SCOPE OF WORK (SOW)
Sagamore Hill National Historic Park – Visitor Center Building Demolition
I. Background and Purpose The visitor center at Sagamore Hill National Historic Site is a single story, structurally sound, wood framed structure. The visitor center was damaged by an electrical fire in January 2019. The building remains weather tight. Most of the fire damage is confined to one end of the building where the restrooms and mechanical room are located. The remainder of the building sustained heavy smoke damage. The government requires that the building be demolished and removed from the property. Existing utilities such as telephone, CCTV, fiber optic, waterline, parking lot lighting, underground fuel oil storage tank, and sanitary sewer will need to be terminated or have operation restored as described herein.
II. Scope and Objectives In general, the scope of this project is to secure the site for demolition, remove all asbestos containing cement board in the restrooms and mechanical spaces complete, remove florescent lights, demolish and remove the entire building from the site. A fiber optic cable, telephone line, electrical service for the parking lot lights, and cables for security cameras located in the parking lot will need to be preserved during demolition and in some cases, relocated in order to maintain service (see drawings sheet E-1 and E-2). Due to archeological sensitivity of the immediate area around the visitor center, the exterior foundation walls will remain in place with the exception that the first two rows of block will be removed. The demolition contractor shall backfill the crawl space with compacted clean soil/topsoil to match surrounding grade and for drainage before performing lawn operations.
III. Supporting Information The following attachments are included for this project:
1. Asbestos Inspection (38 pages)
2. Asbestos Supplemental Inspection Report (13 pages)
3. Lead Paint Inspection (9 pages)
4. Asbestos Abatement Air Monitoring (22 pages)
| 5. Drawings | Sheet | ||||
| a. Cover Sheet | G-1 | ||||
| b. General Notes and Details | G-2 | ||||
| c. Crawl Space Demolition | A-1 | ||||
| d. First Floor Demolition | A-2 | ||||
| e. Demolitions/Removals Electrical and Fiber Optic | E-1 | ||||
| f. Revisions Electrical and Fiber Optic | E-2 | ||||
| g. Site Demolition | S-1 | ||||
| h. Site Remediation | S-2 |
All equipment mobilized on-site shall be free of excess soil and/or plant material collected off-site which could potentially contain exotic/invasive species. All equipment leaving the site, not contained in a dump truck or dumpster, shall be free of asbestos containing material.
Labor practices, tools and equipment shall meet or exceed OSHA requirements. In case of conflicts between Federal, State, and local safety and health requirements, the most stringent shall apply.
Any discrepancies between the drawings and work listed here shall immediately be brought to the attention of the contracting officer in writing.
IV. Purchase Order Requirements, Deliverables, and Timeline The following tasks are included in this contract:
Task #1 – Deliverable: Structural Demolition
1. Partial removal of the building’s concrete block foundation.
2. Demolition and removal of visitor center structure:
a. Top two rows of foundation block and foundation piers.
b. Complete structure and contents above foundation.
c. Concrete pavement adjacent to the building.
d. All equipment, furniture, and appliances inside building.
e. Electrical, Plumbing, and HVAC systems.
3. Protection of existing fiber optic and telephone cables.
4. Protection of electrical to parking lot lights.
5. Protection of sanitary and water outside of building foundation.
6. Protection of existing site improvements
Task #2 – Deliverable: Selective Demolition
1. Demolition and removal top two rows of concrete block foundation.
Task #3 – Deliverable: Removal of Friable Asbestos Containing Material
1. Removal of friable asbestos containing materials (ACM). Demolition and removal of materials as required to support the work.
2. All labor, materials, facilities, equipment, services, employee training and testing, permits and agreements necessary to perform the work required for asbestos removal, clean-up, decontamination, and disposal and all work in accordance with the State of New York Department of Labor 12 NYCRR Part 56, U.S. Environmental Protection Agency (EPA), the Occupational Safety and Health (OSHA), and any other applicable federal, state, and local government regulations. Whenever there is a conflict or overlap of the above references, the most stringent provisions are applicable.
3. The work specified herein shall be performed by competent persons trained, knowledgeable and qualified in the state-of-the-art techniques of asbestos abatement, handling, and subsequent cleaning of contaminated areas.
4. Asbestos abatement and building demolition work will take place on federal government land and disposal of a federal government owned structure. Some permit fees may be waived by regulatory agencies. The contractor shall verify what fees may be waived by regulatory agencies. The contractor will pay all fees for permits.
5. Some formal notifications may not be required due to the project being a federally owned structure on federal government property. In place of a formal notification, the asbestos abatement contractor shall send a written notification to local, state, and federal agencies, as required, as a courtesy to those agencies.
Task #4 – Deliverable: Exterior Carpentry and Hardware
1. The scope of work is to provide and install 6 X 6 treated posts to support utilities to remain.
2. Wood products shall be produced from wood obtained from forests certified by an FSC-accredited certification body to comply with FSC STD-01-001, "FSC Principles and Criteria for Forest Stewardship".
3. Preservative Treatment by Pressure Process: AWPA U1; Use Category UC3b.
4. Species and Grade: Southern pine, pressure-preservative treated.
5. Provide anodized steel threaded rod, washers, and nuts as indicated on the drawings.
6. Galvanized or anodized hardware to securely fasten utility to posts.
7. Paint all exposed wood surfaces before installation.
8. Stacked 6 x 6s shall be connected with continuous threaded rods secured with a nut and washer on each end.
9. Nut and washer to be countersunk so no hardware projects out from the surface of the 6 x 6s.
10. Install appropriate hardware and/or fasteners to support utility.
11. Posts shall be set in compacted backfill immediately adjacent to utilities to be supported.
a. Type and location of support.
i. Triple Post Support – To support new parking lot lighting panel.
ii. Single Post Support – To support heating oil tank vent pipe.
Task #5 – Deliverable: Painting
1. The work of this section consists of preparing surfaces, priming, painting and finishing work of support posts.
2. Remove dust by brushing and remove grease and oil by washing with mineral spirits or other solvent. Remove sap on wood surfaces by scraping and washing with turpentine.
3. Apply finish material when temperature is 50 degrees F or above. Do not apply exterior materials in damp, rainy weather. Do not apply paint on surfaces in direct sunlight, especially when the air and surface temperature get to or above 90 degrees F. level. Apply finishes only when air is free of dust that would speck the finish.
4. Measure moisture content of surfaces using an electronic moisture meter. Do not apply finishes unless moisture content of surfaces are below following maximums:
a. Exterior Wood: 18 percent
5. High quality standard brand. Provide primers produced by same manufacturer as finish coats. Paint products shall be fresh and well ground; shall not settle readily, cake, or thicken in the container; shall be broken up readily with paddle to a smooth consistency; and shall Color to be Oxford Brown, as approved by CO.
6. Paint posts prior to installation. Color to be Oxford Brown as approved by CO.
have easy application properties.
7. The prime coat must be brushed on to allow the coating to penetrate and adhere to the surface. Brushing the finish coat is the required method of application.
8. Stir the paint before applying. Use a one-inch wide paddle. Stir paint while in use on the job to insure uniformity. Do not thin finished coat.
9. Do not use fast drying paint.
10. Do not paint over dirt, rust, scale, grease, moisture, voids and blemishes, or other conditions detrimental to formation of a durable paint film.
11. Apply paint in accordance with manufacturer's directions. Use techniques best suited for substrate and type of material being applied.
12. Secure approval of each coat before proceeding with the next.
13. Apply material evenly without runs, sags, or other defects. Leave moldings, trim, ornaments, edges, and millwork clean and true to details without excess paint in corners or depressions.
14. Apply materials at not less than manufacturer's recommended spreading rate, to establish a total dry film thickness as recommended by the manufacturer.
15. Drying Time: Minimum time recommended by manufacturer. Do not apply succeeding coats until the undercoat is thoroughly dry.
Task #6 – Deliverable: Plumbing
1. Sanitary Sewer
a. Remove all sanitary piping in building up to the foundation wall to remain. Cap end of sanitary pipe where it penetrates the wall. Do not remove any pipe outside of foundation wall.
2. Fuel Oil Lines from Underground Tank
a. Remove all fuel oil piping in building up to foundation wall to remain. Cap end of pipe at the first joint after it penetrates the wall into the crawl space. Do not remove any pipe outside the foundation wall.
b. Protect existing vent pipe for the fuel oil tank. Install support post to secure vent pipe.
3. Waterline
a. Remove all waterline piping in building up to foundation wall to remain. At the location of the first shut off valve after the waterline enters the crawl space, install a copper tee. Off the copper tee fitting install a drain ball valve on one leg and connect the other leg to the yard hydrant as per the manufacturer’s specifications. Install underground utility box to access valves.
4. Oil sludge
a. An estimated 3 gallons of heating oil remains in the tank. Demolition contractor to dump a sufficient quantity of oil absorbent to soak up fuel oil directly into the tank and resecure the lid.
b. All oil must be removed and disposed of prior to dumping oil absorbent to soak up residual fuel oil.
5. Fittings for plumbing work:
a. Copper pipe and fittings shall be Type “L”.
b. Ball valves shall be full port with packing nut.
c. Underground utility box shall be injection molded HDPE with green or black top, designed for underground use, for non-vehicular traffic areas, height of box to match depth of utility.
d. Black iron screw caps shall be malleable steel.
e. DWV caps shall be flexible PVC designed for underground use. The caps must be applicable for cast-iron, plastic, copper, or steel pipe. They shall include a stainless-steel strap/clamp.
f. Support brackets shall be galvanized or anodized to resist erosion.
g. Oil absorbent to be USDA bio preferred certified, 100% organic, silica free, and meets EPA leachate standards.
Task #7 – Deliverable: Electrical
1. As specified and as shown, furnish, install, test, and place in satisfactory and successful operation all equipment, materials, devices, and necessary appurtenances to provide a complete and operable electrical system. Electrical work also includes wiring and connections required for electrical equipment furnished under other divisions.
2. Electrical drawings do not attempt to show complete details of building construction that affect installation. Diagrams are schematic only and do not necessarily show physical arrangement of equipment. Refer to drawings of other trades for additional details which affect work.
3. Conduit, conductor and ground connections are shown diagrammatically only. Layout does not necessarily show total number of conduits or conductors for circuits required and should not be used for obtaining quantities for linear runs of conduits or wires. Locations of indicated runs are not intended to show actual routing of conduits. Provide additional conduits and wire wherever needed to complete installation of specific equipment furnished.
4. Locations of outlets on drawings are approximate and may be distorted for clarity in representation.
5. Install electrical outlets and other equipment clear of and in proper relation to radiators, ducts, grilles, pipes, and other equipment, and items such as cabinets and counters.
6. Changes such as offsetting conduit runs, moving outlets, or other minor changes necessary to facilitate installation shall be made at no additional expense to the Government.
7. The work of this contract consists of providing all labor, materials, tools, equipment and services necessary for the electrical renovations, alterations and modifications of the systems including, but not necessarily limited to, the following:
a. Provide new, load center in new weatherproof enclosure.
b. Provide new surge suppression device at new load center.
c. Provide two, new 125V, 20A GFCI, duplex receptacles adjacent to load center.
8. Work shall be completed as shown on the Drawings, as specified herein, and as required by job conditions.
9. Workers Qualifications
a. Worker's Qualifications: All electrical work shall be performed by licensed electricians or under the direct supervision of a licensed electrician.
10. Codes and Regulations
a. All work shall meet requirements of governing codes and regulations, NFPA 70, latest edition.
b. Advise the Contracting Officer of conflicting codes or conflicts between codes and drawings and specifications.
c. When the requirements of specifications or drawings are more stringent than the codes, regulations, or standards, the specifications or drawings shall prevail.
d. The electrical installation shall meet the requirements of NECA Standard of Installation, except where otherwise specified.
11. UL Listing
a. All electrical materials and equipment shall meet requirements of the applicable standards of UL if UL standards exist for such materials and equipment.
b. The UL authorized listing mark is acceptable as evidence that the materials meet this requirement.
c. In lieu of UL authorized listing mark, the Contractor may submit independent proof satisfactory to the Contracting Officer that the materials meet the standards.
d. Materials and equipment shall be installed only for their intended operational purpose.
12. Standard Products
a. Standard Products: Provide only new electrical equipment of current standard design.
13. Finished Surfaces
a. Finished surfaces of existing facilities that are marred, scratched, or damaged shall be refinished to match original condition.
b. Building surfaces that have been altered for the proper installation of electrical equipment shall be restored by skilled personnel of the trades involved at no additional expense to the Government.
c. Polychlorinated Biphenyl (PCB): Equipment containing PCB is not acceptable.
14. Inspections and Testing
a. Demonstrate that electrical work operates satisfactorily and in accordance with the requirements of the drawings and specifications. Before final inspection, remove the front covers on all panelboards and wire gutters. Replace covers after the final inspection is completed.
b. Make all specified tests in the presence of the Contracting Officer’s Representative or other authorized representative.
c. Furnish all instruments and provide qualified personnel to perform all tests in accordance with the drawings and specifications.
d. Perform all tests at no additional expense to the Government.
e. Operate all electrical equipment within the ranges specified by manufacturer.
f. Correct defects revealed by the tests.
g. Balance Test: Test for proper load balance on the system and make adjustments as required.
h. Conductors: Prior to energizing and circuitry, test installed wires and cables to ensure that insulation resistance levels are adequate, test wires and cables for electrical continuity and for short-circuits.
i. Wiring devices: Ensure proper polarity of connections. Prior to energizing the system, test wiring devices in accordance with manufacturer's recommendations.
j. Panelboards and Load Centers.
k. Prior to energizing of circuitry, check all accessible connections to manufacturer's torque tightening specifications.
l. Prior to energizing of panelboards or load centers, check phase-to-phase and phase-to-ground insulation resistance with ground resistance tester.
15. Existing Equipment and Wiring
a. Surface Wiring Systems to be abandoned: Remove conduit, wire, boxes, and other components to nearest outlet, device, or panelboard that is to remain in use.
b. Concealed Wiring Systems to be abandoned: Remove wire, devices, and other components to nearest outlet, device, or panelboard that is to remain in use. Install blank faceplates on abandoned outlet boxes.
c. Modify existing electrical installation as required by new construction. Provide necessary conduit system, wire, and connections for a complete and operable system.
d. Removing existing equipment: Existing equipment specified to be removed becomes property of Contractor and shall be removed from site, unless otherwise specified.
16. Raceways and Fittings
a. Rigid galvanized steel conduit (RGC), UL 693
b. Electrical metallic tubing, (EMT), UL 79793
c. Flexible nonmetallic tubing (ENT), UL 394
d. Flexible metal conduit (FC), UL 193
e. Liquidtight flexible steel conduit (LTFC), UL 36094
f. Surface metal raceway and fittings, UL 590
g. Wireways, auxiliary gutters, and associated fittings, UL 87091
h. Busways and associated fittings, ANSI/UL 85790
i. Cellular metal floor raceways and fittings, ANSI/UL 20992
j. Aluminum conduit, UL 693
k. Impregnated fiber conduit (heavy or thin wall), UL 54387
l. Schedule 40 and Schedule 80 rigid PVC conduit, UL 65193
m. Intermediate metal conduit (IMC), UL 124293
17. Color Coding
a. The secondary service and branch circuit conductors shall have the color insulation identified below:
i. Color code for single phase 120/240 volts ac:
| 1. Phase A: | Black |
| 2. Phase B: | Red |
| 3. Neutral: | White |
| 4. Ground: | Green |
ii. Color code for three phase 120/208 volts ac:
| 1. Phase A: | Black |
| 2. Phase B: | Red |
| 3. Phase C: | Blue |
| 4. Neutral: | White |
| 5. Ground: | Green |
iii. Color code for three phase 277/480 volts ac:
| 1. Phase A: | Brown |
| 2. Phase B: | Orange |
| 3. Phase C: | Yellow |
| 4. Neutral: | Grey |
| 5. Ground: | Green or Green with Yellow Stripe |
18. Branch and Feeder Circuits
a. Copper Conductors: Comply with NEMA WC 70/ICEA S-95-658. Conductors shall be solid for No. 10 AWG and smaller, stranded for No. 8 AWG and larger.
b. Conductor Insulation: Comply with NEMA WC 70/ICEA S-95-658 for Type THHN-2-THWN-2.
c. Multi-conductor Cable: Comply with NEMA WC 70/ICEA S-95-658 for metal-clad cable, Type MC with ground wire.
d. Minimum size shall be No. 12 AWG and otherwise meet requirements of NFPA 70, latest edition, or the sizes indicated in the specifications or drawings, whichever is larger.
e. Conductors shall be copper.
f. Copper clad and aluminum conductors are not acceptable.
g. Control Wire: No. 12 AWG copper conductor; 600volt rated insulation.
19. Outlet, Pull, and Junction Boxes
a. General: Provide one for each outlet, switch, receptacle, or combination, and each junction point. Boxes shall be as follows:
i. Metal Raceway Systems in Interior Dry Locations: Galvanized sheet metal.
ii. Outdoor and Wet Locations: Weatherproof, cast metal, threaded hub.
iii. Subject to Constant Moisture: Watertight.
20. Wiring Devices
a. Receptacles: UL 49891 and NEMA WD183. Terminals shall be suitable for copper conductors.
i. Duplex Receptacles: Thermosetting plastic, NEMA heavy duty 515R and 520R configurations, Specification grade with Ushaped grounding pole and a greencolored terminal for connection of a bonding jumper. Color shall be as approved by the Government.
ii. Ground Fault Circuit Interrupter Receptacle (GFCI): Duplex 20ampere with NEMA 520R configuration, UL 94395, Class A, Specification grade. Receptacle shall have builtin surge and load noise suppression, with feedthrough capability to protect branch circuit beyond GFCI receptacle against ground fault, and test and reset buttons. Indicator light shall glow only when tripped. Color shall be as approved by the Government.
21. Panel Boards
a. Panelboard shall be designed, manufactured, and tested to comply with the following standards
i. UL 67 – Standard for Panelboards
ii. UL 50 – Enclosures for Electrical Equipment
iii. NEMA PB 1 – Panelboards
iv. NFPA 70 – National Electrical Code
v. Federal Specification W-P-115C Type I Class 1 – Circuit Breaker Panelboards
vi. NFPA 5000, ASCE/SE17 Seismic Qualification.
b. Enclosures and Bus: As shown on the panelboard schedule. Complete with protective devices and enclosures, copper buses, ground and neutral bars, front covers with door and builtin lock. Protective devices shall be removable without disturbing adjacent units. Flush mounted panelboards shall have adjustable fronts with concealed trim clamps. Subpanel neutrals shall be insulated from their enclosures and grounds. Panelboards used as service entrance shall be UL listed as suitable for service entrance equipment.
c. Circuit Breakers: Thermalmagnetic, multipole breakers shall automatically open all poles when an overload occurs in any pole. External tiehandle construction where adjacent poles are on the same phase or leg will not be accepted. Tandem breakers are not acceptable. Branch circuit breakers used for switching duty shall be UL listed as SWD type. Ground fault circuit interrupter protection as required by NEC shall be provided by ground fault circuit interrupting breakers. Main breaker shall be 22,000AIR symmetrical at 240 volts ac. Branch circuit breakers shall have a minimum interrupting rating of 10,000 AIR symmetrical at 240 volts.
22. Load Centers
a. Load centers shall be UL Listed and designed, manufactured, and tested to comply with the following standards:
i. File E-6294
ii. Federal Specification W-P-115c, Type 1, Class 2
iii. Suitable for use as service entrance
iv. 75°C wire rating.
b. Short Circuit Current Rating: Main Circuit Breaker: 22,000 AIR
c. Interior:
i. Shielded, one-piece tin-plated copper bus
ii. Removable interior with single, captive mounting screw
iii. Split branch neutral
iv. Multiple mounting locations for equipment grounding bar: left, right and bottom.
23. Transient Voltage Protection Varistor
a. Suitable for use on system voltages up to 130 volts RMS. Rated transient energy for a 10x1000 microsecond pulse shall be a minimum of 50 joules. Peak rated current for an 8x20 microsecond pulse shall be 6,000 amperes. Maximum clamping voltage at 100 ampere 8x20 microsecond test pulse shall be 325 volts.
24. Grounding
a. The grounding electrode conductor shall be stranded copper.
b. The grounding rod shall be 5/8” diameter by 8-feet long driven vertically to a depth of ten feet (10’).
c. Grounding electrode conductor shall be connected to the ground rod using a clamp suitable for direct burial in the earth or be an exothermal weld.
Task 8 – Deliverable: Fiber Optic Backbone
1. Work required for the alterations and modifications to the existing fiber optic backbone cabling:
a. Splicing, terminations, testing, labeling and documentation of alterations and modifications to the existing fiber optic cable system between buildings as specified and on the drawings.
b. The installation environment includes tie in and coordination with existing optical fiber and copper facilities, underground duct banks, direct-buried conduit.
c. The Contractor shall be responsible for: placement of cable, furnishing and attachment of cable to support devices, underground structures, the placement of conduit, the installation of pull-boxes, the furnishings of fiber optic splice closures, and installation of termination hardware for a fully operable and operating system.
d. Contractor shall be responsible for providing and installing grounding and bonding materials, duct plugs, and fire stopping materials as required completing the installation.
e. Other incidental hardware and appliances, necessary for the proper performance and operation of the communication cable system, which are consistent with the practices of cable installation, are to be provided by the Contractor as required to complete the installation.
f. Contractor is responsible to ensure that utility locating has been performed as per the requirements of state and local requirements. The Contractor is responsible for any damages to any utility caused during construction. In any area where a utility has been located, work activity must be verified through pot holing.
2. Standards and Practices per NFPA 70 (National Electrical Code), state and local codes, requirements of authorities having jurisdiction and the following:
a. BICSI TDM, Current Edition.
b. ANSI/TIA-568-C.0, Generic Telecommunications Cabling for Customer Premises.
c. ANSI/TIN568-C.1, Commercial Building Telecommunications Cabling Standard.
d. ANSI/TIA/568-C.2, Copper Cabling Components Standard.
e. ANSUTIA/568-C.3, Optical Fiber Cabling Components Standard.
f. ANSI/TIA/EIA-569-B„ Commercial Building Standard for Telecommunications Pathways and Spaces.
g. ANSITTIA/E1A-606-A, Administration Standard for the Telecommunications Infrastructure of Commercial Buildings.
h. ANSI/J-STD-607-A, Commercial Building Grounding (Earthing) and Bonding Requirements for Telecommunications The Contractor is responsible to determine and adhere to the most recent edition of these standards when developing their responses and completing the project installation.
3. Optical Fiber Backbone System Description
a. Optical Fibers in the backbone shall be terminated using a pigtailed assembly that have incorporated into those assemblies a LC connector that is fusion spliced to the backbone optical fibers, unless otherwise specified and approved by the government; housed in rack-mount fiber optic enclosures with cable supports.
b. All cables and termination hardware shall be 100% tested for defects in installation and to verify cable performance under installed conditions. All conductors and fibers of each installed cable shall be verified useable prior to system acceptance. Any defect in the cabling system installation including but not limited to cable, connectors, feed-through couplers, patch panels, and connector blocks shall be repaired or replaced at the providers expense in order to ensure 100% useable conductors in all installed cables.
4. Products
a. The materials and products specified herein reflect the minimum acceptable standards of fabrication and manufacture.
b. All materials and products supplied by the Contractor and specified herein are to be new, unused, of first quality and in original packaging or shipping containers.
c. Provide materials as specified or as approved equivalent by the government.
d. Match optical fiber glass for tie in to existing optical fibers.
e. The following manufacturer's warranted systems are approved unless otherwise specified:
i. AMP
ii. Belden
iii. Berk-Tek
iv. CommScope
v. Corning
vi. Ortronics
vii. Siemons
5. Substitutions
a. All substitutions shall be submitted to and approved by the government in writing.
b. Acceptance of substitutions is at the government discretion. The government reserves the right to determine suitability of the substitute product and reject any and all materials submitted for substitution. Submit requests for substitutions in writing to the Contract Officer and Contracting Officer’s Representative for approval within ten (10) days of contract award, or sooner if required to maintain the schedule.
c. Products rejected or otherwise judged unsatisfactory by the government will not be authorized for use in completing the work. Any unapproved products discovered as part of the installation will be removed and replaced with the government specified and approved products at the Contractor's expense.
d. Project Drawings may be based on equipment configuration of a particular manufacturer. If a substitution is approved, the Contractor shall make changes needed to accommodate the substitution at no expense to the University of New Mexico, including work under other divisions.
6. Outside Fiber Optic Cable
a. Single mode fiber is the standard optical fiber media for backbone installations and optical fibers shall be low water-peak, laser optimized, suitable for CVVDM use and complies with the ITU G.562.c/d. standard.
b. The cable types installed shall match the existing fiber optic cables in all respects. It is the Contractor's responsibility to verify and submit an RFI on cables that do not meet code or the environmental requirements of the project, environmental or code requirements of the installation before purchasing or providing.
c. When splicing into existing optical fibers the Contractor is to ensure the matching of optical fiber glass to the new and existing fibers and install the same glass type and manufacturer to prevent optical fiber mismatch.
d. Single Mode Optical Fiber Specification
i. Optical Characteristics — Single-mode fiber optic cable 8.3pm/125pm single-mode low water peak optical fibers.
ii. Attenuation: 0.35dB/km @ 1310 nm; 0.25dB/km @ 1550 nm
e. Multi-Mode Optical Fiber—When Specified by the government only.
i. Install Multi Mode optical fiber when approved and specified by the Owner.
1. Optical Characteristics — 0M3 50pm/125pm laser optimized fibers, for new installations.
2. Optical Characteristics — 0M1 62.5pm/125pm multimode optical fibers as specified for additions and modifications to existing of the same optical fiber.
f. Mechanical Construction — Armored fiber optic cable for direct-buried and conduit installation. Construction shall include: locatable central strength member or an IT approved equivalent, water swell-able yarn, buffer tubes/fibers, water swell-able tape, ripcord, polyethylene inner jacket, high tensile strength, corrugated steel tape armor (for direct buried applications), Polyethylene outer jacket, UV-stabilized jacket or equivalent. Install interlock optical fiber when specified by the manufacture.
g. Install orange interlock optical fiber for building backbone distribution.
h. Provide optical fiber color codes in compliance with Color TIA/EIA 527-7 and 14.
i. Cable shall be assembled to ensure that no more than 12 fiber strands occupy each buffer tube of like fiber strands.
7. Fiber Optic Connectors
a. Provide for all new fiber optic installations with fusion spliced LC pig tail connectors. The connectors shall be manufactured by the cabling system manufacturer and composed of the same optical fiber glass as used in the optical fiber cable specified by the project.
b. When adding to or modifying existing work coordinate connector type with THE GOVERNMENT.
c. Multimode connectors, when specified shall be LC pigtailed connectors. They shall all be fusion spliced unless otherwise specified by the government.
i. Use color code of the existing fiber optic cables.
8. Fiber Optic Enclosures
a. Wall mounted enclosures shall be approved by the government prior to system design and installation. RFI submittal is required. The enclosure shall be equipped for a fusion spliced pigtail connector installation.
b. Provide wire management approved by the government to equipment and interconnection enclosures.
c. Rack Mount enclosures shall be approved by the government prior to system design and installation. RFI submittal is required. The enclosure shall be equipped for pigtail connector splicing and installation.
d. Provide one 2RU wire manager, installed per rack at the top and one 2RU wire manager installed in the middle of the rack coordinated with the FDU installation to provide a crossover pathway for optical fiber jumpers.
e. Provide blank 2RU panel install below the top wire manager.
9. Optical Fiber Splice Closures
a. All splice closures shall be approved by the government prior to installation. An RFI submittal to the government is required for all optical fiber splice closures.
b. Provide splice enclosures that are rated for the environment they are to be installed.
c. All closures shall be pressure tested. No encapsulate shall be used on fiber enclosures.
d. Provide Preformed Coyote Fiber Optic Splice Closures Kits or other approved by the government that are sized as required for the maximum fiber count within the splice case including distribution fibers.
e. Install only the splice enclosure manufacturer's specified splice trays. Splice only 12 fibers per splice tray (no exceptions, unless with written approval prior to installation from the government project manager).
f. Splice trays shall be labeled with a permanent label on the front face of each splice tray indicating fiber count.
g. Support all closures with manufacturer’s approved brackets.
10. Labels
a. Plastic cable labels shall be mechanically printed and shall be attached to all fiber optic cables using black UV rated cable ties or stainless-steel cable ties within six (6) inches of the splice closure and six (6) from all ducts and sleeves.
b. Provide electronically printed, waterproof, self-adhesive, laminated labels installable on the external surface of the outside panel of all FDU's and closures.
11. Optical Fiber Backbone Installation
a. General
i. This item describes the installation for the products and materials, as well as methods and the Standards associated with the optical fiber backbone installation. These specifications, along with the drawings and other supplied specifications shall be provided during the course of the installation.
ii. The Contractor is instructed to coordinate his efforts with other trades who may be working within the same vicinity to avoid conflicts, lost time, cleaned environment for splicing and termination and potential injury. The government will assist in contractor coordination as requested or as required.
iii. The Contractor shall install all materials plumb, square and in a workman-like manner.
iv. The Contractor shall supply all necessary tools, equipment, accessories, safety equipment, protective clothing, etc., as customary for the craft and necessary for the installation.
v. The Contractor shall verify space requirements and locations with the project team and the government before starting cable installations and terminations proceed.
vi. The Contractor shall verify the cable type and jacket rating required for.
vii. The Contractor shall verify existing cable fill in conduit, raceway or cable tray system prior to quote or bid and before installation of additional cables so as not to exceed 40% cable fill. Contractor will be responsible for installation of additional conduit, raceway or cable tray where additional cables to be added will exceed the 40% cable fill.
viii. The Contractor shall comply with all national, state of New York and local codes.
ix. Should any portion of these specifications conflict with applicable codes, the Contractor shall cease work on that particular aspect of the project and notify the government immediately.
x. All equipment shall be installed in a neat and professional manner, arranged for convenient operation, testing and future maintenance.
xi. All fiber cables shall be installed, and terminated/fusion spliced by technicians trained and experienced in the installation and termination of fiber cables.
xii. The Contractor shall employ certified system installation technicians and have at least five (5) years’ experience in the installation of similar and equivalent systems.
xiii. The Contractor shall supply verification of experience, for this type of work, to the COR for approval before performing any work.
b. Field Conditions:
i. The Contractor shall verify fixed facility locations shown on the drawings are based upon the latest design information available at the time this specification was prepared.
c. Splicing & Termination
i. The contractor is responsible to ensure that all outages associated with active cable and equipment is coordinated and approved by the government.
ii. Fusion splice optical fibers in accordance to the approved fusion splicer, optical fiber and enclosure manufacturer's methods, procedures and instructions to ensure warranty compliance.
iii. All optical fiber shall be neatly and efficiently dressed into splice tray management and the contractor is to ensure that splices are accessible without damage to the optical fibers or splices.
iv. The contractor is to ensure that all splice trays are labeled and properly optical fibers trays secured.
v. The contractor shall test and call for splice inspections of all optical fiber splices before closing cable splice enclosures.
12. Optical Fiber Testing
a. Scope of Work
i. The Contractor shall furnish labor, equipment and supplies unless otherwise specified, in performing the following operations recognized as necessary for the successful testing and verification of the installation of the Fiber Optic cable plant described on the drawings and required by these specifications.
ii. Notify the government 48 hours in advance when work, technicians and equipment are prepared for acceptance tests and inspections. Coordinate a meeting with the government’s personnel to discuss the required testing procedures, required performance, test equipment, documentation, etc. to verify to the government a complete understanding of project requirements.
iii. Provide technicians are trained and certified in the use of the test equipment used for the testing operations associated with the specified work.
iv. Maintain test equipment to manufacturers' requirements and ensure that all equipment is calibrated according to the manufacturer's requirements. Provide a copy of the current calibration certificate associated with all test equipment associated with the contracted work.
b. Testing
i. Verify through visual inspection using an optical fiber test scope all fiber optic cable terminations, splices and connecting cables for defects and cleanness.
ii. The fiber optic cables shall be tested utilizing a power meter and stabilized light source capable of testing at 850 nm and 1300 nm for multimode and 1310nm and 1550nm for single mode. Contractor shall complete a fiber optic post installation report at the time of testing containing meter readings at both 850 nm and 1300 nm for multimode and 1310nm and 1550nm for single-mode in one direction (TR to outlet) on each fiber, actual loss and other pertinent data regarding the cables tested, including model and serial number of test equipment, cable part #, installed fiber length, building span loss at 850 nm and 1300 nm for multimode and 1310nrn and 1550nm for single-mode and date tested. Testing required is 100%.
Task 9 – Deliverable: Earthwork
1. Materials shall comply with the following New York State Department of Transportation (NYSDOT) Construction Specifications (Latest Edition):
a. Section 206 – Embankment
2. Site requirements are as follows:
a. Control the grading so that ground is pitched to prevent water from running to excavated areas, damaging other structures, or adjacent properties.
b. Where soil has been softened or eroded by flooding, equipment, traffic, or placement during unfavorable weather, or such other conditions, it shall be removed and replaced by the Contractor with suitable material, and at no cost to the Government.
c. Exercise care to preserve the material below and beyond the lines of excavation. Where excavation is carried out below indicated grade or beyond the lines of excavation, Contractor shall backfill and compact the over excavation with structural fill to the indicated grade, at no additional cost to the Government.
d. Limits of excavation are such that all unsuitable material shall be removed to firm natural ground in the manner specified below.
e. Unsuitable materials which are classified as organics such as peat, trash, fill, roots, debris, and topsoil and subsoil when determined by CO to be unacceptable for incorporation into the work.
f. All suitable material, as determined by the CO, may be reused on the site provided it meets the gradation requirements for the given materials in the information of embankments, subgrades, backfills, topsoil, etc.
3. Backfilling
a. Dewater subgrade areas prior to filling.
b. Soil fill moisture shall be maintained at an acceptable working range to allow for proper compaction.
c. Do not place fill on frozen ground.
d. Do not place frozen fill.
e. Place fill in uniform horizontal layers and compact immediately after placement.
f. To the extent that is practical, each layer of fill shall be compacted to the specific density the same day it is placed.
g. Protect utilities from damage during backfilling operations. Repair damage at no cost to Government.
h. Placement of fill shall not begin prior to observation and approval of subgrade conditions by CO.
i. Upon completion of the work, the final ground surface shall be left in a firm, unyielding, true, uniform condition free from ruts. Repair disturbed areas caused equipment traffic at no cost to the Government.
j. Compaction equipment for fill shall be accomplished by means of drum-type, power-driven, hand-guided vibratory compactors operating at 2,000 cycles per minute, or by hand-guided vibratory plate tampers.
k. Any additional fill needed for this project is the responsibility of the contractor.
l. Fill sections and embankments shall be constructed of earth, or granular fill deposited in successive lifts.
m. During fill and embankment construction operations, earth moving equipment shall be routed as evenly as possible over the entire width of the work.
n. At the close of each day’s work the working surface shall be crowned, shaped, and rolled with smooth steel or pneumatic tired rollers to ensure proper drainage.
Task 10 – Deliverable: Post Hydrant
1. Post Hydrant; Outdoor freeze resistant. Finish to be powder coated gloss black.
a. Basis-of-Design Product: Antique historic style constructed of round heavy duty cast iron or aluminum. Pattern to contain vertical fluted design.
b. Standards:
i. Comply with NSF 61 and NSF 372.
ii. Comply with ICC A117.1.
c. Non-freezing and self-draining to the french drain beneath the unit.
d. Cast iron head and cap, cast iron casing guard, a stainless-steel exterior casing pipe, a stainless steel non-turning interior operating rod, and bronze valve body.
e. Operation of unit by turning a 4-spoke ball wheel operating handle held in place by a square operating nut.
f. Drain outlet must seal in all positions from 1/4 closed to fully open.
g. All working parts shall be removable from the ground with no digging required.
h. Water supply inlet ¾”. Outlet ¾” with standard garden hose threads
i. Bury Depth, Grade to Valve Components: 42-inch adjustable depth.
Task 11 – Deliverable: Topsoil, Seeding, Fertilizing, Mulching
1. Topsoil: Class B topsoil from sources outside the project limits and shall be the original top layer of a soil profile formed under natural conditions, technically defined as the “A” horizon or as defined by USDA-NCRS Soil Survey Division. It shall consist of natural, friable, loamy soil without admixtures of subsoil or other foreign materials and shall be free of viable noxious weed seed, brush, litter and rocks greater than 1” in any dimension. The allowable pH range for Class B topsoil shall be 5.5 to 7.0. Class B topsoil shall be a “sandy loam,” “loamy sand,” or “sandy clay loam” soil as defined by the USDA Soil Textural Classification System with an organic matter content between 1 and 8 percent or as approved by the CO. The soil shall be clean topsoil and free of contaminants.
2. Slow-Release Fertilizer: Granular or pelleted fertilizer consisting of 50 percent water-insoluble nitrogen. Fertilizer shall be a complete, standard product complying with state and federal fertilizer laws. The fertilizer shall be uniform in composition, dry and free flowing, and shall be delivered to the site in the original, unopened containers, each bearing the manufacturer's guaranteed analysis, and submitted to the CO for approval.
a. Fertilizer shall contain the following minimum percentage of available plant food by weight: 10% nitrogen, 10% phosphorus, 10% potash, in which 75% of the nitrogenous elements shall be derived from organic sources or urea form.
b. Exact percentages of fertilizer may vary in accordance with the soil test report.
c. Any fertilizer that becomes caked or otherwise damaged (making it unsuitable for use) will be rejected.
3. Certified seed will be used for all permanent seeding whenever possible. Certified seed is inspected by the certifying agency in New York. The seed must meet published state standards and bear an official “Certified Seed”.
4. Selection of turf seeds is based on climate, topography, soils, land use, and planting season.
5. Appropriate seeding mixtures for various site conditions.
6. If hydroseeding, the Contractor shall submit a certified statement as to number of lbs. of fertilizer, amounts and types of grass seed, and processed fiber, per 100 gallons of water.
7. If applying straw mulch, provide air-dry, clean, mildew- and seed-free, salt hay or threshed straw of wheat, rye, oats, or barley.
8. Installation shall comply with Division 610 – Turf and Wildflowers in the New York Department of Transportation Standards and Specifications.
Deliverables Deliverables shall be reviewed and either approved or disapproved five (5) days after receipt.
1. Work Schedule – this is to ensure adequate planning, coordination, scheduling, and reporting during the execution of the work. This will be reviewed weekly during the progress meetings.
2. Photographs – Photos shall be taken prior to, during and after completion of the work outlined in the SOW. Photos shall be delivered to the COR on a CD-R and be labeled as SAHI Visitor Center Demolition. Images shall be in either a JPEG or PDF format on the disks. These digital images will use the maximum range of depth of field and must be in focus to clearly show work. Out of focus or blurry images will not be accepted.
a. Existing condition images – to be delivered one (1) week after kickoff meeting. These images shall be taken from multiple vantage points. The Contractor shall take as many as are reasonably necessary to document the work so that it can be understood by a reviewer who does not have physical access to the site. The Contractor shall document the existing condition of roads at access points prior to beginning work as well as flag excavation areas before recording these images.
b. Periodic images during work – to be delivered weekly. The Contractor shall take a sufficient number of color, digital images as reasonably necessary to document work so that it could be understood by a viewer who does not have physical access to the site. The Contractor shall select vantage points to show the progress of the work since the last images were taken.
c. After images – to be delivered one (1) week after work ends. The Contractor shall take images from multiple vantage points and take as many as are reasonably necessary to document the work so that it can be understood by a reviewer who doesn’t have physical access to the site.
d. Additional images – the CO may issue requests for additional images, in addition to those mentioned above. Three (3) days’ notice will be given if possible. In emergency situations, the Contractor shall take images within 24 hours of the request. Examples of situations requiring additional images include, but are not limited to, immediate follow-up when onsite events result in damage or losses, substantial completion of a portion of the work, and extra record images at the time of acceptance.
Submittals The following submittals shall be submitted to the CO and COR no less than one (1) week prior to the kickoff meeting:
1. Designation of Project Supervisor
2. Proposed work schedule
3. Accident prevention plan
4. Waste management plan The submittal for structural demolition shall be provided to the COR no later than five (5) days prior to the demo work and shall include:
1. Qualification Data: For qualified refrigerant recovery technician.
2. Proposed Protection Measures: Submit an informational report, including drawings, that indicates the measures proposed for protecting individuals and property, for environmental protection, and for dust control. Indicate proposed locations and construction of barriers.
a. Adjacent Building: Detail special measures proposed to protect adjacent buildings to remain.
b. Native Plant garden: Detail special measures proposed to protect plants from soil compaction and accumulation of debris.
c. Adjacent site improvements including curbs, parking lot pavement, chip seal walks, turf, underground utility boxes, and light poles.
d. Fiber optic line, telephone cable, CCTV cable, electric service to parking lot lights.
3. Detailed sequence of demolition work, with starting and ending dates for each activity.
4. Capping of utility services.
The submittal for removal of asbestos containing material work shall include the following and be submitted to the COR five (5) days prior to work beginning for approval:
1. Documentation as per New York State Department of Labor 12 NYCRR Part 56 and Section 02 82 00 Removal of Friable Asbestos Containing Materials.
The submittal for exterior finished carpentry work shall include the following and be submitted to the COR five (5) days prior to work beginning for approval:
1. Compliance Certificates:
a. For lumber that is not marked with grade stamp.
b. For preservative-treated wood that is not marked with treatment-quality mark.
2. Evaluation Reports: For the following, from ICC-ES:
a. Wood-preservative-treated wood.
The submittal for painting work shall include the following and be submitted to the COR five (5) days prior to work beginning for approval:
1. A complete list of materials proposed to be provided for the work.
The submittal for plumbing work shall include the following and be submitted to the COR five (5) days prior to work beginning for approval:
1. A complete list of materials proposed to be provided for the work.
The submittal…