Sol_140P5326Q0017_Amd_0003.pdf
PDF 208 KB Posted
- Attached to
- MACA-REPAIR OF PEDESTRIAN BRIDGE FOUNDAT
- Solicitation number
- 140P5326Q0017
About this file
This is an Amendment of Solicitation/Modification of Contract (Standard Form 30, Amendment 0003) issued by the National Park Service, Southeast Region – North MABO (Maintenance Base Operations) located in Gatlinburg, Tennessee. The amendment is effective March 31, 2026, and applies to solicitation number 140P5326Q0017, originally dated March 31, 2026.
The amendment incorporates Government responses to vendor inquiries and issues a revised Statement of Work (SOW) reflecting clarifications and scope changes. Key modifications include: incorporation of official Questions and Answers addressing stone stacking foundations, stone cap requirements, bridge loading limitations, sandblasting restrictions, and concrete surface treatments (provided as attachment 140P5326Q0017 MACA Questions and Answers.docx); and a revised SOW (MACA_337611A_SOW.doc) that updates requirements for adhered stone veneer systems, substrate preparation, veneer materials, dowel installation, limestone cap installation for piers/columns, restricted load limits for bridge-mounted equipment, removal of full-surface sandblasting (limited to localized crack repair only), concrete sealer specifications, and enhanced detail on repair methods, quality control, submittal requirements, and continuous pedestrian access obligations. The amendment does not extend the proposal due date or modify evaluation factors. The period of performance is May 6, 2026, through October 28, 2026. All other terms and conditions remain unchanged.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: is not is required copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7.ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
PAGESOF
Contractor
The hour and date specified for receipt of Offers to sign this document and return
William Leady
See continuation page
NPS, SER - North MABO 107 Park Headquarters Road Gatlinburg TN 37738
PSN
140P5326Q0017
03/31/2026
03/31/2026
1 3
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
140P5326Q0017/0003
This amendment incorporates Government responses to vendor inquiries and issues a revised Statement of Work (SOW) reflecting clarifications and scope changes. The following changes are hereby made:
Incorporation of Questions and Answers:
The Government¿s official Questions and Answers dated with the solicitation are hereby incorporated. These include clarifications regarding stone stacking foundations, stone cap requirements, bridge loading limitations, sandblasting restrictions, and existing concrete surface treatments.
- Q&As are provided as Attachment:
140P5326Q0017 MACA Questions and Answers.docx.
Revised Statement of Work (SOW):
The SOW has been updated to incorporate the
Government¿s determinations and technical clarifications in response to vendor questions.
Revisions include, but are not limited to:
- Updated requirements for adhered stone veneer system, substrate preparation, veneer materials, and dowel installation.
- Inclusion of limestone cap installation specifications for piers/columns.
- Clarification of restricted load limits for bridge¿mounted construction equipment.
- Removal of full¿surface sandblasting from the scope; sandblasting limited only to localized crack repair areas.
- Clarification of concrete sealer requirements and existing surface conditions.
- Additional detail on repair methods, quality control, submittal requirements, and continuous pedestrian access obligations.
The revised SOW is issued as Attachment:
MACA_337611A_SOW.doc and fully replaces the previously issued SOW.
Continued...
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
140P5326Q0017/0003
No Changes to Due Date or Evaluation Criteria:
This amendment does not extend the proposal due date and does not modify evaluation factors unless otherwise stated in a subsequent amendment.
All Other Terms and Conditions Remain
Unchanged.
Period of Performance: 05/06/2026 to
10/28/2026
| Amendment of solicitation/modification of contract |
| Contract ID code |
| Amendment/modification number |
| Effective date |
| Requisition/purchase requisition number |
| Project number |
| Issued by |
| Code |
| Administered by |
| Code |
| Name and address of contractor |
| Code |
| Facility code |
| Amendment of solicitation number |
| Dated |
| Modification of contract/order number |
| Dated |
| This item only applies to amendments of solicitations |
| Accounting and appropriation data |
| This item applies only to modifications of contracts/orders. |
| This change order is issued pursuant to: |
| The above numbered contract/order is modified to reflect the administrative changes |
| This supplemental agreement is entered into pursuant to authority of: |
| Other |
| Important: |
| Description of amendment/modification |
| Name and title of signer |
| Contractor/offeror |
| Date signed |
| Name and title of contracting officer |
| Signature of Contracting Officer |
| Date signed |
| Previous edition unusable |
| Standard form 30 (rev. 11/2016) |
| Continuation sheet |
| Reference Number |
| Name of Offeror or Contractor |
| OPTIONAL FORM 336 (4-86)) |
Sponsored by GSA FAR (48 CFR) 53.110
File details come from the government source that posted it. Updated .