This document appears to be Amendment 5 to Solicitation 140P2024R0083 issued by the National Park Service for the GLAC 307606 - Replace Swiftcurrent Water Distribution System project at Glacier National Park in Montana.
The purpose of this amendment is to provide final questions and answers, as well as the well information that was missing from a previous amendment. The solicitation is for the replacement of the existing water distribution system, including a new water storage tank, wells, chlorination building, and associated piping and infrastructure. Key details include that the existing tank will be emptied before construction, the contractor is responsible for a temporary drinking water and fire water system, and there is potential for asbestos abatement. The solicitation states a contract award date of September 15, 2024. Pricing and response instructions are provided, as well as contact information for the contracting office. There are 73 questions and answers addressing various technical and logistical aspects of the project.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P2024R0083_Amd_0005.pdf | ||
| B08-140P2024R0083-Amd4_0004.pdf | ||
| Sol_140P2024R0083_Amd_0004.pdf | ||
| Sol_140P2024R0083_Amd_0003.pdf | ||
| B08-140P2024R0083-Amd3_0003.pdf | ||
| Sol_140P2024R0083_Amd_0002.pdf | ||
| B08-140P2024R0083-Amd2_0002.pdf | ||
| Sol_140P2024R0083_Amd_0001.pdf | ||
| Sol_140P2024R0083.pdf | ||
| B08-140P2024R0083-Complete_Package-2.pdf | ||
| B08-Sectdion_J_-_Attachment_2-GLAC_307606_Swiftcurrent_Water_System_CDs_Drawings_March_2024-Stamped-.pdf | ||
| B08-Section_J-Attachment_1_-Swiftcurrent_Construction_Specifications_05222024-1432-Final.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140P2024R0083 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
PDS
Denver CO 80225-0287 P.O. Box 25287 12795 W. Alameda Pkwy DOI, NPS, DSC Contracting Services
PDS
Denver CO 80225-0287 P.O. Box 25287 12795 W. Alameda Pkwy NPS, DSC Contracting Services Div
07/30/20240005
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
07/08/2024
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
GLAC 307606 - Replace Swift Current Water Distribution System
The purpose of this amendment is to provide for the following:
1. Final responses to Questions and Answers.
2. To provide the well information that was inadvertently left off of Amendment 4.
All other terms and conditions of the solicitation remain unchanged.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Vicki Freese-supler
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
GLAC 307606- Replace Swiftcurrent Utilities 140P2024R0083
Questions and AnswersQuestion Site Showing Ques tions Government Response Amendment # Date Notes
Will the tank need to be empty to be worked on?
The existing storage tank will be emptied by the park before construciton begins. It will not be filled up again until the new system is commissioned. 2 7/12/2024
Does the tank supply the Park housing during construction?
No, the contractor is responsible for constructing and operating temporary drinking water and fire water systems separate from the existing tank. See plan set sheets C6.1 and C6.2. 2 7/12/2024
What is the existing pipe material?
The as-built information provided to the A/E team does not specifically call out existing pipe material. The existing water pipes could be a combination of HDPE, PVC, galvanized and AC pipe. 2 7/12/2024
Is there any transite pipe?
Yes - there could some areas where asbestos abatement may be necessary. 2 7/12/2024
What is the quantity of existing pipe?
The majority of existing pipe is getting abandoned in place, besides where it crosses the alignment of the new pipe. There is estimated over 21,000 LF of existing water pipe in the project area (including services and mains). 2 7/12/2024
Questions and Answers
Are there culverts to be installed in the road to the tank?
Yes, culverts and open-top cross drains. See plan sheets C5.1- C5.6. 2 7/12/2024
Is electric/telemetry hardwired on the road to the tank or wireless? Hardwired. 2 7/12/2024
Is the water from the wells chlorinated before or after it goes to the tank? Before, see plan sheet C3.4. 2 7/12/2024
Does the water main that cuts diagonally through the wooded area north of Route 3 following an existing alignment? Yes, see plan sheet C2.9. 2 7/12/2024
Are there any residents expected during the shutdown season?
Yes - a listing of residents who will be maintaining residency will be provided after contract award. 2 7/12/2024
Where is access required in the ranger/residential area?
There is only one way in and one way out of the residential area.
Access is required in and out at that location. 2 7/12/2024
How is pipe abatement quantified?
There is an estimated 120 LF of AC pipe removal potentially required for this project. All of this is from crossing the existing assumed AC pipe in the campground area, assuming 10’ of pipe removal per crossing (12 crossings). This is an estimate for bids, contractor to verify during construction. 2 7/12/2024
Will the SCADA CLINS include telemetry from the tank to the well?
There is no direct telemetery from tank to well. All SCADA work will fall under CLIN 3. 2 7/12/2024
Is there 1 well pump or 2 well pumps included in the scope of work?
Two well pumps are included in the work. 2 7/12/2024
Questions and Answers
What is the generator’s fuel source? Diesel, gas or propane?
Propane, see specification section 263215. 2 7/12/2024
What does the generator power?
The well pump, telemetry controls, and the chlorine pump.
Basically what is needed to keep the water system functioning during a power outage. 2 7/12/2024
Is there no CLINS for mobilization?
No there is no separate CLIN for mobilization costs. It is up to the Offeror to determine the best placement for these costs within the existing CLIN structure. 2 7/12/2024
Are workers allowed to stay in the park during construction?
No - all contractor personnel must obtain housing outside of the park. 2 7/12/2024
Existing well demo plans indicate the entire well is being demolished?
No, see plan sheet C1.4, well note. 2 7/12/2024
Where does the electric run from the well?
To the chlorination building, see sheet C3.1. 2 7/12/2024
What is the size of the water tank and what is it made of?
The tank is concrete 40'x40' and holds 140,000 gallons. 2 7/12/2024
How do you want us to quantify the price for patching the tank in preparation for coating?
The tank inspection report from 2021 is attached to Addendum 1.
There is one spot where there may be a crack that may require patching. 2 7/12/2024
Refer to tank inspection report in Addendum 1.
Road base is called out near the culverts at the tank road is it intended to run road base on the entire road?
Detail B/C5.4 shows the roadway typical cross section for the entire road. 2 7/12/2024
Questions and Answers
Does the Park want to keep the trench spoils?
No these need to be hauled off and disposed at an appropriate licensed facility. 2 7/12/2024
Is the fire alarm notification system identified on the drawings? No 2 7/12/2024
Can temporary power be pulled from the utility box inside the cabin loops? Yes. 2 7/12/2024
Refer to hookup location and photos in Addendum 1.
Are all meters going to be demoed or abandon? They will be removed as well as their vault. See plansheet C1.4. 2 7/12/2024
Where are we responsible for asphalt removal?
The contractor is responsible for removing asphalt as needed in water line project areas. See plan sheet C4.3 for trenching details.
Revised Amendment 4 7/26/2024
Is there a booster pump as part of the temporary fire system? See plan sheet C6.2. 2 7/12/2024
Does the fire alarm system need to be connected to the temporary fire water system? No 2 7/12/2024
31 Is there a detail for the buried electrical conduit? Yes, see plan sheet E1.7. 2 7/12/2024
Can the main safety, superintendent and other management personnel have dual roles on this project?
No - each management personnel personnel must be separate and apart i.e. separate Quality Control, Site Superintendent and Safety Officer. 2 7/12/2024
How far away from the building do we need to tie the service lines in?
Five (5') feet - please see Detail C/C4.4 on Drawing Sheet 62. 2 7/12/2024
Will FHWA be only other contractor working in the area for coordination purposes? Yes 2 7/12/2024
Was pipe bursting done and if so, can Offerors obtain the locations where this was performed?
Pipe bursting was not done in this project and is not relevant to the project. 2 7/12/2024
Questions and Answers
Are there two well pumps or one pump for two wells?
There are two pumps, one for each well. 2 7/12/2024
Is the generator for the pumps and chlorination system or will the generator need to be sized to also provide for power for the buildings
Only the pumps and chlorination system. The generator has already been sized, see plan sheet E1.2. 2 7/12/2024
Will pre-construction staking being performed by the
NPS?
No, the contractor is responsible for this effort. 2 7/12/2024
Will the contractor be required to sign the trail closures?
No, the NPS will provide any necessary signage as it relates to trail closures. 2 7/12/2024
Does the water line go directly to the chlorination building?
The water line goes directly from the two wells to the chlorination building. 2 7/12/2024
If there are cracks found in the tank - will repairs be needed? If so is there a percentage estimate of the number of cracks to be repaired?
The tank inspection report from 2021 is attached to Addendum 1.
There is one spot where there may be a crack that may require patching. 2 7/12/2024
Include tank inspection report in Addendum 1.
What is the approximate distance from the tank to the chlorination building and electrical?
Approximately 2,500'. Use the scale on the plan sheets to determine the exact distance. 2 7/12/2024
Will the tank be drained every year? Yes, at the end of the season, usually in September. 2 7/12/2024
Is there a temporary power source to be identified in the cabin area and is it required to provide temporary power to the cabins?
Yes, see Addendum 1.
Temporary power for cabins is not necessary if no one is living in the cabins. 2 7/12/2024
Include hookup location and photos in Addendum 1.
Do the fire alarms need to stay active during construction? Yes. 2 7/12/2024
46 What is the cutoff date for questions? 29-Jul-24 2 7/12/2024
Questions and Answers
There is growing concern about formulating a 2024 fall work schedule and compliance with the 90 days required for the Government to consider the proposal prior to award. Will there be an adjustment to the reviw time by the Government to allow the contractor to develop a realistic schedule that allows work to initiate in the 2024 season? The solicitation states that any proposal not allowing this time for review will be rejected.
The 90 days denoted in the solicitation is the time period denoted that the contractor's must maintain the pricing not the time period in which the Government will complete its evaluations of the proposals. As stated during the site visit held, all Offerors shall base their construction schedule on a NTP issuance of September 15, 2024. 3 7/18/2024
Will the asphalt contractors need access to PA-01 for the Fall of 2024 season?
See Summary of Work 01 11 -- Section 1.3.A.4 and the FHWA documents. FHWA will require access to RTE 3 for the entirety of the project for various efforts and the Park will require a full lane of access required for their emergency and other work efforts. 3 7/18/2024
Questions and Answers
What is the asphalt contractor sequencing for the PA- 02 work and related timelines? Will there be an opportunity to coordinate sequencing with the asphalt contract prior to submission of this proposal?
See Summary of Work 01 11 00 Section 1.3.A.5. The FHWA work is currently being solicited under Solicitation #69056724B000012 by the Department of Transportation. There will be no opportunity for potential Offerors to coordinate with FHWA's contractor prior to proposals being due. 3 7/18/2024
During the pre-bid it was mentioned that shutting down the water system early might be an option to facility the early work required this fall. If so, what would that date be? How many days are required to drain th existing water system?
The water system is drained every year in September by the Park. 3 7/18/2024
Questions and Answers
What is the difference between CLIN PA 01 and PA 02. It appears to me that all of the water main installation would be complete under PA02. The way the project would have to be constructed would eliminate CLIN PA
01. Please let me know if I am missing something or DJ&A and clarify exactly the areas in PA 01 and PA 02.
PA01 is just the distribution work located within RTE 3 (including the culverts and parking area) that is designated as FHWA project limits . Coordination required with FHWA since this is majority of their project.
PA01 is everything NOT overlapping with FHWA work - FHWA will just come in after for paving.
01 11 00 Summary of Work outlines project area limits and shoudl match how the areas are designated in the drawings. Phase/schedule requirements for PA01 and 02 are laid out in Section 1.3 of 01 11 00 which is also why they are broken up into separate CLINs.
3 7/18/2024
The specs show medium voltage generator and a 208/120 3 phase generator in the drawings. Would you please clarify which is correct?
The generator is 208VAC as per drawings.
4 7/26/2024
Would please provide the well log for the existing well? Attached.
4 7/26/2024
Questions and Answers
Does a certified arborist approved by Glacier National Park need to perform the tree removal?
No - only coordination with Natural Resources Staff relative to the exact number of threes that will need to be cut.
4 7/26/2024
Is the work within Rte 3 CLIN 1 only the 10" HDPE section from Sta. 51+35.56 to 52+84.34 3" HDPE pipe section between Sta. 220+06.01-229+69.27?
See amendment to the specification Section 01 11 00 for revised pipe stations that are within the RT 3 CLIN 1.
4 7/26/2024
Would NPS states the limits of RTE 3 several times in the spec for CLIN 1 PA 01 so we can accurately include the correct costs for CLIN 1?
See amendment to specification Section 01 11 00 for revised pipe stations that are within the Rte 3 CLIN 1 4 7/26/2024
Questions and Answers
See amendment to specification Section 01 35 05 and list of sources from the park.
4 7/26/2024 Attached Approved Gravel and Topsoil Sources
Section 01 35 05-4 F states the following: “All imported borrow, road base, aggregate, crushed fines, bedding, topsoil, hay bales and other fill materials brought into Glacier National Park and used in this project shall be certified noxious weed and noxious weed seed free, and come from approved sources that have been previously inspected by the Park. Certified imported materials will come from commercial sources that have been approved by the CO, prior to materials entering the Park.
1) As of Spring 2019, six material sources on the west side of Glacier National Park were certified weed free for sand and gravel and none for topsoil (see physical data in FAR 52.236-4 for a summary of the materials sources research.)
2) If these sources are utilized, these sources are subject to continual inspections and approval for use each year.
3) All material sources and materials incorporated into the work, except Asphalt concrete aggregate (Subsection703.07) and those listed under Subsection 105.02@(8) must be free from noxious weeks, invasive plants and deleterious materials .
I can't find Subsection 703.07, Section 105.02 or FAR Clause 52.236-4 (Physical data). Would you please provide the information needed to determine the best source available to provide material for the project?
Questions and Answers
Plan Sheets C2.1&2.2 note 3.1 states "The parallel 10" and 4" mains are horizontally separated 3 ft from center of eachpipe. Would a greater separation between the two pipes be acceptable?
A separation larger than 3' between the parallel 10' and 4' water lines may require a larger trenching area, and therefore, a potentially greater disturbance area for trenching and filling; as a result, maintaining pipes as close to 3' separation as possible is preferred. However, alternative pipe separations may be considered if proposed by the Contractor, provided construction disturbance stays within the limits of the existing roadway.
4 7/26/2024
In the specs for temporary water it calls for the potable water pump to be capable of 80 gpm. This does not give us enough information of the anticipated demand on how much water usage that is anticipated so we can accurately estimate the effort that will be needed to supply enough water to NPS staff. What is the anticipated water demand needed on a daily basis for the project?
The temporary water system is sized to the daily anticipated demand for the maximum number of resident staff.
3,000 gallons per system, there are two systems so 6,000 gallons total. She sheet C6.1 detail 1, and specification 01 50 05, 2.4 B.1
4 7/26/2024
Would DR HDPE pipe be acceptable for the 4" fill and 10" distribution from the tank to the intersection of the loop road approximately 850 lf for both?
DR-9 is acceptable as long as it doesn't incur any extra cost to the NPS.
Questions and Answers
On plan sheet X1.2 Note 2 it s tates “Contractor shall coordinate with utility company to refeed chlorination building per electrical one-line diagram. Would you please clarify who is responsible to pay for these fees?
It is very difficult to get prices out of utility companies before bids are due FYI.
The contractor is responsible for payment of any fees associated with this scope of work. 4 7/26/2024
The tank coating Spec 07 16 16 indicates that application of coatings need to be under the supervision of an inspector.
The next spec then indicates that at theoption of the owner, the owner may hire a full time coating inspector. This is a little confusing can you confirm if the contractor is required to have their own inspector or will one be owner provided?
For the water storage tank coating, the contractor is required to provide an inspector. The owner reserves the right to contract their own coating inspector, independent of the contractor provided inspector.
4 7/26/2024
Building 484 on Sheet C2.31 doesn't contain a call out. Can you confirm the size and length.
Service to building 484 is 78 lf of 2" HDPE water service line.
4 7/26/2024
Building 1356 contains 2 service connections. Can you confirm this is correct?
Correct. One for domestic water and one for fire suppression system. 4 7/26/2024
Can you confirm if the Temporary Fire Protection Tanks need to be 10,000 gallons each (20k total) or if the combined capacity is to be 10,000 gallons.
See specification section 01 60 06, 2.4.B.1
4 7/26/2024
Would an alternative to Crystalline Cementitious Waterproofing be acceptable. Obic 1100 Aromatic Polyurea Coating was offered by one installer.
The product suggested will be evaluated according to the relevant specification and if it meets the requirements, it is acceptable.
Questions and Answers
The details of the water meter vaults reference 6, 8", 10" connections. I found 2 - 8" meters and 2 - 10" meters but do not see a 6" meter. Is there a 6" meter for the project and if so where is it located?
There are no 6" meters in the project
4 7/26/2024 68 Are the well pumps on VFD's? No 5 7/30/2024
Based on the Answer to #59 regarding temporary water.
Is the NPS anticipating that both tanks will need to be filled daily?
It is up to the contractor to determine the amount and frequency of tank filling operations based on the size of tanks the contractor anticipates utilizing during the performance of the work.
5 7/30/2024
The specs indicate that the HDPE on this project can be IPS or DIPS. I just want to confirm that IPS is acceptable to make sure my costs are covered.
Yes, both IPS and DIPS are acceptable. See Spec Section 33 31 23 Fusible HDPE.
5 7/30/2024
Are there any domestic material requirements on this project? If so, which would apply (BABA, Buy American Act, etc)?
The Buy American Act is applicable to this procurement. Please see solicitation clause 52.225-11 Buy American - Construction Materials Under Trade Agreements (NOV 2023)
5 7/30/2024
Can you clarify if the Obic 1100PW material alternative is acceptable for the tank lining?
Please see Q66 - The product will be evaluated based on the salient features of specification 07 16 16.
Generally we do not do shop drawing review for anything before the contractor is under contract.
5 7/30/2024
Site Name: SWIFTCURRENT CAMPGROUND
GWIC Id: 89677
Section 1: Well Owner(s)
1) NATIONAL PARK SERVICE (MAIL)
GLACIER NATIONAL PARK
WEST GLACIER MT 59936 [06/25/1999]
2) UNITED STATES DEPARTMENT OF THE INTERIOR
NATIONAL PARK SERVICE (MAIL)
N/A
WEST GLACIER MT 59936 [07/05/1978]
Section 2: Location
Township Range Section Quarter Sections
35N 16W 14 SE¼ NE¼ NE¼ NE¼
County Geocode
GLACIER
Latitude Longitude Geomethod Datum
48.7963 -113.6742 MAP NAD27
Ground Surface Altitude Ground Surface Method Datum Date
Addition Block Lot
Section 3: Proposed Use of Water
PUBLIC WATER SUPPLY (1)
Section 4: Type of Work Drilling Method: FORWARD ROTARY Status: NEW WELL
Section 5: Well Completion Date Date well completed: Wednesday, July 5, 1978
Section 6: Well Construction Details Borehole dimensions
From To Diameter
0 70 10
Casing
Wall
Thickness
Pressure
Rating Joint Type
0 47.8 8 PVC-SCHED 40
42.7 70 6 WELL SCREEN
Completion (Perf/Screen)
# of
Openings
Size of
Openings Description
42.7 47.8 6 80 SLOT SS SCREEN
47.8 62.7 6
100 SLOT SS
SCREEN
Annular Space (Seal/Grout/Packer)
From To Description
Cont.
Fed?
0 17.7 11 BAGS CEMENT
Section 7: Well Test Data
Total Depth: 70 Static Water Level: 20 Water Temperature:
Pump Test *
Depth pump set for test feet.
150 gpm pump rate with feet of drawdown after 24 hours of pumping.
Time of recovery hours.
Recovery water level feet.
Pumping water level 20.5 feet.
* During the well test the discharge rate shall be as uniform as possible. This rate may or may not be the sustainable yield of the well. Sustainable yield does not include the reservoir of the well casing.
Section 8: Remarks
Section 9: Well Log
Geologic Source
112DRFT - GLACIAL DRIFT
From To Description
0 10 GRAVEL AND SAND
10 30 SAND GRAVEL
30 66 SAND AND GRAVEL
66 70 SHALE
Driller Certification All work performed and reported in this well log is in compliance with the Montana well construction standards.
This report is true to the best of my knowledge.
Name:JR BILLMAYER
Company:BILLMAYER DRILLING
License No:WWC-5
Date
Completed:
7/5/1978
| Site Showing Questions and Answers.pdf |