This is an Amendment of Solicitation/Modification of Contract (Standard Form 30, Amendment 0003) issued by the National Park Service, Southeast Region – North MABO (Maintenance Base Operations) located in Gatlinburg, Tennessee. The amendment is effective March 31, 2026, and applies to solicitation number 140P5326Q0017, originally dated March 31, 2026.

The amendment incorporates Government responses to vendor inquiries and issues a revised Statement of Work (SOW) reflecting clarifications and scope changes. Key modifications include: incorporation of official Questions and Answers addressing stone stacking foundations, stone cap requirements, bridge loading limitations, sandblasting restrictions, and concrete surface treatments (provided as attachment 140P5326Q0017 MACA Questions and Answers.docx); and a revised SOW (MACA_337611A_SOW.doc) that updates requirements for adhered stone veneer systems, substrate preparation, veneer materials, dowel installation, limestone cap installation for piers/columns, restricted load limits for bridge-mounted equipment, removal of full-surface sandblasting (limited to localized crack repair only), concrete sealer specifications, and enhanced detail on repair methods, quality control, submittal requirements, and continuous pedestrian access obligations. The amendment does not extend the proposal due date or modify evaluation factors. The period of performance is May 6, 2026, through October 28, 2026. All other terms and conditions remain unchanged.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: is not is required copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7.ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

PAGESOF

Contractor

The hour and date specified for receipt of Offers to sign this document and return

William Leady

See continuation page

NPS, SER - North MABO 107 Park Headquarters Road Gatlinburg TN 37738

PSN

140P5326Q0017

03/31/2026

03/31/2026

1 3

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

NSN 7540-01-152-8067

140P5326Q0017/0003

This amendment incorporates Government responses to vendor inquiries and issues a revised Statement of Work (SOW) reflecting clarifications and scope changes. The following changes are hereby made:

Incorporation of Questions and Answers:

The Government¿s official Questions and Answers dated with the solicitation are hereby incorporated. These include clarifications regarding stone stacking foundations, stone cap requirements, bridge loading limitations, sandblasting restrictions, and existing concrete surface treatments.

- Q&As are provided as Attachment:

140P5326Q0017 MACA Questions and Answers.docx.

Revised Statement of Work (SOW):

The SOW has been updated to incorporate the

Government¿s determinations and technical clarifications in response to vendor questions.

Revisions include, but are not limited to:

- Updated requirements for adhered stone veneer system, substrate preparation, veneer materials, and dowel installation.

- Inclusion of limestone cap installation specifications for piers/columns.

- Clarification of restricted load limits for bridge¿mounted construction equipment.

- Removal of full¿surface sandblasting from the scope; sandblasting limited only to localized crack repair areas.

- Clarification of concrete sealer requirements and existing surface conditions.

- Additional detail on repair methods, quality control, submittal requirements, and continuous pedestrian access obligations.

The revised SOW is issued as Attachment:

MACA_337611A_SOW.doc and fully replaces the previously issued SOW.

Continued...

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

NSN 7540-01-152-8067

140P5326Q0017/0003

No Changes to Due Date or Evaluation Criteria:

This amendment does not extend the proposal due date and does not modify evaluation factors unless otherwise stated in a subsequent amendment.

All Other Terms and Conditions Remain

Unchanged.

Period of Performance: 05/06/2026 to

10/28/2026

Amendment of solicitation/modification of contract
Contract ID code
Amendment/modification number
Effective date
Requisition/purchase requisition number
Project number
Issued by
Code
Administered by
Code
Name and address of contractor
Code
Facility code
Amendment of solicitation number
Dated
Modification of contract/order number
Dated
This item only applies to amendments of solicitations
Accounting and appropriation data
This item applies only to modifications of contracts/orders.
This change order is issued pursuant to:
The above numbered contract/order is modified to reflect the administrative changes
This supplemental agreement is entered into pursuant to authority of:
Other
Important:
Description of amendment/modification
Name and title of signer
Contractor/offeror
Date signed
Name and title of contracting officer
Signature of Contracting Officer
Date signed
Previous edition unusable
Standard form 30 (rev. 11/2016)
Continuation sheet
Reference Number
Name of Offeror or Contractor
OPTIONAL FORM 336 (4-86))

Sponsored by GSA FAR (48 CFR) 53.110

File details come from the government source that posted it. Updated .