. Not as much as the fire standpipe also shown in the photo with the yellow arrow. See additional photo for proposed new line set route across the mechanical room floor and confirm this will also be acceptable. We would install a cover over the piping to protect it. Yes lines can be routed as contractor sees fit if new installation does NOT present a tripping hazard or is protected by line set kit.

3. We cannot verify where the fresh air intake is for the main unit. Can we get original plans to review or have someone from the NPS confirm where the fresh air intake is and if it is adjustable. Fresh air is required by code, and we need to know if we have to include adding fresh air to the system to bring it into compliance. Attached contractors will find as built plans and original plans to the visitor center. Contractor shall replace HVAC system to code.

4. We need to confirm that the fire standpipe where we would be cutting the sidewalk doesn't run under the area the sidewalk will be sawed to make the new line set run.

Refer to the piping photo with the fire pipe marked with yellow arrow (above). Fire sandpipe runs straight out to pumphouse from behind column. It does not run underneath the area which would require cutting.

5. The 4 ton system has a single phase air handler, but the condenser unit data plate is faded, and we could not verify if it is single phase or 3 phase. Please advise as the bid request states 3 phase 4 ton but as stated the air handler is single phase. Condenser is 3 phase and only a single phase is used for condenser. There is availability for a 3 phase air handler.

6. We have discovered in the process of getting quotes for equipment to replace the existing units that the 7.5 ton system will have some questions moving forward. No brand offers a two condenser to one air handler option with A2L refrigerant. Now all the options are a single air handler to a single, either two stage, two compressor set up or a variable 2 stage condenser with a single compressor. The question comes in is that the existing system has two condensers at 4 ton. They are wired for that size condenser. Now we would have choice but to put a single 7.5 condenser which will have a significantly higher max overcurrent protection device (about 50-60) and a minimum circuit ampacity of around 40 amps. The wires serving these two condensers are inadequate for this new application.

Should we also get an electrician involved to pull a new wire if possible or can your team verify what options we have? If the contractor decides to go with a 3 phase HVAC unit they will have to rewire. If they decide to install a single-phase unit, they can possibly use the same conduit and might need to increase wire size at the panel. Either way it would involve an electrician.