B08_Section J Attachment 1_Specifications.pdf

PDF 12 MB Posted

Attached to
BISC Various Federal contract opportunity
Solicitation number
140P2020R0147
Issued by
Department of the Interior National Park Service National Office

About this file

This solicitation from the National Park Service seeks proposals for multiple hurricane repairs at various Biscayne National Park sites. Offerors are invited to submit proposals by February 14, 2022 for repair projects at BISC 244358, 244359, 244361, 244362, 244363, 251121, and 251215 involving damages from hurricanes. Award is expected by March 31, 2022. The repairs include a range of construction services to restore buildings, facilities, and infrastructure at the national park sites to pre-hurricane conditions. Proposals should include pricing and schedules to complete all work by December 31, 2022. Small businesses, HUBZone certified, service-disabled veteran-owned, and women-owned small businesses are encouraged to compete.

View the file

Other files for this federal contract opportunity

Other files attached to BISC Various, newest first.
File Type Posted
Amendment 5_0007.pdf PDF
Sol_140P2020R0147_Amd_0007.pdf PDF
RFIs and Responses-11.25.20_0007.pdf PDF
Amendment 4_0006.pdf PDF
Sol_140P2020R0147_Amd_0006.pdf PDF
Amendment 3_0005.pdf PDF
BISC Multiple Hurricane Repairs GeoTechnical Report_0005.pdf PDF
Sol_140P2020R0147_Amd_0005.pdf PDF
SOLICITATION 140P2020R0147 RFIs and Responses_0004.pdf PDF
Contracting PreBid Powerpoint Updated 102920_0004.pdf PDF
Attendance List_0004.pdf PDF
Sol_140P2020R0147_Amd_0004.pdf PDF
Amendment 2_0004.pdf PDF
Solicitation 140P2020R0147 Updated 10292020_0004.pdf PDF
Sol_140P2020R0147_Amd_0003.pdf PDF
Solicitation 140P2020R0147 Updated 10262020_0002.pdf PDF
Amendment 1_0002.pdf PDF
Sol_140P2020R0147_Amd_0002.pdf PDF
Contracting PreBid Powerpoint_0002.pdf PDF
B08_Section J Attachment 6a Contracting Powerpoint.pptx PPTX presentation
B08_Solit_PSP_Vol_II_GenRefs.doc DOC document
B08_Section J Attachment 2_Drawings.pdf PDF
B08_Section J Attachment 4_Wage Determination.pdf PDF
B08_Solit_PSP_Vol_II_Equals.doc DOC document
B08_Solit_PSP_Vol_I_PastPerf_REQD.docx DOCX document
B08_Solit_PSP_Vol_I_Exp_REQD.docx DOCX document
B08_Solit_PSP_Cover.rtf RTF text file
B08_Section J Attachment 3_Contract Price Schedule.xlsx XLSX spreadsheet
Sol_140P2020R0147.pdf PDF
B08_Section J Attachment 6a Technical Powerpoint.pptx PPTX presentation
B08_Solit_PSP_Vol_II_HazMat.doc DOC document
B08_Solit_PSP_Vol_II_BidBond.pdf PDF
B08_Solit_PSP_Vol_II_SubKPlanForm_REQD.doc DOC document
Show all 33

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Repair Hurricane Irma Related Damage at Biscayne National Park – Final CD Draft June 2020

National Park Service

Repair Hurricane Irma Related Damage at

Biscayne National Park BISC-PMIS 244358A, 244359A, 244361A, 244362A, 244363A, 251121A, and 251215A

FINAL CD Specifications

June 19, 2020

Prepared by:

Jacobs Engineering Group, Inc.

Jacksonville, FL

Contract No. P15PC00018 Task Order No. P16PD01166

Biscayne National Park HIM BISC Hurricane Repairs Design Calculations

Jacobs Engineering Group, Inc.

200 West Forsyth Street, Suite 1520 Jacksonville, FL 32202 904.636.5432

CA# 2822

Engineer of Record for Division 1, Sections 02 41 00 to 06 15 00, and 31 23 23 to 231 63 00

Maxwell Reese Mozo

PE #56151

Engineer of Record for Sections 26 05 02 to 26 31 00

Marc Paul Goslow

PE # 41733

mmozo disclaim mmozo marc mmozo Mozo mmozo

MARC

mmozo Max Sign

BISC – 251215 TOC-1

TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 Summary of Work 01 26 01 Contract Modification Procedures 01 27 00 Definition of Contract Line Items 01 31 00 Project Management & Coordination 01 32 16 Construction Schedule 01 33 23 Submittal Procedures 01 35 13.22 Archeological Protection 01 35 23 Safety Requirements 01 40 00 Quality Requirements 01 50 00 Temporary Facilities and Controls 01 57 23 Temporary Storm Water Pollution Prevention 01 73 40 Execution 01 74 19 Construction Waste Management and Disposal 01 77 00 Closeout Procedures 01 78 23 Operation and Maintenance Data

DIVISION 02 – TECHNICAL SPECIFICATIONS

02 41 00 Demolition 03 10 00 Concrete Formwork 03 20 00 Concrete Reinforcement 03 30 00 Cast In Place Concrete 03 40 00 Precast Concrete 03 41 33 Precast Prestressed Concrete Deck Units 05 50 00 Metal Fabrications 06 10 00 Rough Carpentry 06 15 00 Wood Decking 26 05 02 Basic Electrical Requirements 26 05 04 Basic Electrical Materials and Methods 26 05 05 Conductors 26 05 26 Grounding and Bonding for Electrical Systems 26 05 33 Raceway and Boxes 26 08 00 Commissioning of Electrical Systems 26 31 00 Standalone Packaged Photovoltaic System 31 23 23 Fill and Backfill 31 62 13 Precast Prestressed Concrete Piles 31 63 13 Helical Piles 31 63 00 Concrete Floating Dock System

Attachment 1 – Elliot Key Additional Debris Recovery and Disposal

BISC - 251215 01 11 00 - 1

091015 SUMMARY OF WORK

SECTION 01 11 00 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes the following:

1. Work covered by the Contract Documents.

2. Work phases.

3. Work under other contracts.

4. Government Furnished Materials.

5. Contractor use of premises.

6. Public use of site.

7. Occupancy requirements for buildings.

8. Work Restrictions.

9. Special Construction Requirements.

10. Soils Investigation Report.

11. Additional Reports.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Location: Biscayne (BISC) National Park, Homestead, FL. Work will be performed on park lands at Black Point Park, and at the Convoy Point Headquarters. Work will also take place offshore at Boca Chita Key, Elliot Key and Adams Key.

B. The Work consists of the following:

1. The Work includes various demolition, repairs, earthwork, redecking, replacement of floating docks, and replacement of boardwalks and fixed concrete dock..

C. Project will be constructed under a single prime contract.

1.3 CONTRACTOR USE OF SITE

A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to work in areas indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Limits: Confine constructions operations to:

a. Areas of Park Entrance Road that require shoulder repair.

b. Convoy Point north shore Boardwalk, east shore Boardwalk, Footbridge, and Jetty

c. Convoy Point Visitor ’s Center Docks

d. Convoy Point NPS Area Docks

e. Black Point Jetty Trail, NPS property

f. Boca Chita Key, Northeast Beach Area, Southeast Beach Area behind Barn and

Stockpile Area behind bard.

BISC - 251215 01 11 00 - 2

g. Elliot Key, eastern boardwalk

h. Adams Key Dock and Ramp (Barge work only)

2. Limit site disturbance, including earthwork and clearing of vegetation, to 40 feet beyond building perimeter; 10 feet beyond surface walkways, patios, surface parking, and utilities less than 12 inches in diameter; 15 feet beyond primary roadway curbs and main utility branch trenches; and 25 feet beyond constructed areas with permeable surfaces (such as pervious paving areas, storm water detention facilities, and fields) that require additional staging areas in order to limit compaction in the constructed area.

B. Storage of Materials: Confine storage of materials to laydown areas listed below:

1. Maintenance area west of parking lot at Convoy Point for all Convoy Point projects storage and material stockpiling.

2. Area behind barn for material stockpile on Boca Chita Key. Material stockpile shall be protected by lockable security fencing, with barbed wire or other protection at top to discourage climbing. Materials may be offloaded from barge but barge must not dock overnight.

3. Elliot Key laydown area shall be at the southern trailhead of the boardwalk to be removed. Laydown area currently contains deck units from boardwalk which must be disposed of or recycled prior to additional materials being stockpiled for removal.

4. Adams Key laydown area shall be a material barge provided by the contractor. No upland storage is permitted at this site. Barge must be moored in approved areas and must have solar warning lights per USCG rules.

5. Black Point Jetty has no area for material stockpiles. Material must be delivered and immediately installed. Area may be available for a 20’ shipping container (connex box) to be placed in a parking space at the park to store equipment.

C. Preservation of Natural Features:

1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.

2. Provide temporary barriers to protect existing trees and plants and root zones.

3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer and remove agreed-on roots and branches that interfere with construction.

4. Do not fasten ropes, cables, or guys to existing trees.

5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.

D. Driveways and Entrances: Keep driveways parking lots and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

1. Schedule deliveries to minimize use of driveways and entrances.

2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

E. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A

BISC - 251215 01 11 00 - 3

special permit will not relieve Contractor of liability for damage which may result from moving of equipment.

1.4 PUBLIC USE OF SITE

A. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public.

Shutdown of specific areas of the park where work is underway is required. In addition, partial road closures will be permitted, when required for work along the park entrance road. A flagman will be required when operations occupy a full lane and traffic visibility is impaired. Coordinate shut downs of park areas with Contracting Officer and park Public Safety Officer as well. Areas of the park that are temporarily closed for construction use shall be secured with temporary fencing to prevent visitor access to the site. This includes the trailhead at Black Point Jetty, Convoy Point Jetty, and along the wall at the convoy point boardwalk to prevent sudden drop offs.

1.5 CONDUCT OF OPERATIONS

A. At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.

B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed without prior consent from the Contracting Officer. Submit requests 48 hours in advance of the work to the Contracting Officer for approval.

C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.

1.6 WORK RESTRICTIONS

A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 8 a.m. to 5 p.m., Monday through Friday, except when otherwise indicated.

1. Weekend Hours: No weekend hours permitted.

2. Early Morning Hours: Offshore locations may be accessed during daylight hours.

B. Existing Utilities

1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.

2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.

3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

BISC - 251215 01 11 00 - 4

1. Notify Contracting Officer not less than two days in advance of proposed utility interruptions.

2. Do not proceed with utility interruptions without Contracting Officer’s written permission.

3. Hours for Utility Shutdowns: Utility Shutdowns may occur between 8am and 5pm for a 15 minutes shutdown or less. After hours or Before hours shutdowns may be longer and will be addressed on a case by case basis.

D. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor air intakes.

1.7 SPECIAL CONSTRUCTION REQUIREMENTS

A. All work at Adams Key shall be performed by barge only.

B. Replacement of Convoy Point Footbridge decking, stringers and caps shall be performed from the surface of the existing walkway. Barge use is not feasible due to shallow waters. The contractor may work from a temporary platform supported by existing concrete piles and work from an end on or top down methodology

C. The work on Boca Chita key shall be performed outside of sea turtle nesting season if practical.

The season is from March to October. If work occurs during this time frame, the site shall be monitored by Park Staff to ensure that no turtles have nested within the site.

D. Care shall be taken to identify, locate and protect Wilson’s Plover and Piping Plover nests located in the work area.

E. When performing in water work, an experienced Manatee and Sea Turtle spotter shall be used. If a Manatee or sea turtle are within 50’ of active work, work shall cease until the animal has moved out of the affected area. The spotter shall produce daily logs in accordance with Florida Fish and Wildlife rules.

F. Attachment 1 of these specifications includes additional debris to be recovered and removed from Elliot Key and disposed of in accordance with these specifications.

1.8 SOILS INVESTIGATION REPORT

A. A soils investigation report will be provided upon completion of the subsurface investigation.

Previous geotechnical reports are available.

B. A copy of the previous report is available to all plan holders with this package.

C. If conflicts occur between the report and drawings or specifications, the drawings and specifications govern.

BISC - 251215 01 11 00 - 5

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 11 00

BISC - 251215 01 26 01 - 1

031414 CONTRACT MODIFICATION PROCEDURES

SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. The work of this section consists of administrative and procedural requirements for contract modifications.

1.2 DEFINITIONS AND ALLOWANCES

A. Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):

1. Rent

2. Utilities

3. Furnishings

4. Office equipment

5. Executive and management staff not exclusively assigned to the project

6. Support, accounting, and administrative staff

7. Preparation of cost proposals, estimating, and schedule analyses connected with

Modifications

8. Estimating and preconstruction services

9. Mortgage costs

10. Real estate and corporate taxes

11. Automobile maintenance and travel costs for home office personnel

12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.

13. Depreciation of equipment and other assets

14. Home office supplies (paper, staples, etc.)

15. Legal services

16. Accounting and data processing

17. Professional fees/registration

B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:

1. Project Manager, Assistant Project Manager

2. Superintendent, Assistant Superintendent

3. Quality Control, Safety Officer, Environmental Manager, etc.

4. Engineers

5. Travel, lodging, and per diem (as established by Federal Travel Regulations)

BISC - 251215 01 26 01 - 2

6. Scheduling

7. Field Office Trailers and associated temporary utilities

8. Field office supplies

a. Mailing and couriers

b. Reproduction costs

c. Storage

d. Phones

e. Computers

f. Copiers

9. Personal vehicles i.e. Superintendent Pickup trucks

C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating General Requirements:

1. Hoisting

2. Material handling

3. Temporary fencing

4. Port-a-lets

5. Trash removal, dumpsters

6. Barricades

7. Small tools

8. Safety supplies

9. Scaffolding

10. Daily cleaning

11. Traffic control

12. Temporary signage

13. Temporary heating and power

D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40 hour week and no overtime or holiday pay will be allowed.

1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:

a. Base Rate: This is the hourly rate paid directly to the worker

b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums , such as:

1) Social Security

2) Medicare

3) Workers Compensation– Policy and company calculation to be made available.

4) FUTA– Cap Rate and percentage to be proportionally allocated over one year.

5) SUTA– Cap Rate and percentage to be proportionally allocated over one year.

BISC - 251215 01 26 01 - 3

6) Union agreement costs – Other costs required under an enforceable collective bargaining agreement.

c. Fringe Benefits: Various non-wage compensations provided to employees such as:

1) Health Care Insurance Premiums

2) Cell Phone

3) Clothing

4) 401K and Pensions

5) Vehicle allowances

6) Gas allowance

7) Life insurance premiums

8) Disability insurance

9) Other Fringe Benefits required under an enforceable collective bargaining agreement

E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.

F. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.

G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.

H. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.

1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS

A. General:

1. Your proposal must be received in the format and within the time frame specified in the Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.

2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may utilize the government provided Contractor Estimate http://en.wikipedia.org/wiki/Employee http://en.wikipedia.org/wiki/Surety_bond http://en.wikipedia.org/wiki/Insurance http://en.wikipedia.org/wiki/Bank http://www.nps.gov/dscw/publicforms.htm#ct

BISC - 251215 01 26 01 - 4

Form, or their own form, provided that it contains the same information and level of detail as the Gov’t provided form.

3. Requests for extensions of contract time as a result of this change must be justified with a Time Impact Analysis (TIA). Refer to Division 01 Specification, “Construction Schedule”, for time impact analysis requirements. TIA and associated costs must be received with the proposal by the date shown within the Request for Proposal letter.

Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving the right for additional time and no time extension will be allowed.

4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.

5. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS.

All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.

6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.

B. Labor:

1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work.

Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.

2. Itemize labor costs for equipment operators separate from equipment costs.

3. The labor cost for foremen shall only be costs for related work required for the modification.

C. Materials:

1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.

2. No markup shall be applied to any material provided by the NPS.

D. Equipment:

1. Equipment used for the project must be appropriately sized for the work being performed.

2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.

3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:

a. U.S. Army Corps of Engineers , Ownership and Operating Expense Schedule (use latest edition and applicable region)

BISC - 251215 01 26 01 - 5

b. Construction Blue Book

c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.

4. The estimated equipment rates shall include the operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per FAR 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.

5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.

6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above. If the US Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs, major repair and overhaul will be accepted.

7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.

8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.

9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.

10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.

E. Establishment and Application of Overhead and Profit Percentages:

1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.

Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:

Overhead………………10% Profit………………10%

2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.

3. If contractors form a partnership, than the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3,E,1 above). It is the responsibility of the partners to decide on the division of revenue.

4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.

BISC - 251215 01 26 01 - 6

5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.

PART 2 - PRODUCTS

PART 3 - EXECUTION

END OF SECTION 01 26 01

BISC - 251215 01 27 00 - 1

082714 DEFINITION OF CONTRACT LINE ITEMS

SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS

PART 1 - GENERAL

1.1 SUMMARY

A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.

B. If no contract line item exists for a portion of the work, include the costs in a related item.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 LIST OF CONTRACT LINE ITEMS

A. Contract Line Item No. 0001 Contract General Conditions

1. This item consists of the cost to perform the work in the contract not specifically listed in items below. It is the cost to perform all management and provide for all requirements of the contract general conditions.

2. Measurement for payment will be Lump Sum.

3. Payment will be made at the contract lump sum price.

B. Contract Line Item No. 0002 PMIS 244359 Repairs to Blackpoint Jetty Trail.

1. This item consists of the fill and grading of areas of shoreline erosion shown on the drawings. The item includes all materials, equipment and labor to construct the repairs including additions of fill, trail material and rip rap. The trail will be raised to meet a minimum grade as shown on the drawings. The raising of the trail will require that Construction of 6 bridge raisings as needed to meet the proposed trail grade along Blackpoint jetty. It will include procurement and installation of all appurtenances shown on drawings including but not limited to trash receptacles, signage and other hardscape items.

2. Measurement for payment will be Lump Sum.

3. Payment will be made at the contract lump sum price.

C. Contract Line Item No. 0003 PMIS 244361 Repairs to Boardwalk and Trails at Convoy Point Visitor’s Center.

1. This item consists of all materials, equipment and labor required to complete the work shown on the contract documents, specifically:

BISC - 251215 01 27 00 - 2

a. Demolition and Replacement of Boardwalk between parking area and Footbridge as shown in plans. This includes construction of new timber boardwalk-foundations, framing and decking. All appurtenance shown in the plans including waste bins, lighting, benches and curbs.

b. Demolition of decking, stringers, and pile caps for footbridge. Construction of new pile caps, stringers and decking. Removal, storage and reinstallation of handrail system on footbridge. Addition of new aluminum top rail for handrail system.

c. Construction of boardwalk on Convoy Point Jetty. This includes construction of new timber boardwalk- foundations, framing and decking. All appurtenance shown in the plans including waste bins, benches and curbs.

d. Fill and grading of the Convoy Point Jetty trail including fill, trail material, and rip rap. The trail bed will be raised to meet the minimum elevation as shown on the plans.

2. Measurement for payment will be Lump Sum.

3. Payment will be made at the contract lump sum price.

D. Contract Line Item No. 0004 PMIS 244362 Repairs to Boardwalk on Elliot Key.

1. This item consists of the materials, equipment and labor required for the demolition, removal from the island, and disposal/recycling of all demolition debris related to the complete demolition of the Elliot Key Boardwalk. This includes removal and disposal/recycling of all stockpiled deck units as well as damaged wayside signs.

2. Measurement for payment will be Lump Sum.

3. Payment will be made at the contract lump sum price.

E. Contract Line Item No. 0005 PMIS 244363 Repairs to Docks at Convoy Point Waterfront.

1. This item consists of all materials, equipment, and labor required to complete the work shown on the contract documents, specifically:

a. The demolition, removal and disposal/recycling of the existing floating docks located adjacent to the park visitor’s center as well as the NPS operations area.

b. The design, procurement, and installation of new floating docks and associated electrical and mechanical system at the visitor’s center and NPS operations area.

This includes the docks, reusing gangways, reusing existing piles, installing new piles (per 1c. below), connections, electrical power and water system connections to the existing system, shore power and water pedestals.

c. Furnish and Install 10 ~ 14” x 14” prestressed concrete piles.

d. Demolish deck topping and existing timber fender components for the two fixed docks adjacent to boat ramp. Install new topping, reinstall cleats, and install new timber fender system as shown in plans.

e. Install two new floats at Visitor’s Center gangway.

2. Measurement for payment will be Lump Sum.

3. Payment will be made at the contract lump sum price.

F. Contract Line Item No. 0006 PMIS 251215 Repairs to Park Entrance Road.

1. This item consists of the fill and grading of areas of shoreline erosion shown on the plans.

The shoreline will be filled and stabilized with the addition of rubble rip-rap as shown on the drawings. The item includes all materials, equipment and labor to construct the repairs including additions of fill, and rip rap.

BISC - 251215 01 27 00 - 3

2. Measurement for payment will be Lump Sum.

3. Payment will be made at the contract lump sum price.

G. Option A PMIS 244358 Repair Shoreline Erosion on Boca Chita Key

1. Contract Line Item No. 0007

a. This item consists of the material, equipment and labor for the fill and grading of shoreline repairs to the Eastern shoreline of Boca Chita Key as shown in the contract documents. Fill to be placed above Mean High Water oly

b. Measurement for payment: Lump Sum.

c. Payment will be made at the contract lump sum price.

H. Option A PMIS 251121 Replace Adams Key Dock

1. Contract Line Item No. 0008

a. This item consists of the demolition, removal from island and disposal/recycling of all demolition debris from the removal of the Adams Key Boat Dock. It also includes all labor, equipment and materials to construct new dock as shown on plans. This includes new foundation, substructure and deck. It includes temporary relocation of fuel offloading devices and reinstallation on new structure.

Contractor shall provide temporary flexible hose and temporarily relocated fueling manifold connected to fuel tank with this hose. It includes new light pole and removal and reinstallation. 5 new timber piles will be installed at the boat ramp area.

b. Measurement for payment: Lump Sum.

I. Payment will be made at the contract lump sum price.

END OF SECTION 01 27 00

BISC - 251215 01 31 00 - 1

091015 PROJECT MANAGEMENT AND COORDINATION

SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. Definitions

2. Construction Coordination.

3. Submittals

4. Coordination Drawings.

5. Requests for Information (RFIs).

6. NPS/DSC SharePoint Project Website.

7. Project meetings.

8. Environmental Coordination.

9. Permits

B. Related Requirements:

1. Section 01 32 16 “Construction Schedule” for preparing and submitting Contractor’s construction schedule.

2. Section 01 73 40 “Execution” for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

3. Section 01 77 00 “Closeout Procedures” for coordinating closeout of the Contract.

1.2 CONSTRUCTION COORDINATION

A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.

5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.

BISC - 251215 01 31 00 - 2

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of Contractor's Construction Schedule.

2. Preparation of the Schedule of Values.

3. Installation and removal of temporary facilities and controls.

4. Delivery and processing of submittals.

5. Progress meetings.

6. Permit requirements.

7. Pre-installation conferences.

8. Project closeout activities.

9. Commissioning activities.

1.3 SUBMITTALS

A. Division 01 documents: The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference.

1. Letter designating Project Superintendent.

2. Construction Schedule.

3. A comprehensive breakdown of the Schedule of Values.

4. Accident Prevention Plan.

5. A list of Subcontractors for this project.

6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.

7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the Contactor and all subcontractors.

8. Waste Management Plan.

9. Quality Control Plan.

10. Temporary Storm Water Pollution Prevention Plan (SWPP or UPPP).

11. Contractors Commissioning Plan.

12. List of Required Construction Permits. Include the following information for each permit:

a. Name of Permit.

b. The Agency(ies) with Jurisdiction issuing the permit.

c. Information required from the Government to complete the permit application.

B. All items listed must be provided to the Contracting Officer before the Pre-Construction Conference is held. If all of these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the Contracting Officer will consider other contractual remedies.

Work shall not commence until written Notice to Proceed has been issued.

BISC - 251215 01 31 00 - 3

1.4 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI utilizing the form created on the NPS/DSC SharePoint Project website.

1. CO will not respond to RFIs submitted by other entities controlled by Contractor.

2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:

1. RFI number, numbered sequentially.

2. Date.

3. RFI subject.

4. Specification Section number and title and related paragraphs, as appropriate.

5. Drawing number and detail references, as appropriate.

6. Field dimensions and conditions, as appropriate.

7. Contractor's suggested resolution. If Contractor's suggested resolution impacts the

Contract Time or the Contract Sum, Contractor shall state impact in the RFI.

8. Contractor's signature.

9. Requested date for response.

10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop

Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

C. RFI Form: Complete the RFI Form on the NPS/DSC SharePoint website as follows:

1. Enter the general information at the top of the form.

2. Under the “Action” section at the bottom of the form, select “Question” then select

“CMR” in the drop-down of the “Send to” box.

3. Enter the details of the question and attach related documents.

4. Select “Submit Form” at the bottom of the page.

D. Contracting Officer’s Action: CO will review each RFI, determine action required, and respond. CO will determine the critical nature of each RFI and issue a response accordingly.

1. The following are not considered to be RFIs and will receive no action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for approval of Contractor's means and methods.

d. Requests for coordination information already indicated in the Contract

Documents.

e. Requests for adjustments in the Contract Time or the Contract Sum.

f. Requests for interpretation of Architect's actions on submittals.

g. Incomplete RFIs or inaccurately prepared RFIs.

BISC - 251215 01 31 00 - 4

2. CO's action may include a request for additional information, in which case time for response will date from time of receipt of additional information.

3. CO's action on RFIs may result in the need for a change to the Contract Time or the Contract Sum. All contract changes will be processed following the terms and conditions of the contract.

1.5 PROJECT WEB SITE

A. Use the NPS/DSC SharePoint Project website for communication throughout the contract period. The NPS/DSC SharePoint Project website will be used for the following functions:

1. Project directory.

2. Project correspondence.

3. Meeting agendas and minutes.

4. Contract modifications forms and logs.

5. RFI form and processing.

6. Task and issue management.

7. Photo documentation.

8. Baseline schedule, schedule updates and calendar management.

9. Submittal form and processing.

10. Payment coordination documentation.

11. Drawing and specification document hosting, viewing, and updating.

12. Online document collaboration.

13. Reminder and tracking functions.

14. Archiving functions.

15. Notification of submittal and RFI statuses and current responsible party.

16. Permits and addendums

B. Some documents however are not suitable to be shared using the NPS/DSC SharePoint Project website. Documents containing Personal Identifying Information (PII) (i.e. certified payrolls) shall not be shared using the NPS/DSC SharePoint Project website and shall be coordinated with the SharePoint Project team as appropriate.

C. Submit to the CO a list of all employees who will need access to the website. The users will receive an invitation to register from the Department of Interior (DOI). Once the user is registered on the DOI website, they will be given access to the NPS/DSC SharePoint Project website. For login procedures and other SharePoint information, refer to the Workflows website at http://www.nps.gov/dscw/precon_spproj.htm.

D. All users will be required to have the following software packages:

1. Internet Explorer version 7 or later.

2. Adobe Acrobat Professional (Pro) version 9 or later

1.6 PROJECT MEETINGS

A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. The meeting agenda will include the following as a minimum:

http://www.nps.gov/dscw/precon_spproj.htm http://www.nps.gov/dscw/precon_spproj.htm

BISC - 251215 01 31 00 - 5

1. Roles & Responsibilities/ Lines of Authority.

2. Park rules and regulations.

3. Jobsite Safety.

4. Resolution of comments on required Division 01 documents.

5. Coordination of Subcontractors.

6. Labor law application.

7. Modifications.

8. Payments to Contractor.

9. Payroll reports.

10. Contract time.

11. Liquidated damages.

12. Contractor Performance Evaluation.

13. Display of Hotline posters.

14. Notice to proceed.

15. Correspondence procedures.

16. NPS/DSC SharePoint Project website.

17. Acceptance/rejection of work.

18. Progress meetings.

19. Submittal procedures.

20. NPS Final Accessibility Inspection.

21. Environmental requirements.

22. Permit requirements.

23. As-constructed drawings/operation and maintenance (O&M) manuals.

24. Saturday, Sunday, holiday and night work.

25. Reference materials.

26. Value engineering.

B. Progress Meetings: The Contracting Officer will schedule weekly meetings with the Contractor.

1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings.

All participants at the meeting shall be familiar with the Project and authorized to conclude matters relating to the Work.

2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. The meeting agenda will include the following:

a. Approval of minutes of previous meetings.

b. Submittal status.

c. Review of off-site fabrication and delivery schedules.

d. Requests for information (RFI) and other issues.

e. Modifications.

f. Work in progress and projected.

1) Status of required inspections (Special Inspections, Accessibility, etc.)

g. Inspections of work in progress and projected (Special inspections,

h. Construction Schedule update (provide updated CPM).

i. Status of Project Record Drawings and O&M manuals.

j. Other business relating to work.

k. Permit requirements.

BISC - 251215 01 31 00 - 6

C. Preinstallation Conferences: Conduct a preinstallation conference at Project site before each construction activity that requires coordination with other construction.

1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise CO of scheduled meeting dates.

2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:

a. Contract Documents.

b. Options.

c. Related RFIs.

d. Related Change Orders.

e. Purchases.

f. Deliveries.

g. Submittals.

h. Review of mockups.

i. Possible conflicts.

j. Compatibility requirements.

k. Time schedules.

l. Weather limitations.

m. Manufacturer's written instructions.

n. Warranty requirements.

o. Compatibility of materials.

p. Acceptability of substrates.

q. Temporary facilities and controls.

r. Space and access limitations.

s. Regulations of agency(ies) with jurisdiction.

t. Testing and inspecting requirements.

u. Installation procedures.

v. Coordination with other work.

w. Required performance results.

x. Protection of adjacent work.

y. Protection of construction and personnel.

3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.

4. Reporting: Distribute minutes of the meeting to each party present and to other parties requiring information.

5. Do not proceed with installation if the conference cannot be successfully concluded.

Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.

1.7 ENVIRONMENTAL COORDINATION

A. Contractor’s Environmental Manager: Designate an on-site party responsible for overseeing the Contractor’s conformance to environmental goals for the project and implementing procedures for environmental protection.

BISC - 251215 01 31 00 - 7

1. Qualifications: Minimum 3 years Construction experience on projects of similar size and scope; with environmental procedures similar to those of this project; must be familiar with environmental regulations applicable to construction operations.

2. Responsibilities: Responsibilities shall include:

a. Compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.

b. Implementation of the Waste Management Plan(WMP).

c. Implementation of the Storm Water Pollution Prevention Plan(SWPPP).

d. Present an overview of environmental issues and summarize site specific procedures relating to management plans at the Preconstruction conference.

e. Training for Contractor personnel in accordance with their position requirements.

f. Monitoring and documentation of environmental procedures.

B. Perform project quality control in accordance with requirements specified in Related Sections, including:

1. Quality Requirements.

2. Regulatory Requirements.

3. Temporary Storm Water Pollution Prevention Environmental Management.

4. Construction Waste Management.

C. Contractor’s Environmental Training Program: Contractor shall provide environmental training for workers performing work on the project site. Training shall include the following:

1. Overview of environmental issues related to the building industry.

2. Overview of environmental issues related to the Project.

3. Review of site specific procedures and management plans:

a. Construction Waste Management.

b. Temporary Storm Water Pollution Prevention.

4. Compliance with environmental regulations: As specified in Regulatory Requirements.

Submit Contractor 40 CFR employee training records upon request of Contracting Officer.

D. Provide documentation for environmental procedures as specified herein and in accordance with approved Waste Management Plan, IAQ Management Plan, and Storm Water Pollution Prevention Plan.

1.8 PERMITS

A. General:

1. Permits and Responsibilities: The Contractor shall, without additional expense to the

Government, be responsible for obtaining any necessary licenses and permits, and for complying with any Federal, State and municipal laws, codes, and regulations applicable to the performance of the work. The Contractor shall also be responsible for all damages to persons or property that occur as a result of the Contractor’s fault or negligence. The Contractor shall also be responsible for all materials delivered and work performed until completion and acceptance of the work.

BISC - 251215 01 31 00 - 8

2. For the purpose of this contract the Contractor will not be considered an agent of the Government. Therefore the Contractor will comply with the appropriate Federal, State and local laws.

B. Government Furnished Permits: During the development of the project’s design the permits listed below were negotiated and agreed to by the Government. The terms and provisions of these permits shall be adhered to for the duration specified in each permit.

1. Permits have been applied for and finalized permits will be issued to the contractor upon availability. Potential mitigations erquired for permits have been included in the construction documents.

C. Potential Permits: The permits listed below were identified during the design process as likely to be required based on typical means and methods of construction. The list is provided to assist the contractor in determining which permits will be required for the contract’s chosen means and methods. The list shall not be considered complete, as it is the responsibility of the contractor to determine means and methods, and obtain the required permits. It is the responsibility of the Contractor to obtain all permits required to legally conduct the work.

1. Electrical Utility Hookup – Florida Power and Light

2. Construction trailer, Utilities hookup permit – Miami Dade County

3. Stormwater Pollution Prevention Permit – EPA, FDEP

D. Coordination with Agency(ies) with Jurisdiction Issuing Permits

1. Coordination: Contact the Agency(ies) with Jurisdiction as needed and sufficiently in advance to avoid delaying the work: Coordinate meetings, reporting requirements, inspections, or any other requirements.

E. Administrative Procedures:

1. Coordinate scheduling and timing of required administrative provisions of project permits with Agency(ies) with Jurisdiction, Construction Manager, and Park to avoid conflicts and to ensure orderly execution of the Work.

2. Supply all needed information to Agency(ies) with Jurisdiction issuing permits, pay any fees required and provide all material needed to comply with the permit’s conditions and provisions.

3. Upload permits to the NPS/DSC SharePoint project website when the permits are obtained.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 31 00

BISC - 251215 01 32 16 - 1

031414 CONSTRUCTION SCHEDULE

SECTION 01 32 16 – CONSTRUCTION SCHEDULE

PART 1 - GENERAL

1.1 SUMMARY

A. This Section consists of Construction Schedule requirements including but not limited to the following:

1. Schedule of Values

2. Construction Schedule Requirements.

3. Construction Schedule Updates.

4. Time Impact Analysis.

B.…