Sol_140P5123Q0035_Amd_0001.pdf

PDF 891 KB Posted

Attached to
REPLACE LOOSE/STAINED FLOOR COVERING-LS Federal contract opportunity
Solicitation number
140P5123Q0035
Issued by
Department of the Interior National Park Service Southeast Region

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

140P5123Q0035 x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

PSE

Atlanta GA 30303-8701 1924 Building 100 Alabama St., SW

NPS SER EAST MABO

PSE

Atlanta GA 30303-8701 1924 Building 100 Alabama St., SW

NPS SER EAST MABO

06/15/20230001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

06/02/2023

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The purpose of this amendment is to provide responses to questions received in response to the solicitation.

Questions and answers are provided as attachment 0006.

Period of Performance: 06/26/2023 to 08/25/2023

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Edward Dingle

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

Amendment 0001; RFQ #140P5123Q0035 Attachment 0006

Replace the Tile and Carpet Flooring in the Fort Sumter Liberty Square Education Center, Charleston, South

Carolina Solicitation # 140P5123Q0035

Questions and Answers

Question 1. Please provide additional information in specs or preference of carpet and tile size and color as well as preferred manufacturer or brand. Additionally, please advise who is responsible of moving office furniture and equipment to accommodate the removal and installation of the carpet. If contractor is responsible, please advise on where the furniture will have to be moved to.

Answer: The Park would like the contractor to provide quarry tile with matching durability, color, and size to be approved by Park official (tiles are estimated to be about 6" x 6"). Carpet tiles to match existing in durability and by size (2' x 2') and color to be similar or if other more suitable options available provide to Park official for approval. Moving furniture to and from the Parks provided storage location will be the responsibility of the contractor.

Question 2. Can the Government please confirm the magnitude of this construction project?

Answer: This requirement is considered a service under FAR Part 37 and advance disclosure of the magnitude of the project is not required.

Question 3. The Solicitation states that the Government wants the period of performance to start on 6/26/2023, which is the same date that bids are due and end on 8/25/2023. Page 8 of the solicitation then states the POP is 90 days after NTP. Can we assume that the latter is correct?

Answer: The period of performance shall be ninety (90) days after receipt notice of award.

Question 4. What year was the building built?

Answer: 2000 – 2001

Question 5. When was the last tile floor installed?

Answer: Current staff does not have any records of previous flooring installation.

Question 6. Can one entrance at a time be blocked off during installation of tile?

Answer: The park can make arrangements to block an entrance during installation.

Question 7. During the demo of tile, the tools make a good bit of noise. Would the customer want to close during that time?

Answer: It’s preferable that this work be performed during either oof or closed hours.

Question 8. There is tile popping loose directly over the storage room dividing wall. Can the contractor assume they must include this additional work needed here to firm up the subfloor once the tile is removed as a part of the bid?

Answer:

Question 9. Neither the scope nor the solicitation calls out specific materials/products to be used. Given the drastic change in price from product to product, can the Government please specify what product of carpet, tile, base, transitions, grout, and thin set it would like used? If not, can you please provide specifications for the required product?

Answer: The scope calls for materials that will be strong enough for the intended use and the Park would like to keep the look and color somewhat similar, however, during project formulation the existing tile was not found. The Park would like the contractor to provide options that would be best suitable.

Question 10. Will restrooms be accessible for contractor crew, or will we need to supply a porta potty?

Answer: Yes, restrooms will be available.

Question 11. The solicitation states the that the contractor must provide a project manager/site supervisor and that it cannot be a sub-contractor. Does the project manager/site supervisor need to be on site at all times?

Answer: Yes.

Question 12. 52.219-14, Limitations on Subcontracting (OCT 2022) ( 15 U.S.C. 637s) is an incorporated FAR Clause in this contract. Can you please confirm if the Government is considering this project to be ‘Construction’ or ‘Construction by Specialty Trade’?

Answer: This requirement is considered a service under FAR Part 37.

Question 13. Can you please confirm if there are any specific permits that must be pulled for this project?

Answer: There should not be any, however, it is up to the contractor to verify with any manufacturer or Architectural Barriers Act Standards.

Question 14. May we please receive clearer images of the floor plans so that we may see measurements clearer?

Answer: Photos are attached below.

Question 15. Will any security clearances be required for personnel on job site?

Answer: No, there is no security clearance is needed, however, the scope illustrates the expectations of employees on site of both contractors and subcontractors in section 13.

Question 16. Can you please provide a list of submittals that need to be submitted by the Contractor post award and throughout the project? (i.e., Safety Plan, Hazard Plan, Shop Drawings, MSDSs, etc.

Answer: The list of submittals can be found in the Scope of Work on Page 6 under the section titled Submittals/Transmittals.

Question 17. May the Contractor invoice for materials upon purchase and submission of purchase order? If not, may the Contractor invoice for materials upon arrival of materials to job site.

Answer: No, not for this requirement, the project must be satisfactorily completed prior to invoice submission.

Photos for question number 14 above

File details come from the government source that posted it. Updated .