Amendment Number 1_0001.pdf
PDF 173 KB Posted
- Attached to
- Rehabilitate the Lippincott Cottage Roof
- Solicitation number
- 140P2120R0028
About this file
This amendment modifies a solicitation for the rehabilitation of the Lippincott Cottage Roof at the Johnstown Flood National Memorial in St. Michael, Pennsylvania. The National Park Service seeks offers to remove all existing roof sheathing except at the tower, install new 7/16-inch sheathing, and complete a weather-tight enclosed roof by a date prior to winter onset. The period of performance is modified to begin within 7 calendar days of award and last 204 calendar days, with preliminary work to be completed approximately 30 days after award to ensure a weather-tight roof prior to winter. Structural repairs to the porch will follow under a separate future contract. The submission date is changed to September 1, 2020 with offers due by noon local time. Attachments 1 and 2 providing specifications and drawings are replaced with updated versions dated August 18, 2020.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Amendment Number 1 Solicitation Number: 140P2120R0028
THEREFORE:
A. PRE-PROPOSAL CONFERENCE AND SITE VISIT
Attached is the Sign-In Sheet consisting of one page.
B. QUESTIONS
Response to questions are as follows:
1. Can the existing sheathing be left in place if it is in good condition and new 7/16" sheathing be laid over top of it?
The National Park Service (NPS) wants Offeror’s to follow the construction documents. These require all roof sheathing be removed, except for the sheathing at the tower.
2. There might be a long lead time in receiving trusses. Would the NPS consider a change in schedule?
A change in the period of performance has been made, however the NPS must have a weather-tight enclosed roof prior to the onset of winter. Work will begin within 7 calendar days after the award of the contract to ensure preliminary work is done to achieve a weather-tight enclosed roof prior to the onset of winter. This period is anticipated to be approximately 30 calendar days of work. A Spring start date of March 22, 2021 is anticipated to complete all remaining work. All work shall be completed within 29 calendar days after the Spring start date with a final completion date on or before April 20, 2021.
If the Offeror proposes to install products/systems that will remain and become part of the specified roof, the Offeror must provide documentation from product manufacturers that the pre-winter installation does not void specified and manufacturer’s warranties.
3. Should the porch be stabilized structurally before the reroofing process is started?
The porch will be re roofed now with structural repairs to follow at a later date under a separate contract.
4. Modifications have been made Attachment 1 Specifications and Attachment 2, Drawings. New copies are attached, and the current version date is August 18, 2020 on both documents.
Solicitation Number: 140P2120R0028
C. MODIFICATIONS TO THE SOLICITATION
1. Standard Form 1442, Solicitation, Offer and Award (Construction, Alteration, or
Repair), is modified to make the following changes:
(a) Block 11, is modified to delete 7 calendar days and complete within 59 calendar days after receiving notice to proceed and is replace it with: 7 calendar days complete within 204 calendar days after receiving notice to proceed.
(b) Block 13, is modified to change the submission date of August 26, 2020 to
September 1, 2020. The submission time of 1200 local time remains unchanged.
2. Page 11 of 71, Section F – Deliveries or Performance, FAR 52.211-10
COMMENCEMENT, PROSECURTION, AND COMPLETION OF WORK
(APR 1984), is modified to delete the clause in its entirety and replace it with the following:
FAR 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF
WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 7 calendar days calendar day after the date the Contractor receives the notice to proceed,
(b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 204 calendar days. The time stated for completion shall include final cleanup of the premises.
(End of clause)
3. Page 35 of 71, Section J – List of Documents, Exhibits and Other Attachments, is modified to delete the following:
(a) Delete Attachment 1, Specifications or Structural Stabilization of Lippincott Cottage, Johnstown Flood National Memorial (JOFL) St. Michaels, PA, 427 – 159961, PMIS No: 171820, 308 Pages and replace it with Attachment 1, Specifications for Structural Stabilization of Lippincott Cottage, Johnstown Flood National Memorial (JOFL) St. Michaels, PA, 427 – 159961, PMIS No:
171820, 308 dated August 18, 2020.
Solicitation Number: 140P2120R0028
(b) Delete Attachment 2, Attachment 2, Drawings entitled “Structural Stabilization of Lippincott Cottage, Johnstown Floor National Memorial (JOFL) St. Michael, PA PMIS #171820, 23 Pages and replace it with Attachment 2, Attachment 2, Drawings entitled “Structural Stabilization of Lippincott Cottage, Johnstown Floor National Memorial (JOFL) St. Michael, PA PMIS #171820, 23 Pages dated August 18, 2020.
-ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED-