B08_DRTO 241934_Solicitation - Attach 01 Final Specifications.pdf
PDF 9 MB Posted
- Attached to
- DRTO 241934 - Harbor LighthouseDry Tortugas Nati
- Solicitation number
- 140P2020R0004
About this file
This solicitation is for the preservation, repair and rehabilitation of the 1876 Tortugas Harbor Lighthouse located at Dry Tortugas National Park in Florida. The project will be completed in three phases: disassembly of the lighthouse, treatment of components off-site, and reinstallation. Phase I involves disassembling and removing the lighthouse and scaffolding. Phase II treats components by removing finishes and hazardous materials, and fabricating replacements. Phase III transports components back to reinstall the lighthouse. The contract will be a single prime contract with a Notice to Proceed by June 1, 2020 and Phase III work between November and June. The contractor must plan transportation, staging and waste removal logistics given the remote island location. The National Park Service will provide existing scaffolding and crew boat transportation, while the contractor must provide all other resources, permits and insurance.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DRY TORTUGAS NATIONAL PARK
MONROE COUNTY, FLORIDA
PROJECT SOLICITATION NO. 140P2020R0004
PRESERVE TORTUGAS HARBOR LIGHTHOUSE
PMIS NO. DRTO 241934
PROJECT SPECIFICATIONS
CONSTRUCTION DOCUMENTS
NATIONAL PARK SERVICE
SOUTHEAST REGION
February 4, 2020
[This page intentionally left blank] kgawinek Snapshot kgawinek Stamp
DRTO - 241934 TOC-1
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 Summary of Work 01 26 01 Contract Modification Procedures 01 27 00 Definition of Contract Line Items 01 31 00 Project Management & Coordination 01 32 16 Construction Schedule 01 32 33 Photographic Documentation for Historic Preservation Projects 01 33 23 Submittal Procedures 01 35 13.22 Archeological Protection 01 35 23 Safety Requirements 01 35 91 Historic Preservation Treatment Procedures 01 40 00 Quality Requirements 01 42 00 Reference Standards 01 50 00 Temporary Facilities and Controls 015710 Moat Protection 01 57 19.12 Noise & Acoustics Management 01 57 23 Temporary Storm Water Pollution Prevention 01 67 00 Product Requirements 01 73 40 Execution 01 74 19 Construction Waste Management and Disposal 01 77 00 Closeout Procedures
DIVISION 02 – 34 TECHNICAL REQUIREMENTS
DIVISION 02 – EXISTING CONDITIONS
02 83 19 Lead-Based Paint Remediation
DIVISION 04 – MASONRY
04 01 20 Masonry Repointing and Repair
DIVISION 05 – METAL FABRICATIONS
05 03 12 Conservation Treatment for Wrought Iron 05 03 13 Conservation Treatment for Cast Iron 05 70 00 Decorative Metal
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES
06 10 00 Rough Carpentry 06 20 00 Finish Carpentry
DIVISION 07 – THERMAL AND MOISTURE PROTECTION
07 90 00 Joint Sealants
DRTO - 241934 TOC-2
DIVISION 08 – OPENINGS
08 81 00 Laminated Glass Glazing
DIVISION 09 – FINISHES
09 91 00 Paints and Coatings 09 96 00 High Performance Coatings 09 99 00 Cleaning and Surface Preparation
DIVISION 26 – ELECTRICAL
26 00 10 Electrical General 26 00 90 Electrical Performance Verification 26 11 00 Raceways 26 12 00 Building Wire and Cable, 600 VOLT 26 13 00 Boxes 26 14 30 Wiring Devices 26 17 00 Circuit and Motor Disconnects 26 19 00 Supporting Devices 26 45 00 Grounding 26 45 10 Lightning Protection System 26 47 10 Panelboards 26 47 50 Overcurrent Protection Devices 26 51 00 Luminaires 26 59 10 Lighting Control Devices
APPENDICES
Everglades & Dry Tortugas Hurricane Plan (Version 2018)
DRTO - 241934 01 11 00 - 1
091015 SUMMARY OF WORK
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes the following:
1. Work covered by the Contract Documents.
2. Work phases.
3. Work under other contracts.
4. Government Furnished Materials.
5. Contractor use of premises.
6. Public use of site.
7. Occupancy requirements for buildings.
8. Work Restrictions.
9. Special Construction Requirements.
10. Additional Reports.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: The project is located on Bastion 6 at Fort Jefferson, Dry Tortugas National Park, Garden Key, in Monroe County, Florida. Garden Key is located in the Gulf of Mexico approximately 68 miles west of Key West. Garden Key is only accessible by boat or seaplane. The logistics of transporting personnel, supplies, materials and equipment to the Dry Tortugas and maintaining a productive construction site far from the mainland will require careful planning and coordination by the Contractor.
B. The Work consists of the following:
1. The Work of this project involves the conservation, repair and rehabilitation of the 1876 Tortugas Harbor Lighthouse located on top of Bastion 6 at Fort Jefferson, Dry Tortugas National Park. The work shall be completed in three phases; Lighthouse Disassembly, Lighthouse Treatment and Lighthouse Reinstallation. Due to the extreme conditions of the site, the lighthouse shall be disassembled and transported to the mainland for conservation and repair. Following treatment, the lighthouse components shall be transported back to Garden Key and the structure reassembled in its original location.
Phase I - Disassembly
Existing government-furnished scaffolding/shoring shall be modified by Contractor as needed to facilitate disassembly of the lighthouse. Contractor shall disassemble scaffolding/shoring in coordination with lighthouse disassembly and store on Garden Key where directed by Contracting Officer. Architectural and electrical components shall be removed in advance of disassembly of lighthouse structure. All components shall be lowered to grade within the Parade Ground and transported from the base of Bastion 6, through the sally port to the main dock area for loading on a vessel and transported to an
DRTO - 241934 01 11 00 - 2
off-site, contractor-furnished facility. It is anticipated the Contractor will complete disassembly prior to June 1, 2020. Hurricane Season commences on June 1st. In the event of severe weather/hurricane, the contractor shall commence with their sever weather/hurricane plan located within their approved Safety Plan, which shall include securing all resources and materials within 72 hours of projected landfall and be able to demobilize all personnel from Garden Key no later than 48 hours out from projected land fall. Contractor shall return to site for continuation/completion of Phase I work upon receiving all clear notification from Government. Existing Government-furnished scaffolding/shoring becomes property of the Contractor at Notice to Proceed and shall be modified, as necessary, to complete the work and shall be properly disposed of upon completion of work.
Phase II – Treatment
Lighthouse components shall be transported to a location where repair and conservation shall take place. Prior to treatment it will be necessary to further disassemble lighthouse components into smaller elements to accommodate conservation and repair. As part of the treatment scope, existing finishes shall be removed and hazardous materials abated.
Treatment shall also include the fabrication of new compatible wrought and cast-iron components to repair areas lost to advanced corrosion. NPS personnel and their representatives shall be allowed access to treatment facility in order to observe treatment process and evaluate progress. New high-performance corrosion-resistant, durable finishes shall be applied to all lighthouse components.
Phase III – Reinstallation
Phase III includes erection of Contractor-furnished scaffolding and repairs to the masonry of the Bastion 6 stair tower, including re-pointing and the setting of new anchor bolts in the masonry walls. The repaired and conserved lighthouse components shall be transported back to Dry Tortugas for reinstallation in their original location on top of Bastion 6. The conserved elements shall be lifted back into place using the Contractor-furnished scaffolding, beginning with the base and progressing to the lantern. New wood floor structure shall be installed along with new wood flooring, wall and ceiling paneling. These elements shall be replaced in-kind. Treated doors and shutters removed during Phase I shall be reinstalled and upgraded electrical power and lighting fixtures shall be installed in the lighthouse and stair tower. The lantern shall receive new glazing, upgraded light fixtures, new ventilator ball and new lightning protection system. Demobilization will include, but not limited to removal of scaffolding installed during Phase III and its transportation from the island. Phase III must be completed between the months of November and June.
All work shall be performed in a manner that minimizes impacts to Park operations and visitor experience.
C. Project will be constructed under a single prime contract.
1.3 WORK PHASES
A. The Work shall be conducted in three phases in the following order, with each phase substantially complete before beginning the next phase. Final determination of substantial completion will be made by the CO at the end of each phase.
DRTO - 241934 01 11 00 - 3
1. Phase I: Disassembly of lighthouse and government-furnished scaffolding and transportation off-island. It is anticipated the Contractor will complete disassembly prior to June 1, 2020. Hurricane Season commences on June 1st. In the event of severe weather/hurricane, the contractor shall commence with their sever weather/hurricane plan located within their approved Safety Plan, which shall include securing all resources and materials within 72 hours of projected landfall and be able to demobilize all personnel from Garden Key no later than 48 hours out from projected land fall. Contractor shall return to site for continuation/completion of Phase I work upon receiving all clear notification from Government.
2. Phase II: Conservation treatment of the lighthouse components.
3. Phase III: Transportation to Garden Key and reassembly of the lighthouse in its original location on Bastion 6 at Fort Jefferson. Phase III - Reinstallation shall be completed between the months of November and June.
1.4 GOVERNMENT FURNISHED MATERIALS
A. Existing Scaffolding/Shoring: The lighthouse is currently shored with scaffolding, steel framing and wood framing. The existing scaffolding/shoring is being furnished to the Contractor at no cost. The existing scaffolding/shoring shall become property of the Contractor at Notice to Proceed and Contractor shall modify, as necessary, to facilitate disassembly of the lighthouse and remove and store shoring as directed by Contracting Officer. All scaffolding/shoring shall be properly disposed of upon completion of work.
1.5 CONTRACTOR USE OF PREMISES
A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to areas indicated on the drawings. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Limits: Confine staging and operations to Contractor work areas indicated on the drawings.
2. Contractor Mooring Area: Contractor Mooring Area shown on drawings will be available to Contractor vessels on a limited and temporary basis for loading and unloading of materials and equipment. The mooring area will not be available to the Contractor when the tour boat, NPS Ft. Jefferson or other official vessels (such as Coast Guard vessels) are scheduled to use the main dock. The Yankee Freedom III is moored at the main dock daily from approximately 10:15 am – 3:00 pm (See 1.4.A.10.e.1). The mooring times of other official vessels varies. Contractor vessels using the mooring area shall be relocated immediately following completion of their tasks. In order to provide temporary controls and limit public access to the area, the Contractor shall coordinate use of the mooring location with the Contracting Office. Contractor shall provide a minimum of 48hrs notice of any Contractor vessel arriving at DRTO. Contracting Officer will then provide the Contractor with a schedule for mooring at the dock. Vessels over 50 meters (164’) in length are not permitted to anchor in Garden Key Harbor.
3. Limits on Number of Contractor Personnel: The Contractor’s crew (including subcontractor personnel) shall not exceed ten (10) individuals staying overnight on Garden Key and using water and sewage utilities during a 24-hour period.
DRTO - 241934 01 11 00 - 4
4. Contractor Housing: There is one dormitory facility referred to as “The Crew’s Quarters” with bunk beds (10 beds total) that the Contractor may use to accommodate its staff. The cost of these accommodations is $450.00 per night. If assigned a different quarters, cost will be $45.00 per night per bed. Contractor shall include in its technical proposal the anticipated crew size. Further, during contract performance, the Contractor is responsible for tracking the number of beds used each month and making payment to Dry Tortugas National Park on a fixed payment schedule (every 3 months). The Contractor shall submit a report to the Government indicating the actual number of beds used by date with each payment. Facilities and supplies available in the Crew’s Quarters includes two toilets, two showers, one lavatory, one satellite television, three refrigerator/freezers, one freezer, one ice-maker, one microwave, two ranges/ovens, two coffee makers, pots, pans and tableware. The Contractor agrees that its staff shall not damage these accommodations and shall use reasonable amounts of electricity, water, and waste disposal. This requirement for conservation of electricity, water and waste disposal is required due to the remote location of the site and the Park’s schedule for waste and water management. No cleaning or other services are provided by the Government.
5. Provisions: The Contractor and or Contractor’s personnel shall provide their own food/condiments/drinks/toiletries and any other personal items for the length of their stay.
Recreation items desired such as fishing/snorkeling gear, beach accessories, or flashlights shall likewise be brought to the site by the Contractor and/or its personnel.
6. Use of Contractor Housing:
a. All food and drink containers such as plastic (all types), glass, tin and aluminum is recycled. All recycled containers that have been brought to the island shall be carried back to the mainland at the Contractor’s expense. Contractor is responsible for all recyclable material.
b. Government-furnished composters may be used for fruit and vegetable waste.
c. Recyclable material and domestic waste shall be removed from the island at regular intervals of no more than every three weeks.
d. All food shall be removed upon departure.
e. Water shall be conserved by taking quick showers and consolidating dirty dishes to be washed once a day.
f. Housing units shall be thoroughly cleaned daily and upon departure.
g. Quiet hours are from 10:00 PM to 7:00 AM.
h. Contractor employees are restricted from using the NPS staff Recreation Room.
i. Contractor is restricted from using the Park’s laundry facilities. The Contractor shall arrange to have laundry processed off-site at Contractor’s expense.
j. Contractor is restricted from using NPS boats without prior approval and NPS staff must operate all NPS vessels.
7. Construction Camp: Establishment of a camp within the park is not permitted. As an alternative to on-site housing, the Contractor may propose to house its staff or subcontractors on boats in the harbor as long as the boats are self-contained and the contractor does not use the park’s facilities to dispose of sewage/gray water. If the Contractor proposes to house staff or subcontractors on boats in the harbor, the Contractor shall be responsible for storing and hauling out of the park, and surrounding waterways, the sewage/gray water to an appropriate treatment facility.
DRTO - 241934 01 11 00 - 5
8. Telephone/Internet/Cellular Communications Systems: There is no hard line on site for telephone/internet or cellular communications. Contractor shall be responsible for their own telephone/internet/cellular communications systems. Close coordination with Park personnel will be necessary to establish where equipment components can or cannot be located. Contractor shall receive approval from the Contracting Officer before installing any communications equipment.
9. Conduct:
a. All Park regulations shall be followed including but not limited to those regulations found in 36 CFR 7.27 – Dry Tortugas National Park and the 2016 Dry Tortugas National Park Compendium.
b. Do not litter.
c. All natural, archeological, and historical features and artifacts are protected.
Do not take or collect anything without a permit.
d. Avoid interaction or interfering with protected, endangered species. Do not kill, harm or interact with any wildlife. Do not feed or approach any wildlife.
e. Do not enter posted closed areas.
f. Do not stand on any sea grass or coral.
g. Fishing is allowed with a current Florida State saltwater fishing license.
h. Smoking is not permitted in or on top of the Fort, on the parade ground or within 25 feet of the Fort entrance.
i. Appropriate language in public areas.
j. Sexual harassment in any form is prohibited.
k. No music will be played at work site.
l. Smoking is prohibited within the fortification and only allowed in designated areas per federal law.
10. Transportation to the Project Site:
a. The Contractor shall be responsible for all transportation of personnel.
b. The Contractor shall be responsible for procuring, shipping and handling all construction materials.
c. The Contractor shall be responsible for packaging, transporting and disposal of all construction debris and personal trash. Micro plastics and wrapping that easily breaks down with UV exposure is discouraged. Due to limited space on site, debris and trash shall be removed from the island at regular intervals throughout the contract period – See 1.4.A.6.c.
d. USCG-approved vessels shall be used for transport of equipment, material and personnel. Contractor shall provide written verification that vessels used in the completion of this contract are USCG-approved.
e. Commercial Modes of Travel: The following schedules may be affected by weather conditions and are subject to cancellation or change.
1) Yankee Freedom III Ferry/Tour Boat Daily Schedule: Boat departs Key West at 8:00 AM with a 6:30-6:45 AM check in time for passengers with luggage and 7:00 AM – 7:30 AM check-in time for passengers with only carry-on type
DRTO - 241934 01 11 00 - 6
bags. The amount of personal supplies/gear that can be carried on the vessel is limited to no more than 60lbs dry weight. All passengers with luggage are required to pass through a luggage screening check prior to boarding. The screening process may include a search of the luggage. Equipment and supplies for construction should be transported via the National Park Service’s tender, M/V Fort Jefferson or other Contractor secured vessel.
Transportation of supplies/equipment other than personal gear aboard the Yankee Freedom requires prior approval of the Captain. Ferry arrives at Fort Jefferson at approximately 10:15 AM and departs at 3:00 PM – check-in is at 2:30 PM. Approximately 2 ½ hours of travel time (each-way).
a) The rate for Contractors is $99.00 one way. The single-day round trip rate is $165.00. Breakfast and lunch is included on outbound trips.
Lunch can be purchased separately for $7.00. The contractor is responsible for verifying all rules and rates and accounting for any differences in actual costs versus rates included in this document.
b) Contractor reservations must be made online using the NPS Contractor/Cooperator dedicated website – the web address will be provided to the Contractor after award. Cancellations or changes to reservations may be made by telephone at 305-294-7009 or 1-800-634- 0939.
c) The Yankee Freedom III is not contractually obligated to transport persons other than park visitors and may refuse transportation of any individual not traveling to the park for public visitation.
2) Key West Seaplane Adventures Daily Schedule: Flight times are subject to availability. Flights leave Key West Airport at 8:00 AM, 10:00 AM, 12:00 PM and 2:00 PM. Flights leave the Fort at 11:00 AM, 1:00 PM, 3:00 PM and 5:00 PM. Approximately 45 min. flight time each way.
a) As of March 1st 2018, Contractor rates for traveling on the seaplane are $273.60 per person each way or the same price for a 4 hour round trip. A full day (8 hour round trip) will cost $480 and a 10 hour day trip (first flight out, last flight back) will cost $546.40. The contractor is responsible for verifying all rules and rates and accounting for any differences in actual costs versus rates included in this document.
b) Contact Key West Seaplane Adventures for weight limitations and lists of items that can and cannot be transported by air.
c) Contact Information: By phone: 1-305-293-9300, by email:
info@keywestseaplanecharters.com
d) Key West Seaplane Adventures is not contractually obligated to transport persons other than park visitors and may refuse transportation of any individual not traveling to the park for public visitation.
f. National Park Service Crew Boat (Motor Vessel Fort Jefferson): The Government has a crew boat that is available at no cost to the Contractor to arrange transportation mailto:info@keywestseaplanecharters.com
DRTO - 241934 01 11 00 - 7
for its construction personnel to the site, rather than relying on commercial modes of transportation. While the Contractor may make arrangements for its personnel to be transported to the construction site on the Government’s crew boat, this vessel’s schedule and availability is uncertain and subject to weather conditions and other operational requirements such as staff scheduled maintenance, repairs, emergency assignments etc. Since this alternative method of transportation might be available but is not being provided as Government-furnished property/services, the Contractor shall be responsible for determining what method to use to transport its personnel to the construction site. If the Contractor chooses to use the Government crew boat and the crew boat is unable to make a trip, the Contractor shall bear all responsibility and expense for transporting its crew to the site; and this shall not be recognized as a Government delay of work or be an acceptable reason for the Contractor to make a request for equitable adjustment or additional time under the contract. The Contractor shall be responsible for making arrangements for the Government crew boat with the park personnel.
Information and restrictions that apply to passengers on the Government crew boat include the following:
1) All food items shall be placed in cardboard boxes or coolers labeled with the owner’s name.
2) All other cargo shall be labeled and easily identifiable as to the owner of the property.
3) The USCG Sector Key West base is accessed through the USN Key West Naval Air Station Trumbo Point Annex main gate. NPS staff (crew of M/V Fort Jefferson) must escort passengers through the USN main gate and USCG gate. Truck deliveries require a driver with a TWIC card and inspection of the vehicle at the USN Key West Naval Air Station Boca Chica entrance station.
4) The trip is approximately 5-1/2 hours of travel time from Key West to Dry Tortugas. The Government crew boat typically departs at 9:00 am from Key West Trumbo Point Naval Annex every other Tuesday. Return trips to Key West are generally the following Thursday, departing at 7:00 am from Dry Tortugas. There would be no charge for use of the Government crew boat when used with the normal operational schedule and solely for the transportation of Contractor personnel, groceries and personal items.
Scheduled trips are generally every other week. The Government crew boat is unavailable when the crew have scheduled leave, training, scheduled maintenance at a ship yard or have chartered trips supporting research. On an annual average basis, the Government crew boat will make approximately 18 resupply trips to Dry Tortugas.
5) Arrangements for use of the Government crew boat shall be made at least two weeks in advance of travel.
6) All Contractor personnel cargo shall be loaded, secured and unloaded by the Contractor or its personnel with guidance from the motor vessel Fort Jefferson crew. Contractor is not permitted to use crane on vessel. Crane shall
DRTO - 241934 01 11 00 - 8
be operated by ship’s crew. The Government is not responsible for lost or damaged goods.
7) The Contractor and Contractor’s personnel or subcontractors’ personnel shall present proper identification at the naval base gate and be escorted to the boat by a crew member of the M/V Fort Jefferson. The Government will not be responsible for personnel unable to access the boat prior to departure.
8) Private vehicles may not be parked overnight on the base. A small parking area is located directly outside the main gate and can be used to park privately owned vehicles. The Government shall not be liable for vehicle damage or theft if the Contractor’s or subcontractor’s personnel park their vehicle at this site.
9) Entry to the naval base may be denied anytime the national security level is elevated to orange or red or the naval base determines the individual(s) may not enter.
10) The Contractor shall be responsible for completing liability waivers for each person traveling on the Government crew boat. These waivers shall be presented to the captain prior to the Government crew boat getting underway.
B. Storage of Materials: Confine storage of materials to the North Coaling Dock or other designated staging areas indicated on drawings.
C. Preservation of Natural Features:
1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
2. Provide temporary barriers to protect existing trees and plants and root zones.
3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with
Contracting Officer and remove agreed-on roots and branches that interfere with construction.
4. Do not fasten ropes, cables, or guys to existing trees.
5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
6. In the event that natural features are inadvertently damaged, Contractor shall notify
Construction Management Representative immediately.
7. Construction workers shall be educated regarding fishing regulations, including identification of protected species.
8. Roosting or foraging birds shall not be disturbed.
9. Minimize activities at night that produce light scatter, especially from May to September during turtle nesting season.
10. Care shall be taken to avoid impacts to sessile marine organisms such as coral and sponges.
11. Refueling and maintenance of construction equipment shall be conducted in designated areas over spill pads.
D. Preservation of Cultural Resources: Due to the elevated historic status of this resource, preservation treatment approaches shall concur with The Secretary of the Interior’s “Standards for the Treatment
DRTO - 241934 01 11 00 - 9
of Historic Properties,” along with The Secretary of the Interior’s Guidelines for Treatment of Cultural Landscapes.”
This property is listed on the National Register of Historic Places (NR) and managed as a cultural resource and local aid to navigation. It includes historic features such as structures, landscapes and associated landscape features (sidewalk, planters culverts, fences, site walls, retaining walls, etc. and engineering features such as bridges, towers, etc.) This significance also extends to subterranean items including undiscovered or unexcavated archeological resources. It is also possible that certain site features within the project boundary are not mentioned in the NR document, but those unnamed items are considered potentially eligible and are treated with the same level of concern.
During construction and transportation of lighthouse components, care shall be taken to protect all cultural and natural resources. When planning construction means and methods, preservation and protection of this resource is paramount. Contractor will proceed with care, using conservative and cautious approaches when working on and around historic fabric. Recognized and approved methods, favoring hand tools over power tools along with demonstrated experience and skill, will take precedence over radical and unproven procedures. If potential exists for irreversible damage or loss of fabric, contractor will cease work and seek guidance and approval from CO (Contracting Officer) before resuming work. Actions deemed detrimental to the resource, that would otherwise place the resource at jeopardy of loss to its historical integrity, regardless of cause, will not be undertaken without prior review and approval by CO.
E. Driveways and Entrances: Keep walkways, boardwalks, sally port and counterscarp clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
1. Schedule deliveries, pick-ups/removals to minimize use of docks, seaplane ramp, counterscarp and sally port. Major delivery or pick-up of material shall not take place during peak visitor use times (10:00 am – 3:00 pm).
2. Schedule deliveries, pick-ups/removals to minimize space and time requirements for storage of materials and equipment on-site.
G. Hauling Restrictions: There are no standard roadways on Garden Key. Vehicular circulation is over dirt pathways and boardwalks where there are tight spaces and limited turning radiuses. Therefore only small vehicles can be used for transport of materials, supplies and debris. Comply with all legal load restrictions in the hauling of materials. (Dimensions of bridge and counterscarp and associated load restrictions are indicated on drawings). Information regarding rules and regulations for vehicular traffic on Garden Key may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
H. Contractor shall install temporary roadway surface or protective mats along haul route within the fortification between the Bastion 6 staging area and Sally Port to minimize damage to existing turf and protect significant archeological deposits known to exist in the area.
I. Contractor shall store fuels greater than 5 gallons in containers with appropriate NFPA marking.
DRTO - 241934 01 11 00 - 10
1.6 PUBLIC USE OF SITE
A. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public.
Sally port closures will be permitted before 10:00 am and after 3:00 pm, upon specific approval of Contracting Officer.
1.7 OCCUPANCY REQUIRMENTS FOR BUILIDINGS
A. Existing Buildings
1. Full Government Occupancy: Government will occupy portions of the Fort adjacent to those areas that will be under construction during the entire contract period. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government's day-to-day operations. Maintain existing exits, unless otherwise indicated.
a. With the exception of the Bastion 6 stair tower, maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the CO.
b. Repair damage caused by construction operations. Protect building and its occupants during construction period.
1.8 CONDUCT OF OPERATIONS
A. At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.
B. Work at night (after 6:00 pm) may not be performed without prior consent from the Contracting Officer. Submit requests 72 hours in advance of the work to the Contracting Officer for approval.
Work outside regular hours may be subject to limitations and will be granted on a case by case basis for specific durations and in response to specific needs.
C. Contractor is permitted to work on Federal holidays.
D. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
1.9 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7:00 a.m. to 6:00 p.m., seven days a week, except when otherwise indicated.
1. Hours for noisy activity shall occur between 8:00 am and 5:00 pm.
B. Existing Utilities
DRTO - 241934 01 11 00 - 11
1. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, consult with Contracting Officer and Park staff prior to repairing damaged utility components. Repairs will be made at no additional expense to the Government.
2. If damage occurs to an unknown utility, consult with Contracting Officer and Park staff prior to repairing utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government.
Coordinate any required temporary interruptions (less than 2 hrs) with Contracting Officer, CMR and on-site facilities maintenance supervisor.
1.10 SPECIAL CONSTRUCTION REQUIREMENTS
A. Seasonal Shutdown: It is anticipated the Contractor will complete disassembly prior to June 1, 2020.
Hurricane Season commences on June 1st. If contractor cannot be fully demobilized from the site by June 1st they must have a severe weather/hurricane plan that can secure all resources and materials within 72 hours of projected landfall and be able to demobilize all personnel from Garden Key no later than 48 hours out from projected land fall. Contractor shall return to site for completion of work upon receiving all clear notification from Government. Phase III - Reinstallation shall be completed between the months of November and June.
B. No off-season temporary storage will be provided at Garden Key.
C. Contractor is solely responsible for all contents stored on site during the construction period and temporary barriers shall be designed to withstand extreme weather events. Barriers shall be maintained in good condition at all times. Use of plastics that break down in UV exposure are discouraged.
1.11 ADDITIONAL REPORTS
A. A report entitled Everglades & Dry Tortugas Hurricane Plan Version 2018 has been prepared by National Park Services and included as Appendix A.
B. If conflicts occur between the report and drawings or specifications, the drawings and specifications govern.
C. Drawings of the existing shoring/scaffolding are available to bidders upon request.
D. Drawings of the dock bridge are available to bidders upon request.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 11 00
DRTO - 241934 01 26 01 - 1
031414 CONTRACT MODIFICATION PROCEDURES
SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. The work of this section consists of administrative and procedural requirements for contract modifications.
1.2 DEFINITIONS AND ALLOWANCES
A. Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):
1. Rent
2. Utilities
3. Furnishings
4. Office equipment
5. Executive and management staff not exclusively assigned to the project
6. Support, accounting, and administrative staff
7. Preparation of cost proposals, estimating, and schedule analyses connected with
Modifications
8. Estimating and preconstruction services
9. Mortgage costs
10. Real estate and corporate taxes
11. Automobile maintenance and travel costs for home office personnel
12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.
13. Depreciation of equipment and other assets
14. Home office supplies (paper, staples, etc.)
15. Legal services
16. Accounting and data processing
17. Professional fees/registration
B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:
1. Project Manager, Assistant Project Manager
2. Superintendent, Assistant Superintendent
3. Quality Control, Safety Officer, Environmental Manager, etc.
4. Engineers
5. Travel, lodging, and per diem (as established by Federal Travel Regulations)
DRTO - 241934 01 26 01 - 2
6. Scheduling
7. Field Office Trailers and associated temporary utilities
8. Field office supplies
a. Mailing and couriers
b. Reproduction costs
c. Storage
d. Phones
e. Computers
f. Copiers
9. Personal vehicles i.e. Superintendent Pickup trucks
C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating General Requirements:
1. Hoisting
2. Material handling
3. Temporary fencing
4. Port-a-lets
5. Trash removal, dumpsters
6. Barricades
7. Small tools
8. Safety supplies
9. Scaffolding
10. Daily cleaning
11. Traffic control
12. Temporary signage
13. Temporary heating and power
D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40 hour week and no overtime or holiday pay will be allowed.
1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:
a. Base Rate: This is the hourly rate paid directly to the worker
b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums , such as:
1) Social Security
2) Medicare
3) Workers Compensation– Policy and company calculation to be made available.
4) FUTA– Cap Rate and percentage to be proportionally allocated over one year.
5) SUTA– Cap Rate and percentage to be proportionally allocated over one year.
DRTO - 241934 01 26 01 - 3
6) Union agreement costs – Other costs required under an enforceable collective bargaining agreement.
c. Fringe Benefits: Various non-wage compensations provided to employees such as:
1) Health Care Insurance Premiums
2) Cell Phone
3) Clothing
4) 401K and Pensions
5) Vehicle allowances
6) Gas allowance
7) Life insurance premiums
8) Disability insurance
9) Other Fringe Benefits required under an enforceable collective bargaining agreement
E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.
F. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.
G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.
H. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.
1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS
A. General:
1. Your proposal must be received in the format and within the time frame specified in the Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.
2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement.
Contractor may utilize the government provided Contractor Estimate Form, or their http://en.wikipedia.org/wiki/Employee http://en.wikipedia.org/wiki/Surety_bond http://en.wikipedia.org/wiki/Insurance http://en.wikipedia.org/wiki/Bank http://www.nps.gov/dscw/publicforms.htm
DRTO - 241934 01 26 01 - 4
own form, provided that it contains the same information and level of detail as the Gov’t provided form.
3. Requests for extensions of contract time as a result of this change must be justified with a Time Impact Analysis (TIA). Refer to Division 01 Specification, “Construction Schedule”, for time impact analysis requirements. TIA and associated costs must be received with the proposal by the date shown within the Request for Proposal letter.
Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving the right for additional time and no time extension will be allowed.
4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.
5. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.
6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.
B. Labor:
1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work.
Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.
2. Itemize labor costs for equipment operators separate from equipment costs.
3. The labor cost for foremen shall only be costs for related work required for the modification.
C. Materials:
1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.
2. No markup shall be applied to any material provided by the NPS.
D. Equipment:
1. Equipment used for the project must be appropriately sized for the work being performed.
2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.
3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:
a. U.S. Army Corps of Engineers , Ownership and Operating Expense Schedule (use latest edition and applicable region)
b. Construction Blue Book
DRTO - 241934 01 26 01 - 5
c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.
4. The estimated equipment rates shall include the operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per FAR 31.105(d)(2)), depreciation, storage, insurance, and all incidentals.
Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.
5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.
6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above. If the US Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs, major repair and overhaul will be accepted.
7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.
8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.
9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.
10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.
E. Establishment and Application of Overhead and Profit Percentages:
1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.
Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:
Overhead………………10% Profit………………7.75%
2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.
3. If contractors form a partnership, than the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par 1.3,E,1 above). It is the responsibility of the partners to decide on the division of revenue.
4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.
5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.
DRTO - 241934 01 26 01 - 6
PART 2 - PRODUCTS
PART 3 - EXECUTION
END OF SECTION 012601
DRTO - 241934 01 27 00 - 1
082714 DEFINITION OF CONTRACT LINE ITEMS
1. SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
PART 1 - GENERAL
1.1 SUMMARY
A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of the work, include the costs in a related item.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. Contract Line Item No. 01: Phase I - Disassembly
1. This item consists of all work required to disassemble the lighthouse and transport all components from the project site to off-site facility. This item also includes disassembly and removal of the scaffolding/shoring from Garden Key for legal disposal.
2. No separate measurement of quantities will be made.
3. Payment will be made at the contract lump sum price.
B. Contract Line Item No. 02.A: Phase II – General Treatment
1. This item consists of all work required for treatment items not covered under unit cost
Contract Line Items 2.B - 2.T, including but not limited to the following:
DRTO - 241934 01 27 00 - 2
2. No separate measurement of quantities will be made.
3. Payment will be made at the contract lump sum price.
3.2 CAST IRON REPAIR UNIT PRICES
C. Contract Line Item No. 2.B: C1 - Perform pitting repair on exposed surfaces of cast iron with polymer fill as indicated in specification section 050313-3.3C.
1. This item consists of all work required to perform a pitting repair.
2. Measurements of quantities included on Contract Price Schedule.
3. Payment will be made at the contract unit price per square foot.
D. Contract Line Item No. 2.C; C2 - Perform pitting repair on concealed surfaces of cast iron by fusion welding as indicated in specification section 050313-3.3D.
1. This item consists of all work required to perform a pitting repair.
2. Measurements of quantities included on Contract Price Schedule.
3. Payment will be made at the contract unit price per square foot.
E. Contract Line Item No. 2.D, C3 - Perform small hole plug repair on cast iron as indicated in specification section 050313-3.3E.
1. This item consists of all work required to perform a small hole plug repair.
2. Measurements of quantities included on Contract Price Schedule.
3. Payment will be made at the contract unit price per each unit.
Item Total Quantity Quantity Repair
Quantity Replace
WROUGHT IRON/STEEL
Sill plate 143 lf 0 lf 143 lf Head plate 152 lf 33 lf 119 lf Wall plate 1004 sf 733 sf 272 sf Seam plate 282 lf 136 lf 146 lf Corner plate 17 sf 0 sf 17 sf Channel rib 174 lf 131 lf 44 lf WT rib 205 lf 154 lf 51 lf Bent strap 5 sf 3 sf 3 sf Balcony 13 sf 0 sf 13 sf
CAST IRON
Cast floor 166 sf 87 sf 79 sf Lantern sill 36 lf 36 lf 0 lf Lantern mullions 33 lf 33 lf 0 lf Roof 94 sf 94 sf 0 sf Door frames 40 lf 40 lf 0 lf Window frames 181 lf 181 lf 0 lf
WOOD
Wood floor 191 sf 0 sf 191 sf
DRTO - 241934 01 27 00 - 3
F. Contract Line Item No. 2.E: C6.1 - Perform structural crack repair on cast iron by mechanical means as indicated in specification section 050313-3.3F.
1. This item consists of all work required to perform a structural crack repair.
2. Measurements of quantities…
This is the start of the file's text. The full file is on GovTribe.