B09_Att_34_RFI_10-3-24_0003.pdf

PDF 135 KB Posted

Attached to
FOSU 318708-322870 Replace Fort Sumter and Fort Mo
Solicitation number
140P2024R0151
Issued by

About this file

This document contains questions and answers related to a Request for Information (RFI) for Solicitation 140P2024R0151 to replace the Fort Sumter and Fort Moultrie docks and rehabilitate the Liberty Square Pier for the National Park Service.

Key details include:

  • The contractor will not be allowed to install temporary trestle at Fort Moultrie, and must complete the project from water/shore without impacting the wetlands.
  • Specifications regarding concrete placement time limits have been removed, provided the alternate mix design conforms to the remaining specifications.
  • The use of additional admixtures beyond those specified is allowed to accommodate the remote project location.
  • For the required documentation in Volume 1, small businesses can reference their small business status in lieu of providing a Subcontracting Plan Form.
  • The agency will not consider substituting the specified concrete floating docks with the contractor's aluminum framed docks, as the concrete system was determined to best meet the project requirements.

View the file

Other files

File Type Posted
B09_Att_35_RFI_10-10-24_0004.pdf PDF
Sol_140P2024R0151_Amd_0004.pdf PDF
Sol_140P2024R0151_Amd_0003.pdf PDF
B09_Att_33_Specifications_Div_2-49_(rev_10-3-24)_0003.pdf PDF
B09_Att_25_Emergency_Dock_Inspection_Report_0002.pdf PDF
B09_Att_24_673938-FOSU_392_41065_(LSQ_plans)_0002.pdf PDF
Sol_140P2024R0151_Amd_0002.pdf PDF
B09_Att_22_LISQ_Permit_LSAC-1988-09074_0002.pdf PDF
B09_Att_31_FOSU_318708-322870_Sect_B-M_(rev)_0002.pdf PDF
B09_Att_27_FOSU_211428_Rehab_Dock_As-Built_Dwgs_0002.pdf PDF
B09_Att_28_Banking_Info_Questionnaire_(rev)_0002.docx DOCX document
B09_Att_29_Ft_Moultrie_Natl_Hist_Park_(SCDHEC)_0002.pdf PDF
B09_Att_30_RFI_9-26-24_0002.pdf PDF
B09_Att_26_FOSU_Geotechnical_Report_0002.pdf PDF
B09_Att_32_WD_Hvy_Dredge_SC20230004_0002.txt TXT text file
B09_Att_21_Specifications_Div_One_(rev)_0002.pdf PDF
B09_Att_23_1990_FOSU_Plans_0002.pdf PDF
Sol_140P2024R0151_Amd_0001.pdf PDF
Att_18_Sol_Sec_B-M_0001.pdf PDF
Att_19_RFI_9-18-24_0001.pdf PDF
Att_20_Pre_Bid_Sign_In_Sheet_0001.pdf PDF
B08_Att_4_Ft_Moultrie_Drawings.pdf PDF
B08_Att_13_Project_Experience_Questionnaire.docx DOCX document
B08_Att_7_Wetland_Delineation_Report.pdf PDF
B08_Att_17_Sections_B-M_Solicitation.pdf PDF
B08_Att_11_Wage_Determination_SC20240023_Building_1-5-24.pdf PDF
B08_Att_16_Small_Business_Subcontracting_Plan_Form.doc DOC document
B08_Att_10_Fort_Moultrie_Survey.pdf PDF
B08_Att_3_Ft_Sumter_Drawings.pdf PDF
B08_Att_6_FONSI_Fort_Sumter_and_Fort_Moultrie_Dock_Replacement.pdf PDF
B08_Att_2_Specifications_Div_2-49.pdf PDF
Sol_140P2024R0151.pdf PDF
B08_Att_14_Past_Performance_Questionnaire.docx DOCX document
B08_Att_1_Specifications_Div_One.pdf PDF
B08_Att_5_Liberty_Square_Drawings.pdf PDF
B08_Att_12_Contract_Price_Schedule.xlsx XLSX spreadsheet
B08_Att_15_Banking_Information_Questionnaire.docx DOCX document
B08_Att_9_Fort_Sumter_Survey.pdf PDF
B08_Att_8_Combined_Design_Calcs_FOSU_318708-322870.pdf PDF
Show all 39

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFIs

FOSU 318708-322870

Solicitation 140P2024R0151

Amendment 3

10-3-2024

1. Question: Being that the contractor will not be allowed to install temporary trestle at

Fort Moultrie, please very that it is also unacceptable to build out a land causeway or any other methodology that may damage the wetlands and contractor must complete the project from water/shore. Please note, it is not feasible to build out the entire pier from the water, requiring contractor to mobilize a land-based crane that will likely need to increase the LOD.

Answer: Due to impacts to the potential shellfish habitat, the SCHED permitting and the

FONSI documentation, we cannot impact the wetlands. If a landside crane requires adjustments to the limits of disturbance (LOD), any proposed changes to the limits of

LOD as shown in the final construction plans must be submitted to the Contracting

Officer for approval. The Contracting Officer will coordinate review with NPS subject matter experts to ensure proposed changes are consistent with the analysis and determinations in the Environmental Assessment and resulting FONSI as required by

NEPA, related documentation for compliance with the National Historic Preservation Act, Endangered Species Act, Clean Water Act, and other applicable laws/regulations prior to approving any changes to the LOD. All avoidance and minimization measures included in the approved environmental compliance documentation would apply. Refer to the FONSI and other compliance documentation that were provided with the solicitation for more detail.

2. Question: In specification section “03 30 00 CAST-IN-PLACE CONCRETE” paragraph

“3.01.E.3” it is mentioned that concrete shall be no older than 45 minutes after addition of water and no older than 90 minutes after cement and aggregate are mixed before placement. Due to the remote nature of the project(s), specifically Fort Sumter, and the lack of adequate upland real estate to field batch the concrete, wet concrete will have to be transported from mainland to the placement location with the aid of retarding admixtures. Specification section 03 00 00, 3.01, E, 3 is not feasible. Can this requirement be removed from the specifications?

Answer: See Att 33 Specifications Div 2-49 (rev 10-3-24) where this portion of the specification is removed, provided the alternate mix design conforms with the remained of the specification and has proven performance meeting the requirements.

3. Question: In specification section “03 30 00 CAST-IN-PLACE CONCRETE” paragraph

“3.01.E.4” it is noted that "No admixtures, except those mentioned in paragraph 2.1 shall be used. Calcium chloride will not be permitted" Specification section 03 00 00, 3.01, E, 4 is not feasible as additional admixtures will need to be added to the concrete due to the plant’s remote location from the project. Can this requirement be removed from the specifications?

Answer: See response to Question 2.

4. Question: For Volume 1 part 4 for section, I and K is there a spot in SAM.gov that we can fill that information out? Or should we just be copying and pasting from the solicitation and filling out those specific questions/ sections?

Answer: You may contact SAM.gov if you have questions regarding your entity information with them. Refer to Solicitation Section L, Volume 1: Required

Documentation, 4. Section I and K Representations and Certifications two bullet points for requirement descriptions, but including copying and pasting from the solicitation with information provided is acceptable.

5. Question: For small businesses we qualify as a small business are we needing to put in our document that we are a small business in place of the Subcontracting Plan Form?

Answer: No. Refer to the Solicitation Section L, Volume 1: Required Documentation, #6.

Small Business Subcontracting Plan bullet points requirements.

6. Question: Reading through the drawings for the project, I noticed that you guys are asking for concrete floating docks. We manufacture marine grade aluminum framed floating docks with closed cell foam incapsulated in hand welded HDPE plastic and decked with Wolf PVC decking. Would you consider us an approved equal?

Answer: Refer to the substitution clause in SECTION 01 67 00 - PRODUCT

REQUIREMENTS, that states the winning bidder may request substitutions. However, through the existing conditions investigations, calculations, compliance, and the value analysis process, the system chosen to meet the project parameters was determined to be concrete.

File details come from the government source that posted it. Updated .