This document is a set of Division 1 specifications for a federal contract opportunity to replace and rehabilitate docks at Fort Sumter, Fort Moultrie, and Liberty Square within the Fort Sumter and Fort Moultrie National Historical Park.

The key requirements include demolishing and installing new docks at Fort Sumter, Fort Moultrie, and Liberty Square to meet Architectural Barriers Act (ABA) compliance, providing loading/unloading operations, utilities, lighting, access controls, and signage. The work is divided into a base bid and several options, including storm event preparation, pile jackets, a boat lift, guardrail replacement, and landside electrical work. The contract period is approximately 546 days, with work to be completed by May 31, 2026. Specific requirements are provided for site access, staging, environmental protection, cultural resource preservation, and coordination with park operations and visitors. The specifications also detail the proposal pricing structure, contract modification procedures, and definition of contract line items.

View the file

Other files

File Type Posted
B09_Att_35_RFI_10-10-24_0004.pdf PDF
Sol_140P2024R0151_Amd_0004.pdf PDF
B09_Att_34_RFI_10-3-24_0003.pdf PDF
Sol_140P2024R0151_Amd_0003.pdf PDF
B09_Att_33_Specifications_Div_2-49_(rev_10-3-24)_0003.pdf PDF
B09_Att_25_Emergency_Dock_Inspection_Report_0002.pdf PDF
B09_Att_24_673938-FOSU_392_41065_(LSQ_plans)_0002.pdf PDF
Sol_140P2024R0151_Amd_0002.pdf PDF
B09_Att_22_LISQ_Permit_LSAC-1988-09074_0002.pdf PDF
B09_Att_31_FOSU_318708-322870_Sect_B-M_(rev)_0002.pdf PDF
B09_Att_27_FOSU_211428_Rehab_Dock_As-Built_Dwgs_0002.pdf PDF
B09_Att_28_Banking_Info_Questionnaire_(rev)_0002.docx DOCX document
B09_Att_29_Ft_Moultrie_Natl_Hist_Park_(SCDHEC)_0002.pdf PDF
B09_Att_30_RFI_9-26-24_0002.pdf PDF
B09_Att_26_FOSU_Geotechnical_Report_0002.pdf PDF
B09_Att_32_WD_Hvy_Dredge_SC20230004_0002.txt TXT text file
B09_Att_23_1990_FOSU_Plans_0002.pdf PDF
Sol_140P2024R0151_Amd_0001.pdf PDF
Att_18_Sol_Sec_B-M_0001.pdf PDF
Att_19_RFI_9-18-24_0001.pdf PDF
Att_20_Pre_Bid_Sign_In_Sheet_0001.pdf PDF
B08_Att_4_Ft_Moultrie_Drawings.pdf PDF
B08_Att_13_Project_Experience_Questionnaire.docx DOCX document
B08_Att_7_Wetland_Delineation_Report.pdf PDF
B08_Att_17_Sections_B-M_Solicitation.pdf PDF
B08_Att_11_Wage_Determination_SC20240023_Building_1-5-24.pdf PDF
B08_Att_16_Small_Business_Subcontracting_Plan_Form.doc DOC document
B08_Att_10_Fort_Moultrie_Survey.pdf PDF
B08_Att_3_Ft_Sumter_Drawings.pdf PDF
B08_Att_6_FONSI_Fort_Sumter_and_Fort_Moultrie_Dock_Replacement.pdf PDF
B08_Att_2_Specifications_Div_2-49.pdf PDF
Sol_140P2024R0151.pdf PDF
B08_Att_14_Past_Performance_Questionnaire.docx DOCX document
B08_Att_1_Specifications_Div_One.pdf PDF
B08_Att_5_Liberty_Square_Drawings.pdf PDF
B08_Att_12_Contract_Price_Schedule.xlsx XLSX spreadsheet
B08_Att_15_Banking_Information_Questionnaire.docx DOCX document
B08_Att_9_Fort_Sumter_Survey.pdf PDF
B08_Att_8_Combined_Design_Calcs_FOSU_318708-322870.pdf PDF
Show all 39

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REPLACE AND REHABILITATE DOCKS AT

FORT SUMTER, FORT MOULTRIE AND

LIBERTY SQUARE

FORT SUMTER AND FORT MOULTRIE

NATIONAL HISTORICAL PARK

FOSU PMIS NO. 318708 / 322870

DIVISION 1

SPECIFICATIONS

Table of Contents (TOC) 01 11 00 Summary of Work 01 26 01 Contract Modification Procedures 01 27 00 Definition of Contract Line Items 01 31 00 Project Management and Coordination 01 32 16 Construction Schedule 01 32 33 Photographic Documentation 01 33 23 Submittal Procedures 01 35 13.22 Archeological Protection 01 35 23 Safety Requirements 01 35 91 Historic Preservation Treatment Procedures 01 40 00 Quality Requirements 01 42 00 Reference Standards 01 50 00 Temporary Facilities and Controls 01 56 39 Tree Retention and Protection 01 57 19.12 Noise and Acoustics Management 01 57 23 Under-an-Acre Pollution Prevention (UPPP) 01 67 00 Product Requirements 01 73 29 Cutting and Patching 01 73 40 Execution 01 74 19 Construction Waste Management and Disposal 01 77 00 Closeout Procedures 01 78 23 Operation and Maintenance (O&M) Data 01 79 00 Demonstration & Training 01 81 13 Sustainable Design Requirements-LEED™ (Leadership in Energy & Environmental Design)

Non-LEED Projects

Supporting Documents Submittal List Template (01 33 23) Closeout and Operation & Maintenance (O&M) Requirements Template & Sample (01 77 00, 01 78 23, 01 79 00) Project Waste Management Plan Worksheet Sample (01 74 19)

FOSU 318708 / 322870 01 11 00 - 1

051121 SUMMARY OF WORK

FOSU 318708 / 322870

SECTION 01 11 00 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes the following:

1. Work Covered by Contract Documents

2. Work Phases

3. Work Under Other Contracts

4. Government-Furnished Materials

5. Contractor Use of Site

6. Public Use of Site

7. Occupancy Requirements for Buildings

8. Conduct of Operations

9. Work Restrictions

10. Special Construction Requirements

11. Soils Investigation Report

12. Additional Reports

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Locations:

1. Fort Sumter, Fort Sumter and Fort Moultrie National Historical Park, Charleston, South

Carolina.

2. Fort Moultrie, Fort Sumter and Fort Moultrie National Historical Park, Charleston, South

Carolina.

3. Liberty Square, Fort Sumter and Fort Moultrie National Historical Park, Charleston, South

Carolina.

B. The Work consists of:

1. Fort Sumter, Fort Sumter and Fort Moultrie National Historical Park, Charleston, South

Carolina; The work includes, but is not limited to: demolishing and replacing the dock meeting Architectural Barriers Act (ABA) compliance, provide NPS and Concessionaire loading/unloading operations, providing empty conduit, shore power, convenience power, site lighting, access control, and hose bibs, removing existing park identity signage on land and constructing new signage on the dock, and incorporating new interpretive panels on the dock.

2. Fort Moultrie, Fort Sumter and Fort Moultrie National Historical Park, Charleston, South Carolina; The work includes, but is not limited to: demolishing and replacing the dock meeting Architectural Barriers Act (ABA) compliance, provide loading/unloading operations on a pierhead and floating dock systems, fishing access, providing empty conduit, shore power, convenience power, site lighting, access control, and hose bibs, removing and installing new concrete pad and benches at the dock entry.

FOSU 318708 / 322870 01 11 00 - 2

3. Liberty Square, Fort Sumter and Fort Moultrie National Historical Park, Charleston, South Carolina; The work includes, but is not limited to: removal and replacement of pedestrian loading ramp and platform, select pierhead repairs, removal and removal and replacement of select guardrail panels, providing empty conduit, side mounted utilities, shore power, convenience power, site lighting protected in place, access control, hose bibs, and added sub-meter.

4. This project is not seeking a Certification Level according to the U.S. Green Building Council's Leadership in Energy & Environmental Design (LEED) Rating System. See Division 01 Section "Sustainable Design Requirements for Non LEED Projects” for additional information.

C. Project will be constructed under a single prime contract.

1.3 WORK PHASES

A. The Work at Fort Sumter shall be conducted in four (4) phases in the following order, with each phase substantially complete before beginning the next phase:

1. Ferry access to the pier and visitor access from the ferries to the Fort must be maintained at all times during tour operations. The new pier will be constructed while the existing pier remains, to the longest extent possible.

2. Phase 1: Construct the outshore portion of the pier from pile cap type 4 and beyond.

Including all fender units to the extent possible

3. Phase 2: Demolish the inshore end of the existing pier to allow for the completion of the new pier to the existing landside pavement. Special coordination is required to schedule this phase during non-operational hours for the tours.

4. Phase 3: Complete the construction of the new pier to the landscape paving. Provide two temporary, ABA compliant, 48” clear width, passenger gangways to span the gap between the land and new pier during tour operational hours.

5. Phase 4: Complete the demolition of the existing pier and install all remaining fender units.

Remove temporary construction.

1.4 SUBMITTALS

1. Staging and Access Plan: Contractor shall provide a Staging and Access Plan, demonstrating all physical and operational needs to fully complete deconstruction and construction at each of the three sites within the allocated construction period, including but not limited to; sequencing, phasing, traffic management, pedestrian and vehicular detour and safety plans, temporary signage and barricades, temporary gangways, scaffolding, barge mooring and docking locations, barge loading locations, siltation curtain and debris boom, natural resource protection and all temporary measures.

2. Refer to Section 01 3591 “Historic Preservation Treatment Procedures” for cultural resource protection.

3. Refer to Section 01 3513.22 “Archeological Protection” for archeological resource proection.

1.5 WORK UNDER OTHER CONTRACTS

A. General: Cooperate with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under either Contract. Coordinate Work of this

FOSU 318708 / 322870 01 11 00 - 3

Contract with work performed under separate contracts. Allow for access routes and staging areas as necessary to complete work.

1.6 GOVERNMENT FURNISHED MATERIALS

A. In case of Government furnished materials:

1. Government will arrange and pay for delivery of Government-furnished items according to Contractor's Construction Schedule.

2. Contractor is responsible for initial inspection, receiving, unloading, and handling

Government-furnished items at Project site.

3. Government will inspect delivered items for damage after delivery. Contractor shall be present for and assist in Government's inspection.

4. Government will arrange for replacement if Government-furnished items are damaged, defective, or missing.

5. Contractor is responsible for protecting Government-furnished items from damage during storage and handling, including damage from exposure to the elements.

6. If Government-furnished items are damaged as a result of Contractor's operations, Contractor shall repair or replace them.

7. Contractor shall install and otherwise incorporate Government-furnished items into Work.

B. Government Furnished Materials:

1. Regulatory and identity signage to be provided by the Government. Quantities and locations to be verified by the Government. Signage includes:

a. Exit to Ferry

b. Accessible Sign

c. Fort Sumter Entrance/Restroom

d. Official Docking Only

e. Two (2) US Govt. Property, Authorized Docking Only

f. Slow to No Wake

g. Fort Sumter and Fort Moultrie National Historical Park

h. Fort Site Closed, Do Not Enter

i. Visitor Information & Regulations

ii. No Fishing Beyond this Point

iii. No Fishing

iv. No Swimming

2. Park identity signage, sign only, frame provided by Contractor.

3. Two (2) interpretive signage panels at Fort Sumter, signs only, frames provided by

Contractor.

1.7 CONTRACTOR USE OF SITE

A. General: Contractor shall have limited use of site for construction operations and minimize site disturbance to the extent possible. Limit use of premises to areas within the approved construction limits indicated on drawings and to work areas that are dependent on construction phases and work areas. Contractor’s work areas will be determined at the preconstruction meeting and directed by the Contracting Officer. Access to other portions of the site must be maintained for the public and Park activities. Do not disturb portions of Project site beyond areas in which the Work is indicated.

Contractor's use of the site is limited only by visitor access, the Government's right to perform work or to retain other contractors on portions of Project.

FOSU 318708 / 322870 01 11 00 - 4

1. Prior to commencing construction, the Contractor shall familiarize themselves with conditions at the sites and suggested construction sequences shown on the drawings. It shall be the Contractor’s responsibility to provide all necessary safeguards to maintain all parts of the existing structures in safe condition at all times during the process of construction and to protect the Government property from damage.

a. Contractor shall construct and maintain shoring, bracing, and supports as required.

2. The Contractor shall provide temporary fencing with gates or barriers surrounding the work site to preclude safety hazards as necessary.

3. The Contractor shall conduct a pre-construction survey to verify all dimensions and conditions pertaining to the work. Should actual field dimensions vary from those shown, the Contractor shall notify the Contracting Officer and present them with an adjusted plan prior to proceeding with the work.

4. If the Contractor encounters utilities that affect the work that are not shown on the plans the Contractor shall notify the Contracting Officer prior to continuing with the work.

5. Reference Section 01 7340 “Execution” for topographic and bathymetric survey requirements prior to commencing work, during construction and as required to complete construction.

6. Limits of disturbance adjacent to the wetlands to be surveyed, staked and GPS digitally documented and walked in the field at low tide with the Contracting Officer prior to construction.

7. Contractor shall be solely responsible for maintaining emergency access and egress at all times.

a. All emergency egress points, including the pierhead and docks, are to remain unobstructed at all times during construction.

b. Liberty Square exterior ramp and elevator at the Fort Sumter Visitor Center at

Liberty Square are to remain open at all times.

c. Staging and Access Plan to include pedestrian access and egress routes for Bid

Option H.

8. Contractor to minimize impacts to visitor services to the extent possible.

9. Contractor to minimize impacts to visitor services during peak times, where practical.

a. Seasonal peak visitor use of ferry operations is from March through November.

b. Week days of peak visitor ferry use are Thursday, Friday, Saturday and Sunday.

c. A schedule of ferry service and additional peak times must be obtained from the

Contracting Officer.

10. Restrict staging and stockpiling areas to hardened areas only or as approved by the

Contracting Officer.

11. When possible, place storage of soils on top of asphalt, paved areas, planks or tarps to reduce ground and vegetation disturbance.

12. Landside - equipment will be kept on hardened surfaces, except where needed to perform grading and utility work.

13. Upon completion of staging area and stockpiling area use, return all areas to preconstruction conditions or better at no additional cost to the Government.

14. Contractor vessel mooring location areas will be provided to the Contractor by the

Contracting Officer as necessary.

a. Locations will be determined at the site pre-construction meeting.

b. Locations are subject to change with the tides.

c. Locations are subject to change by the Contracting Officer.

d. Contractor proposal of locations shall be submitted in writing and approved by the

Contracting Officer prior to use.

15. Contractor barge docking areas;

a. Locations will be determined at the site pre-construction meeting.

FOSU 318708 / 322870 01 11 00 - 5

b. Locations are subject to change with the tides.

c. Locations are subject to change by the Contracting Officer.

d. Contractor proposal of locations shall be submitted in writing and approved by the

Contracting Officer prior to use.

16. Dredging is prohibited.

17. Barge loading is to take place from either the Contractor’s dock or an off-site location permitted for barge operations and contractor use.

a. Fort Moultrie – Contractor to confirm channel width and depth restrictions for all tides to determine type of vessel and access limitations.

18. The Contractor shall provide fall protection for workers where required. Workers shall wear life jackets per OSHA requirements.

19. Scaffolding shall be provided as necessary, and scaffolding plan shall be submitted to the

Contracting Officer for review prior to commencement of work.

20. Fort Sumter

a. Marine construction is to take place from the waterside.

b. Landside work will be accessed via a barge with limited work area.

c. Contractor shall provide a dock capacity limitation assessment, prepared by a qualified professional Engineer in South Carolina, as needed for continued visitor use, deconstruction and construction.

i. Reference the “Emergency Dock Inspection Report_Childs

Engineering_June 2022”, for additional information. An appendix with this package.

d. Ferry tour operations will remain active during construction. Dock will continue to be in service with vessels and visitors loading and unloading.

i. Staging and Access Plan to include seasonal sequence plan.

e. Reference Fort Sumter phasing in Article 1.3.

i. Vessel size and lengths vary. Contractor to coordinate vessel access requirements throughout construction.

ii. Contractor to coordinate with ferry tour operators weekly.

iii. Contractor to provide three (3) week advance notice for when docking locations change.

f. Contractor shall provide and maintain access and egress route from the vessel.

i. Ferry access to the pier and visitor access from the ferries to the Fort must be maintained at all times during tour operations.

ii. Contractor to provide a temporary gangway.

iii. Contractor to set up and maintain temporary gangways during tour operation hours and remove and safely store during non-operational hours.

g. The new pier will be constructed while the existing pier remains, to the longest extent possible.

i. Special coordination is required to schedule this phase during non-operational hours for the tours.

21. Fort Moultrie

a. Marine construction is to take place from the waterside, to the greatest extent possible. Marine construction planned from the landside must be submitted to and approved by the Contracting Officer, prior to performing the work.

b. Vehicular access on the dock is prohibited. The existing dock is not structurally sound for heavy loads.

c. Contractor shall provide a dock capacity limitation assessment, prepared by a qualified professional Engineer in South Carolina, as needed for deconstruction.

d. The pierhead will be closed to visitors during construction.

FOSU 318708 / 322870 01 11 00 - 6

e. Sullivan’s Island – Contractor to confirm vehicular access limitations and identify a feasible route for access to Fort Moultrie.

f. Contractor is to utilize the preapproved construction haul route only. Strict adherence will be monitored due to significant archeological sites located throughout the entire project area.

g. Barge is to be removed daily and berthed at contractor’s dock or an off-site location permitted for barge operations and contractor use.Barge my remain on-site provided it does not impeded the channel. Size must be approved by CO

h. Contractor shall provide composite matting, per equipment weight, along the construction haul route. Soil compacted in laydown/haul route due to construction activities shall be decompacted and re-sodded, if necessary. Depth of decompaction shall be limited to 6 inches.

22. Liberty Square

a. Marine construction is to take place from the waterside.

b. Contractor shall provide a pierhead capacity limitation assessment, prepared by a qualified professional Engineer in South Carolina, as needed for deconstruction and construction.

c. Ferry tour operations will remain active during construction. Pierhead will continue to be in service with vessels and visitors loading and unloading.

i. Staging and Access Plan to include seasonal sequence plan.

d. A maximum of 25% of the total guardrail base bid or any one guardrail bid option is permitted to be under construction at one time.

i. Vessel size and lengths vary. Contractor to coordinate vessel access requirements throughout construction.

ii. Contractor to coordinate with ferry tour operators weekly.

iii. Contractor to provide three (3) week advance notice for when docking locations change.

e. Contractor shall provide and maintain access and egress routes from the vessel.

f. Contractor shall provide and maintain a visitor queuing area to sufficiently accommodate 385 visitors. Utilize the existing location under the building, if feasible.

i. Contractor shall notify NPS three (3) weeks in advance, if the queuing locations need to move.

ii. Warmer temperatures typically take place between May 1st – September 30th.

If the queuing locations need to move from under the building during this time, the Contractor may be required to provide a temporary shade solution for visitor comfort.

g. Barge is to be removed daily and berthed at contractor’s dock or an off-site location permitted for barge operations and contractor use.

h. The pier may be closed for a maximum of two (2) consecutive days, with 30 day advanced notice for approval. During this time, tours will be temporarily operated through Patriots Point.

i. Closures are to be avoided and durations limited to the extent possible.

ii. If closures are deemed necessary for limited construction activities, such as fenders and the gangway, avoid peak visitor seasons to the extent possible.

i. Contractor shall provide temporary guardrails complying with OSHA and local, state and Federal code requirements.

B. Emergency Evacuation Due to Storm Events: Contractor shall relocate, including necessary vessels, equipment, vehicles and materials prior to significant storm events.

1. Contractor shall designate safe locations for all personnel for each project site.

MPisano Line

MPisano Line

FOSU 318708 / 322870 01 11 00 - 7

2. Contractor shall designate safe harbor and relocation sites for each project site.

3. Accident Prevention Plan: Contractor to provide a preparedness plan for extreme weather conditions. The plan is to include, but not limited to, identifying specific procedures to secure scaffolding or take down parameters, banding loose materials, and documentation requirements of the site prior to the start of the event.

4. Plan to include means and methods for properly securing in progress construction activities.

5. Submit for Contracting Officer, Park and local Law Enforcement approval.

6. Reference section 01 3523 “Safety Requirements” for additional information.

C. Storage of Materials: Confine storage of materials to the staging areas identified on the drawings.

Contractor is to coordinate the final staging area boundaries with the Contracting Officer.

Modifications to the approved staging area boundaries are to be approved in writing by the Contracting Officer.

1. Staging area erosion control and stormwater management per Section 01 5723 “Under-An- Acre Pollution Prevention” requirements and plans and specifications.

2. The Contractor shall provide temporary fencing or barriers surrounding the storage of materials as necessary.

3. Fort Sumter

a. All materials and equipment are to remain on the barge. Landside staging is prohibited.

b. A temporary barge shall be staged within the project area. Barge spuds to be lowered and installed in the sediment to hold the barge in place. During construction of the new dock and demolition of the existing dock, the temporary barge shall be moved around as needed and the barge spuds to be re-installed with each move.

c. Anchoring of barges is prohibited in or near any known archeological sites and/or delineated wetlands. Spud barges would be anchored with two steel pilings, which would be driven by self-weight or vibration.

4. Fort Moultrie

a. Confine storage of materials to the staging areas identified on the drawings and/or on the Contractor’s barge.

i. Location(s) are subject to change by the Contracting Officer.

b. All materials and equipment are to remain on the barge and/or within the designated landside staging area.

c. A temporary barge would be staged within the project area. Barge spuds would be lowered and installed in the sediment to hold the barge in place. During construction of the new dock and demolition of the existing dock, the temporary barge would be moved around as needed and the barge spuds would be re-installed with each move.

d. Barge is to be removed daily and berthed at contractor’s dock or an off-site location permitted for barge operations and contractor use.

e. Anchoring of barges would be prohibited in or near any known archeological sites and/or delineated wetlands. Spud barges would be anchored with two steel pilings, which would be driven by self-weight or vibration.

f. Staging area located at For Moultrie is to accommodate storage of materials for all three sites; Fort Moultrie, Fort Sumter and Liberty Square.

5. Liberty Square

a. Confine storage of materials to the staging areas identified on the drawings and/or on the Contractor’s barge.

i. Location(s) are subject to change by the Contracting Officer.

b. All materials and equipment are to remain on the barge and/or within the designated landside staging area.

FOSU 318708 / 322870 01 11 00 - 8

c. A temporary barge would be staged within the project area. Barge spuds would be lowered and installed in the sediment to hold the barge in place. During construction of the new dock and demolition of the existing dock, the temporary barge would be moved around as needed and the barge spuds would be re-installed with each move.

d. Barge is to be removed daily and berthed at contractor’s dock or an off-site location permitted for barge operations and contractor use.

e. Anchoring of barges would be prohibited in or near any known archeological sites and/or delineated wetlands. Spud barges would be anchored with two steel pilings, which would be driven by self-weight or vibration.

f. Contractor shall have access to a lay down area(s) up to 1,000 SF.

i. Location(s) will be determined at the site pre-construction meeting.

ii. Location(s) are subject to change by the Contracting Officer.

iii. Contractor proposal of locations shall be submitted to and approved by the

Contracting Officer prior to use.

g. Contractor shall maintain and move the lay down area(s) as necessary to maintain emergency and visitor access.

D. Parking: Confine parking to areas identified on the drawings. There is limited to no on-site parking.

1. Contractor shall designate and Contracting Officer shall approve specific area or areas for contractor on-site and off-site parking.

2. Contractor parking to take place at barge loading area, as needed.

3. Contractor to adhere to Park, City and State regulations.

a. Fort Sumter – no parking.

b. Fort Moultrie – areas identified on the drawings. On-site parking is limited to one

CMR vehicle and one Contractor vehicle.

c. Liberty Square – areas identified on the drawings.

E. Stockpiling: Confine stockpiling to staging areas identified on the drawings and/or barges.

Contractor is to coordinate the final stockpile plan with the Contracting Officer.

F. Preservation of Natural Features:

1. The cultural landscape of Fort Sumter and Fort Moultrie are listed in the National Register of Historic Places. There are contributing built and natural resources located throughout the project area. All work must adhere to the Secretary of Interior’s Standards.

2. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

3. Maintain barriers or temporary chain link fence throughout the duration of construction.

Ground penetrations are prohibited. Remove measures after construction is complete.

4. Provide temporary barriers to protect existing trees and plants and root zones, as identified by the Contracting Officer.

5. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer (CO) and remove agreed-on roots and branches that interfere with construction.

6. Do not fasten ropes, cables, or guys to existing trees.

7. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.

8. If ground inside the limits of disturbance is wet with standing water, contact the

Contracting Officer for instructions.

G. NPS to provide Archeological Monitoring to observe ground-disturbing site work, including but not limited to, the below listed construction activities, at all archeologically sensitive areas, from a safe

FOSU 318708 / 322870 01 11 00 - 9

location mutually agreed on by Contractor and Monitor. As new ground is broken, Monitor will examine excavated materials, using construction layout centerline and perimeter staking as a reference point to record locations of findings.

1. Fort Sumter – NPS shall provide archeological monitoring for electrical work.

2. Fort Moultrie – NPS shall provide archeological monitoring, in the event it is needed.

3. Liberty Square – not applicable.

4. Reference Section 01 3513.22 Archeological Protection for additional information and submittals.

5. Any artifacts recovered are property of Fort Sumter, Fort Moultrie and Liberty Square and should be immediately submitted to the Contracting Officer.

6. Should unknown archeological resources be uncovered during construction, work would be halted in the discovery area and the park staff would consult with the South Carolina State Historic Preservation Office (SHPO) according to 36 CFR 800.13, South Carolina Institute of Archaeology and Anthropology and, as appropriate, provisions of the Native American Graves Protection and Repatriation Act of 1990.

7. Known submerged cultural resources are to be avoided. If additional submerged resources were to be encountered during construction, the SHPO would be consulted.

H. Preservation of Existing Built Features:

1. Identification and protection of built features are to be field verified with the Contracting

Officer prior to issuing the Historic Preservation Features Preservation Plan.

a. Reference Section 01 3591 Historic Preservation Treatment for additional requirements.

2. Prevent damage to existing features not included in the Scope of Work. Restore damage to pre-existing conditions, repairing or replacing damage as directed by Contracting Officer, at no additional expense to the Government.

3. Provide temporary barriers to protect existing features and portions thereof.

4. Carefully supervise excavating, grading, filling, and other construction operations near existing features to prevent unintended damage.

I. Cultural Resource Protection

1. All construction activities and equipment and people must remain inside the limits of disturbance at all times in order to protect adjacent cultural resources.

J. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government employees, and emergency vehicles at all times. Do not use for parking or storage of materials.

1. Schedule deliveries to minimize use of driveways and entrances.

2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

K. Construction Camp: Establishment of a camp within park will not be permitted.

L. Construction Trailer: one trailer is permitted to be located at Fort Moultrie and one Conex sized trailer is permitted to be located at Liberty Square. Refer to the drawings for parking lot locations.

M. Hauling Restrictions: Comply with legal, NPS and SCDOT load restrictions in hauling of materials.

Load restrictions on park roads are identical to state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special

FOSU 318708 / 322870 01 11 00 - 10

permit will not relieve Contractor of liability for damage which may result from moving of equipment.

N. Work must be completed without damage to historic features and the cultural landscapes, including but not limited to, stone walls, brick pavers, concrete entry plaza, granite gun mount, gravesite, earthworks, trees and vegetation not to be removed, survey monuments or signs, roads, or other property. The Contractor will be financially liable to the park for any costs incurred for repairing and/or replacing any of the aforementioned items or for the value of the item as assessed by an archeologist or biologist.

1. If damage occurs to natural resources or historic property, the Contractor must immediately stop work and notify the Contracting Officer to consult with the appropriate parties and damage is to be repaired in a manner consistent with the Secretary of the Interior’s Standards for the Treatment of Historic Properties”.

O. Contractor’s operations shall be conducted reasonably to prevent rutting or other soil damage. No landside work shall be allowed for at least a 24-hour period following a rain accumulation of one

(1) inch or more during the proceeding 24-hour period. After any work stoppage, it will be the responsibility of the Contracting Officer to determine when work may re-commence. Any lost time due to prolonged periods of rain will automatically be credited and added to the length of the contract.

P. All vehicles and other heavy equipment involved in the completion of this contract will be restricted to roads, parking areas, unless given case-specific permission by the Contracting Officer.

Off road equipment use is solely at the discretion of the Contracting Officer and subject to change based on current or anticipated conditions. Rutting or other resource damage will not be tolerated.

Q. All vehicles shall be equipped with absorptive pads or approved spill kits while on park property in order to quickly contain any spills of oil or hydraulic fluid. Any such spills must be reported to the Contracting Officer as soon as is safely possible.

R. Equipment Cleaning (including Marine Equipment):

1. Clean vehicles and construction equipment prior to entry into the Park to minimize the potential for introduction and/or proliferation of invasive non-native weeds through project actions. The contractor is required to wash equipment, with emphasis on undercarriages, with a high pressure spray prior to transporting such equipment to National Parks.

2. All vehicles and construction equipment entering National Parks shall be inspected and approved by the Contracting Officer prior to entering the park. The contractor shall provide at least two business days advance notice to the Contracting Officer and Park prior to equipment inspection.

3. Equipment not deemed clean by the Contracting Officer will not be allowed to enter the park. The contractor remains liable for additional transportation fees incurred when equipment fails inspection.

4. Cleaning will not be permitted within the park. Contractor shall be responsible for identifying and using a cleaning location outside the park. Note that this may be some distance from the park and project site.

S. Concrete Washout Area(s): Location to be coordinated and approved by the Contracting Officer prior to start of construction. Water containing waste from construction activities shall be discharged into a self-contained, leak-proof wash out system; contractor provided, maintained and disposed of per regulations. The direct or indirect discharge of water containing waste to the storm system, bodies of water and wetlands is prohibited. Washout sites shall be returned to their original, pre-construction condition, at the close of work. Site repair/cleaned washout site(s) shall

FOSU 318708 / 322870 01 11 00 - 11

be reviewed and approved by Contracting Officer. Washout area locations are prohibited near wetlands.

T. Protection of Wetlands, Existing Vegetation, Structures, Equipment, Utilities and Improvements;

1. Construction areas are near wetlands and riparian zone; it is a sensitive and protected ecosystem. All construction activities shall be kept within the defined Limits of Disturbance to avoid impacts, with the exception of minimal disturbance from the diameter of pile driving.

2. All construction activities and equipment and people must remain inside the limits of disturbance at all times in order to protect adjacent wetlands, with the exception of minimal disturbance from the diameter of pile driving. If ground inside the limits of disturbance is wet with standing water, contact the Contracting Officer for instructions.

3. There shall be minimal impacts to wetlands. Any construction related activities, such as but not limited to; construction access, grading, fill, tie back grades, trenching and improvements that requires repair or remediation as determined by the Contracting Officer shall be completed at the Contractor’s own expense.

4. Provide temporary barriers, such as chain-link fencing, to protect wetlands. Contractor to coordinate scheduling of a qualified NPS staff member(s) to establish the wetland protection boundary with the Contracting Officer. Contractor to provide, install and maintain staking and temporary barriers as determined by the Contracting Officer. Written approval is required prior to any boundary adjustments.

5. Construction related activities outside the approved limits of construction are prohibited.

Any construction related activities, such as but not limited to; construction access, grading, fill, tie back grades, trenching and improvements outside the approved limits of disturbance that requires repair or remediation as determined by the Contracting Officer shall be completed at the Contractor’s own expense.

6. All waters of the State (WoS), including wetlands, are to be flagged or otherwise clearly marked in the field. A double row of silt fence is to be installed in all areas where a 50 foot buffer can’t be maintained between the disturbed area and all WoS. A 10-foot buffer should be maintained between the last row of silt fence and all WoS.

1.8 PUBLIC USE OF SITE

A. The approved designated construction areas will be closed to the public during construction.

1. Designated construction areas to be sequenced to maintain public visitation, egress and access routes to facilities and vessels, around the areas of construction.

2. Ferry services will remain operational at all times.

B. Contractor shall conduct his operations to ensure the least inconvenience to public. Building, road, and parking lot closures are not permitted.

C. Contractor shall at all times conduct their operations to ensure the least inconvenience to the public.

Contractor shall make any and all necessary measures to protect the general public from the construction sites. Temporary walk closures will be permitted, when required, upon specific approval of Contracting Officer for a maximum amount of time as approved by NPS.

1. Contractor to identify and provide all means necessary for maintaining ABAAS access routes, egress routes, emergency access and service access within NPS property.

Contractor to sequence construction as necessary and relocate temporary ramps, fencing and gates, signage, barriers and other identified means necessary for access as needed throughout the construction period.

FOSU 318708 / 322870 01 11 00 - 12

2. Contractor to coordinate vehicular and pedestrian detour plan with Contracting Officer.

Temporary closers to be approved by the Contracting Officer.

1.9 OCCUPANCY REQUIRMENTS FOR BUILIDINGS

A. Existing Buildings

1. Full Government Occupancy: Government will occupy buildings under construction during the entire contract period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform Work so as not to interfere with Government's day-to-day operations. Maintain existing exits, unless otherwise indicated.

a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Contracting Officer.

b. Maintain existing building in weather tight condition throughout construction period. Repair damage caused by construction operations. Protect building and occupants during construction period.

1.10 CONDUCT OF OPERATIONS

A. Contractor shall conduct his operations in conformance with rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by Park Superintendent.

B. Work on Saturdays, Sundays, Federal holidays, or Federal Government Closures may not be performed without prior consent from the Contracting Officer. Submit requests 2 business/calendar days in advance of the work to the Contracting Officer for approval.

C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.

1.11 WORK RESTRICTIONS

A. Schedule: The recommended contract length for all three sites is 546 days.

1. Contractor to coordinate temporary stabilization and permanent seeding windows, as per technical specifications, within the 546 day contract period.

2. Work shall be complete on or before May 31, 2026 for the commemoration of the 250th anniversary of the country.

B. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7:00 a.m. to 7:00 p.m., Monday through Friday, during daylight times only, except when otherwise indicated. Work hours to begin later than 7:00 a.m. or end earlier than 7:00 p.m., pending sunrise and sunset changes throughout the construction period.

1. Construction activities are to only occur during daylight hours. No temporary lighting is permitted on the docks or surrounding areas. The start and finish of a normal business work day will change throughout the year.

2. Weekend Hours: 7:00 a.m. to 7:00 p.m., per above seasonal daylight changes, are permitted upon request and approval by the Contracting Officer.

FOSU 318708 / 322870 01 11 00 - 13

3. Night Work is not permitted.

4. Early Morning Hours are not permitted.

5. Park scheduled annual events, work may not be permitted or limited. Contractor to coordinate specific dates with the Contracting Officer.

6. Hours for noisy activity: No noisy activities such as earth moving, jackhammers or similar noisy activities to take place prior to 8:00 a.m. or after 6:00 p.m. without approval from Contracting Officer. Contractor shall follow all local, state, and Federal noise ordinances.

a. Reference Section 01 5719.12 “Noise and Acoustics Management” for additional information.

7. Natural and cultural resource protection measures may require construction to cease until the areas have been investigated and/or birds and mammals leave the area, per local, state and Federal requirements. Reference the Environmental Assessment Report for additional information.

8. Unforeseen circumstances or closures mandated by the Federal Government: the Park is closed.

C. Existing Utilities

1. Existing Utilities: Notify Contracting Officer and utility companies and park of proposed locations and times for excavation not less than one week in advance.

2. The utilities shown in the drawings are indicated in accordance with available records. All utilities may not be shown and those which are shown may not be shown accurately. The contractor shall be responsible for field locating all utilities including public utilities and NPS owned utilities to determine exact locations, elevations and sizes.

3. Contractor shall be responsible for calling the South Carolina 811, (888) 721-7877 for all public utilities a minimum one week in advance of digging. For all public and NPS owned utilities, the Contractor may be required to use additional methods for utility locations, such as electromagnetic utility locating, acoustic pipe locating, ground penetrating radar or potholing at no additional cost to the Government.

4. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.

5. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.

D. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

1. Notify Contracting Officer not less than two business days in advance of proposed utility interruptions.

2. Do not proceed with utility interruptions without Contracting Officer’s written permission.

3. Hours and length of Utility Shutdowns: Contracting Officer approved outages must not extend beyond 4 hours. Utilities must be restored at that time, and no later than 5:00p.m.

E. Nonsmoking Building/Tobacco Use/Vaping: Smoking is not permitted within building or within 25 feet of entrances, operable windows, or outdoor air intakes.

1. Smoking is not allowed except in designated smoking areas identified during the preconstruction meeting.

FOSU 318708 / 322870 01 11 00 - 14

1.12 SPECIAL CONSTRUCTION REQUIREMENTS

A. Project Website: A project website administered by NPS will be used for purposes of managing communication and documents during construction stage.

1. See Section 01 31 00 "Project Management and Coordination" for requirements on using

Project Website.

B. Delegated designs: Contractor shall submit complete stamped design drawings and calculations, including but not limited to, analysis of loads, provided by a qualified engineer in South Carolina.

Reference technical specifications for additional items and requirements. Items include;

1. Temporary and permanent vessel access ramps.

2. Scaffolding plan, as necessary.

3. Erection bracing drawings with structural steel connections.

4. Piles.

5. Gangways.

6. Boat lifts.

7. Cantilever gates.

8. Fort Moultrie – Security Gate.

9. Reference drawings and specifications for additional items.

C. Facilities are exposed to severe weather conditions that will effect the work. Contractor shall take adequate precautions to protect the work and shall be responsible for any loss of time and equipment or damage to the work as a result of the weather.

D. The Contractor shall provide all fall protection for workers where required. Workers shall wear life jackets per OSHA requirements. Scaffolding shall be provided as necessary, and a scaffolding plan shall be submitted to the Contracting Officer for review prior to commencement of work.

E. The Contractor shall notify the Contracting Officer when unanticipated or apparently dangerous conditions are uncovered during demolition or construction.

F. Contractor to provide all third-party inspections as indicated in Division 01 and technical specifications. Contractor shall provide materials and assistance in preparing specimens, reports and submit inspection reports to the Contracting Officer.

G. Contractor shall make sure all measures are laid out in their approved Spill Prevention, Control, and Response (SPCR) plan are in place prior to the start of any construction work.

H. Contractor shall not allow any waste materials to enter the water. Contractor shall take measures to collect all demolished waste, including paint chips.

I. Contractor shall install a debris boom around all work areas over the water.

1. The Contractor shall be responsible for continuous maintenance of both the siltation curtains and debris booms to ensure performance.

2. All debris collected in the siltation curtains and booms shall be removed daily.

J. Contractor shall collect and remove all demolition debris and waste materials that enter the water and lay on the bottom.

FOSU 318708 / 322870 01 11 00 - 15

K. Contractor shall remove demolished materials from the site on a daily basis and maintain a clean work site. Neatly and safely store materials that cannot be removed daily in areas specified by the Contracting Officer.

L. Contractor shall take precautions while transporting demolished materials to prevent spillage on streets or other areas. Any materials spilled shall be cleaned up immediately to the satisfaction of the Contracting Officer.

M. Existing fender piles to be removed shall be extracted in their entirety.

N. Contractor shall consider all existing timber to have preservation treatment.

O. Contractor to assume that all concrete contains reinforcing steel.

P. Fort Sumter - Contractor to provide electrical conduit scoping to confirm feasibility of reuse.

Contractor to recommend approach and Contracting Officer to approve.

Q. Unforeseen circumstances or closures mandated by the Federal Government: the Park is closed.

R. To minimize risks to marine protected species, all construction would follow the National Oceanic and Atmospheric Administration (NOAA) Southeast Regional Office Protected Species Construction Conditions (NOAA 2021).

S. To minimize risks to the federally threatened West Indian manatee (Trichechus manatus), the NPS would implement the Manatee Protection Measures for South Carolina proposed by the USFWS (presented in EA, Appendix A).

T. Refer to U.S. Army Corps of Engineers (USACE) permit provided by NPS for additional conditions.

U. To minimize risks to sea turtles, Contractor shall utilize turbidity booms to mitigate impacts to water quality.

V. Park biologists to conduct a survey for West Indian manatee and federally listed sea turtles in the project area prior to construction. If signs of these species are identified within the project area, mitigation measures to avoid impacts to the manatee and sea turtles would be employed, including restricting construction to periods of inactivity (typically November through March) to the extent possible.

W. Contractor personnel would be responsible for observing all water-related activities for the presence of protected species.

X. If a sea turtle is observed within 150 feet of the construction area, construction would cease until the sea turtle is observed departing the project area on its own or after 20 minutes have passed since the sea turtle is last observed within the construction area. Additional monitoring of sea turtles would be conducted, as necessary.

Y. To protect birds under the Migratory Bird Treaty Act (MBTA, 16 USC 703–712), all construction work performed between February 1 and August 31 would require a site survey performed by trained NPS staff. The survey would be completed within two weeks prior to the start of construction. Additional surveys would be required after periods of no work exceeding two weeks.

FOSU 318708 / 322870 01 11 00 - 16

Z. Operations of moving equipment shall cease if a protected species is observed within 150 feet of operations. Activities shall not resume until the protected species has departed the project area of its own volition. All on-site project personnel are responsible for observing water-related activities for the presence of protected species.

AA. BMPs such as noise abatement, avoiding vessel strikes, and following the Marine Mammal Protection Act shall be implemented to mitigate risks to marine mammals.

BB. Bird Protection Acts

1. In order to protect birds under the Migratory Bird Treaty Act (MBTA, 16 U.S.C. 703–712), all construction work performed between February 1 and August 31 requires a site survey, to be performed by trained NPS staff. The survey must be completed within two weeks prior to the start of construction. Additional surveys will be required after periods of no work exceeding two weeks. The Contractor will be required to avoid cutting down trees with active nests, however, other work would be permitted to continue. Some species may also require a buffer around active nests where work cannot occur.

a. Contractor shall request a site survey a minimum of one month prior to mobilization.

CC. Fort Sumter and Fort Moultrie - Piping Plover. At Fort Sumter, piping plovers use the intertidal wetlands for foraging. During construction, piping plovers may be impacted due to noise disturbance and may avoid the area. Potential nesting habitat for piping plover occurs in the sandy beach area well south of the project area. To minimize impacts on the piping plover, if this species enters the construction area while construction operation is underway, construction would cease until the bird has left the area. In addition, park staff would ensure no active nests are located in the beach area south of the project area from mid- March through August.

DD. Fort Sumter and Fort Moultrie - Red Knot. The red knot has been observed at Fort Sumter;

however, this species is not common. Red knots will use tidal flats in the winter, but they migrate to summer breeding habitat in tundra environments. If red knots are in the vicinity of the project area during construction, there is potential for impacts due to noise disturbance. Like the piping plover, if this species enters the construction area while construction operation is underway, construction would cease until the bird has left the area.

EE. Floodplains

1. The entirety of the park is located in the Federal Emergency Management Agency (FEMA)

AE and VE…