This document is an attachment containing questions and answers related to solicitation number 140P5424R0004 from the Department of the Interior National Park Service Southeast Region to replace the shake roof at Timuquana Park. The solicitation seeks bids to replace an existing shake roof at a National Park Service site located in the Southeast Region. Bids are due by the date specified in the original solicitation document, and the contract is to be awarded shortly thereafter. The work must be completed during the timeframe outlined in the performance work statement.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P5424R0004_Amd_0003.pdf | ||
| Sol_140P5424R0004_Amd_0002.pdf | ||
| Sol_140P5424R0004_Amd_0001.pdf | ||
| Atch_2_to_Amd_1_Report_0001.pdf | ||
| Sol_140P5424R0004.pdf | ||
| Atch_4_Site_Visit_Info.pdf | ||
| Atch_2_DOL_DBA_WD.pdf | ||
| Atch_1_SOW.pdf | ||
| Atch_5_Past_Perf_Questionnaire.pdf | ||
| Atch_3_Drawings_and_Photos.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
140P5424R004 Amendment 1 Attachment 1
Page 1 of 3 Pages
Question #1: Since this will be a government project, if we hold a contractor’s license in other states, are there any other licenses that are required by the state of Florida or is it not required since it’s a government contract?
Answer: When a project is under the jurisdiction of a federal agency and located on federal property, state licensing requirements will normally not be enforceable. You should be fine as long as you’re able to provide the required documents. (bonds, insurance, bid guarantee, etc)
Question #2: What size and type of shingle or shake that is to be used? We might be overlooking it in the documents, but did not see that in there. Is it a shingle or wooden shake?
Answer: Reference top of page 3 of the Statement of Work (Atch 1 of the solicitation) “Western Red Cedar Shingles, 100% clear, 100% heartwood, 100% edge grain with no defects”
Question #3: Can you verify if it is closed decking or open-spaced?
Answer: It is mostly closed, but there is only a small spot in the second story that we can actually see the decking.
Question #4: Will the government be providing the shingles?
Answer: No
Question #5: Will the NPS accept estimates that include Metal Shake Roofing as an alternative to the Red Cedar Shake?
Answer: No
Question #6: Can we get clarification regarding the copper discussed in paragraph K of the SOW? Are the copper strips required on every row of shingles from the gutter to ridge?
Answer: No. Not every row. The kitchen building, as an example, has two rows of copper strips. One at the top of the roof and then one about midway down.
Question #7: Is a Florida roofing license required for this project?
Answer: No
Question #8: Will a separate Superintendent, Quality Control and SSHO be needed for the project or if one individual can serve as a triple hat for all of these roles?
Answer: One person can do all if needed.
Question #9: Per the provided Roof Plan Drawings issued by Shepard Associates, (Sheets A-4 – A-6) reference other work regarding the Main House and Carriage House. Please confirm the Carriage House work is not to be part of this scope of work and not included in the (Main House Bid). Please also confirm work associated to grade adjustments, plaster, painting, etc. as shown on the plans are for reference only and are not to be completed in the bid as well, as not referenced in the Solicitation – Description of Services Answer: Carriage House and the Breezeway are not part of this part of this project. This project is for the roof and the gutters of the Main House.
Question #10: Page 3 – D. What is hardware cloth? Inspect and replace as needed. This is not industry standard, and direction is needed.
Answer: Disregard the hardware cloth in the specifications and SOW.
Attachment 1
Page 2 of 3 Pages
Question #11: M- Spec is calling for Boston Ridge cap style. Is this to be Installed as is or field cut to pitch?
Answer: Field Cut
Question #12: No drip or rake exists. Is the goal to have drip and rake installed throughout the project?
Answer: Yes
Question #13: There is no gutter on the upper roof. Are we adding that with downspouts to the dead valleys?
Answer: No
Question #14: Is the skylight going to be replaced with like and kind. Is this to be impact?
Answer: No
Question #15: Are the two built wooden structures that sit at two different peaks going to be discarded or are they going to be roofed around or rebuilt?
Answer: No. The finials will be copied, rebuilt, and replaced as part of the contract. At the end of the project they will be on the 4 peaks of the house.
Question #16: The small structure at one of the peaks cannot be roofed without removal. When this is removed is the goal to reinstall? Also, should we budget to rebuild any structures that are damaged due to poor condition during removal process?
Answer: Yes the finial will be removed, replicated, and placed atop the roof. The other two missing finials will also be replicated and placed atop the roof, as well.
Question #17: Do we need to provide pricing for the painting?
Answer: Yes
Question #18: Has there been a lead base paint survey performed? Please provide if available.
Answer: Yes. The lead based survey was done in 2019 just before the house was painted. See Atch 2 to this amendment.
Question #19: Does the Government know if there is any lead base paint on the building?
Answer: Please refer to the lead-based survey attached in attachment 2.
Question #20: When we replace the head wall and the side wall flashing, is the goal to take out only the siding that is necessary to complete the roofing work or all the siding?
Answer: Only the siding that is necessary.
Question #21: Is a historical preservationist required for this project 100% of the time onsite?
Answer: No
Question #22: Can we utilize drone photography for estimating purposes and historical record-keeping?
If so, what would be the best time to do so?
Answer: Yes. Please contact the COR at 904-571-8372.
Attachment 1
Page 3 of 3 Pages
Question #23: Please confirm the staging area as designated by TIMU.
Answer: At this moment the area is southwest of the Main House, but this is subject to change.
Question #24: In keeping with historical replacement, western cedar is being requested, yet the building has Alaskan yellow - please confirm this is the intent to change the product during replacement.
Answer: Yes. The project is calling for western red cedar.
Question #25: Task Item #3, section C, subsection i) states that the a deduct price still needs to be provided to accommodate full ice and water installation. All old furring must be removed. Please advise.
Answer: We do not understand your question.
Question #26: Is there any additional information on airflow calculations that led the HPTC to determine furring strips were more effective at ventilating than using a continuous breather mat?
Answer: No
Question #27: Specifications 4 Item B- Do you know if there is any additional information/direction to be provided regarding carpentry items requested for Widows Walk?
Answer: No carpentry needed for the Widow’s Walk
Question #28: Specification 4 Item D- If a conflict occurs with technical information between CSSB/NRCA and Historic Guidelines, please confirm that CCSB will supersede.
Answer: CSSB supersedes
Question #29: Please confirm the location of the requested mockup.
Answer: 11676 Palmetto Ave. Jacksonville, FL 32226
Question #30: Will exceptions be made for rain delays and material delivery to regular working hours?
Answer: If awardee is nearing the end of the 60 day period and determines they will not be able to complete the project in the allotted time, they must coordinate with the appointed Contracting Officer Representative (COR) with justification to request the Contracting Officer (CO) process a modification to the contract that extends the period of performance.
Question #31: Please confirm which road will be utilized for receiving the material, as cedar comes as direct trucks.
Answer: Deliveries should use Palmetto Avenue since it is a straight road.
Question #32: Is the covered walkway and other structure included in the requirement?
Answer: No
Note: Any answers or clarifications that add to or change any information currently in the statement of work (SOW) will be incorporated before award. Acknowledgement of these answers demonstrates offeror’s receipt of updated info.