This document appears to be a modification to Section 01 50 00 of a construction contract regarding Temporary Facilities and Controls. The changes outline the use charges for water and electric power services during the contract period. For water service, potable water from the existing water system is available without metering or use charges for up to 10 users/camper hook-ups, with connections and extensions provided for construction operations at no additional permit cost. Importantly, this excludes construction and non-potable water availability.
For electric power service, power from the existing system is available with metering and use charges to be paid through the local power company. The contractor must coordinate temporary metering installation and billing with the local electrical provider, and provide necessary connections and extensions for construction operations, covering any additional permit costs. The use charges for these temporary facilities are to be included in the overall Contract Sum as required.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
The following changes should be made to 01 50 00 Temporary Facilities and Controls:
1.3
USE CHARGES
A. General: Cost or use charges for temporary facilities shall be included in Contract Sum as required.
B. Water Service: Potable Water from existing water system is available for use without metering and without payment of use charges for personal use for up to 10 users/camper hook-ups during the Period of Performance. Provide connections and extensions of services as required for construction operations without any additional permit costs.
1. This excludes construction and non-potable water availability.
D. Electric Power Service: Electric power from existing system is available for use with metering and with payment of use charges through the power company.
Coordinate temporary metering installation and billing with local electrical provider. Provide connections and extensions of services as required for construction operations with any additional permit costs.