This is a Questions and Answers document for National Park Service solicitation 140P2126R0003 regarding C5 Bathhouse & Visitor Access renovation work at an unnamed National Park Service facility.

The Q&A clarifies key project parameters and requirements: the period of performance is 160 days as defined in clause 52.211-10; work must commence immediately upon notice to proceed with the camp closed during construction, though the park remains open; the correct NAICS code is 236220; this is a small business set-aside; no liquidated damages are included; and no third-party inspections are required. The contract involves multiple construction activities including bathhouse renovation, visitor access improvements, paving with deteriorated base course replacement, roofing repair (existing GAF Timberline with no warranty), retaining wall construction, plumbing tie-ins at floor cleanouts, construction fencing, stormwater management permitting, landscaping restoration with soil preparation and seeding, and equipment salvage and reinstallation. The contractor is responsible for completing stormwater management permitting with Virginia DEQ, though NPS has obtained plan approval. The document confirms that one individual may serve as superintendent, SSHO, and QC manager if appropriately qualified and on-site during all work; addresses utility availability (none anticipated); clarifies asbestos and lead information is in Appendix A; and specifies the contractor must remove and return existing toilets to the park. The project includes both base contract work and potential options related to flexible porous pavement paths, with detailed specifications referenced throughout for permits, landscaping, material removal, and construction requirements.

View the file

Other files for this federal contract opportunity

Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Do the Superintendent, SSHO and QC Manager need to be 3 separate individuals?

As long as this person knows they have to be on-site whenever work is happening and meet the qualifications for all positions, the superintendent requirement should govern.

2. Can the period of performance be extended after award once the material/equipment lead times are confirmed due to current market conditions for the equipment for this project? Typically there are very limited circumstances where third party supplier delays. It is recommended that offerors who feel the period of performance is inadequate demonstrate this during the bidding process.

3. Are soil boring reports available? If not, it will be assumed that excavation will be clear of rocks and obstructions. Please read the specs.

4. Please provide bidding quantities for deteriorated base course (paving). ? Please ?

5. Please confirm the manufacturer of the existing roofing system and who carries the current warranty of the roofing system. GAF Timberline (shakewood) No warranty.

6. Is there a bulk water fill i.e. a hydrant or water source we can pump from for grading operations in close proximity? Offeror should not plan on utilities being available.

7. Please confirm whether asbestos or lead is present on this project, and if so, provide the relevant documentation. Appendix A specs

8. Does this project require phasing? The camp will be closed while work is in progress.

9. Is this project tax exempt? This contract is in support of the National Park Service, a tax exempt Government Agency. You will need to confirm with your state tax department if taxes need to be paid.

10. When do you anticipate on site work starting? As soon as the notice to proceed is issued.

11. Are third party inspections required? No

12. Is permitting required? Please read the specifications; 1.11 PERMITS, FEES, AND RESPONSIBILITIES

13. Is any landscaping restoration required for this project? For example; topsoil, seeding, and fertilizer. Please read the specifications; SECTION 329115 - SOIL PREPARATION (PERFORMANCE SPECIFICATION)

14. Is the period of performance 1 year as implied on page 3 of the solicitation under Supplies/Services? Or is the period of performance 160 days as listed in SECTION F - Deliveries or Performance - 52.211-10 -- Commencement, Prosecution, and Completion or Work (Apr 1984)?

The period of performance is defined at 52.211-10. The SF-1442 includes approximate performance dates for internal planning.

15. Drawing C7 for the Visitor Access lists Option 1. Nowhere on the solicitation is there a place to list the price for this option. Is this not an option? Please explain. Correct, there is no option listed in the solicitation for Visitor Access as referenced in Drawing C7 (Option 1).

16. Drawing C7 Key Notes 7 & 8 state to see structural for details concerning the (2) retaining walls. There are no details to be had. Please provide. The missing pages are attached.

17. Is this a small business set aside? Yes please refer to 52.219-6.

18. Please confirm if plumbing tie ins would be at FCO. FCO indicates floor cleanout.

19. Do we need to install any construction fence even when the camp house is closed? Yes

20. What are the liquidated damages? Liquidated damages are not included in this contract.

21. Will any equipment be required to be salvaged? Yes, there is a requirement to remove, store and then re-install. There is also a requirement to remove the existing toilets and return to the park.

22. Are any hazardous materials reports available? Are any hazardous materials reports available? Yes, Appendix A of the Specs.

23. Page 7 of the solicitation is the bid schedule. The specifications include section 01 27 00 which list contract line items within each of the respective CLINs in the bid schedule. Is this more detailed pricing as outlined in the specification section required with the pricing volume?, That's a question for contracting.

24. Have the stormwater management permit and erosion and sediment control permit already been obtained by NPS? If not, is this the responsibility of the Contractor? , NPS and its designers have successfully obtained plan review/plan approval of stormwater management concepts. However, the ultimate permit holder will be the contractor who is actually performing the work. The successful offeror is responsible for completing the stormwater management permitting process with Virginia DEQ wherever applicable. Virginia DEQ approval letters are attached for reference. Duplicate sets of drawings that bear the Virginia DEQ Plan Approval stamp on the coversheet are also included.

25. Will the park be open to visitors during construction? , The park will be open but Camp 5 will be closed durning construction

26. Where is Panel 5A fed from? , 5A is fed from the main panels located by the propane tank and to the left of dorm A-16

27. The sheet contains red and yellow colored flexible porous pavement paths that have notes indicting they are options either not in contract or being considered. Please confirm which, if any of these are in contract and if they are options, how are we to indicate the option costs in the pricing volume. , The red color is not in the contract. The yellow is in the contract and could be an option.

28. Factor 2 states a 5 page limit. Are there any page limits for the rest of the technical volume? , No.

29. Factor 1 states to submit the attached "Project Experience" form, however a form was not provided. Please provide. There is no required form. Offerors should document experience on their own forms.

30. Please confirm the schedule does not count towards the 5 page limit for the technical approach. Correct.

31. Page 31 lists the NAICS code for this project as 237310. However, page 46 lists the NAICS code as 236220. Please confirm 236220 is the correct NAICS code. The correct NAICS code is 236220.

32. Please confirm 11" x 17" is acceptable for the schedule., Yes

33. Please provide staking data points for the project. INSTALLATION OF TREE-STABILIZATION MATERIALS / Specs. Page 329300 – 8 / Drawing C-26

34. Please provide details for the retaining wall. The 3 pages that were missing can be sent.

35. Please provide door hardware schedule. Hardware schedule is in the specifications.

36. Please provide the existing siding type, profile and finish. Siding information is in specifications, Cedar beveled board siding, painted

37. Will there be onsite utilities available? Offeror should anticipate that no utilities will be available.