AMENDMENT 3

View the file

Other files

File Type Posted
140P2018R0026_AMD_4.pdf PDF
140P2018R0026_AMD_3_Drawings.pdf PDF
140P2018R0026_AMD_2.pdf PDF
AMD_1_SPECS.pdf PDF
140P2018R0026_AMD_1.pdf PDF
AMD_1_PRE_PROP_AGND.pdf PDF
AMD_1_SIGN_IN_SHEET.pdf PDF
AMD_1_DWGS.pdf PDF
Attach_3_Sub_Plan.docx DOCX document
Attach_1_Exp_Form.docx DOCX document
Attach_6_Dwgs.pdf PDF
140P2018R0026_Solicitation.pdf PDF
Attach_2_PPQ_Form.docx DOCX document
Attach_5_Spec_Vol_2.pdf PDF
Attach_4_Spec_Vol_1.pdf PDF
B01_PRESOL.docx DOCX document
Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

AMENDMENT 00003

PDS

The subject amendment 00003 for the construction solicitation 140P2018R0026 to rehabilitate the Valley Forge National Historical Park Visitor Center, King of Prussia, PA is amended as follows: The questions and answers are on pages 2 - 13, the revised page 145 of the solicitation is on page 14, pages 15-29 included the updated wage determination PA123, Mod 12, dated 8/10/18. The revised drawings are attached.

NPS, DSC CONTRACTING SERVICES DIV

12795 W. ALAMEDA PKWY

P.O. BOX 25287

DENVER, CO 80225-0287

140P2018R0026

140P2018R0026

VAFO 211497

1 28

08/10/2018

140P2018R0026 AMENDMENT 3 DATED 8/10/18 PAGE 2

VALLEY FORGE NATIONAL HISTORICAL PARK

VAFO-211497, 244026, 248737, AND 248779

REVISIONS, ADDITIONS & CLARIFICATIONS

The Wage Determination is updated to PA123 Mod 12 dated 8/10/18.

Solicitation Page 145 revised and incorporated into this amendment.

Specification Revisions

1. REPLACE - None

2. ADD - None

3. DELETE Specification Section 26 31 00 in entirety.

Construction Drawings Revisions

Drawing Number 464/141261 – RehabilitateVisitor Center For Energy Efficiency, Safety and ADA Access Sheets 1A, 2A, 6, 12A, 22A, 25A, 38A, 41A, 57A, 58A and 67 DELETE in entirety, and SUBSTITUTE the attached revised sheets: 1B, 2B, 6A, 12B, 22B, 25B, 38B, 41B, 57B, 58B and 67A.

Clarifications

Answers to Q1 and Q2 were included in Amendment 1.

Q3. Please provide the following information or clarification: Drawing M-24 : Refers to Cabinet Unit Heaters being hot water. There does not seem to be any hot water available.

A3. Cabinet unit heaters are to be electric as scheduled on sheet M-19. The electric heaters are air curtain type and are to be controlled via the devices stated in specification 23-84-00 section 2.5 H.

Q4. Spec. Vol. 2 : Pg. 323-324 1.3 Products Furnished by but not installed under this section A.

Installation of following items furnished under this section but installed by Mechanical Item # 5.

BTU Meters (there is no Detail on any Control Drawings for this. Does this device exist)Please reference drawing if applicable.

A4. Btu meters are not applicable to the project scope.

Q5. Drawing M-26 Input / Output Points Summary Chilled Water System Differential Pressure Control Valve: Please Explain Location and Drawing #.

A5. The chilled water system differential pressure control valve is to be provided in the chilled water system by-pass line. This line is to be installed in an accessible location preferably in a mechanical room. Drawing M-26 will be revised to show this bypass line in a conformed set of Construction documents to be provided to the successful bidder.

140P2018R0026 AMENDMENT 3 DATED 8/10/18 PAGE 3

Q6. What are the solar requirements?

A6. The 350 KW solar PV system has been deleted from the project. Spec section 26 31 00 is to be deleted. There is a solar hot water component that is still in the project. Amendment 1 drawing A1.4 shows the location of the panels on the roof.

Q7. The Solicitation page 145 of 162 Tab A - Factor 1 Experience/Past Performance in the section offerers are directed to use # 12 font. May we use a smaller font when placing a caption to a graphic or photo?

A7. Yes.

Q8. The Solicitation directs us to use 8.5 * 11 page size. May our schedule and logistics be on 11 * 17 to make it easier to read for the reviewer and if so will the 11 * 17 count as one page?

A8. See Amendment 3, revised page # 145.

Q9. Per Page 145 of 162 of the Solicitation, D. Volume 1 – Technical Proposal Submission Requirements please advise where you want the DUNS numbers listed for each party of the Joint Venture.

A9. See Amendment 3, revised page # 145.

Q10. Drawing E0 Logistics Temp Building Power Plan, Key Note 1 discusses additional electric wood poles (Approximately 3) to be installed in the NPS property line to carry the new PECO feed to the new 225kVA transformer. Please verify that these new poles will be furnished and installed by PECO A10. These new poles will be furnished and installed by PECO at Park’s expense.

Q11. Drawing E0 Logistics Temp Building Power Plan, Key Note 1 states that the new 5kV cable that is to be extended from the existing PECO overhead pole, located in County Line Road, will be furnished by PECO and installed by the Electrical Contractor. Please provide a "to-scale" drawing(s) that shows the location of the existing PECO overhead pole in County Line Road, the (3) estimated new wood poles and the routing that is to be taken to extend the new 5kV power to the new 225kVA transformer shown on Drawing E0.

A11. Poles, cable and transformer to be provided and installed by PECO at Park’s expense.

Q12. Section 01 50 00 Temporary Facilities and Controls 3.1E.1 discusses the requirement for tapping into the existing Telephone and Data service located in the Auditorium Building and then to distribute a Corning, Altos, All-Dielectric Gell-Free 36 fibers polyethylene coated line on poles to the Temporary Visitor's Center. Please provide "to-scale" drawing(s) that show the tie-in location(s) and routing of phone and data within and exiting the Auditorium Building, routing from the Auditorium Building to the Temporary Visitor's Center, locations of existing poles that may be utilized for the route, new temporary pole requirements if any and a detail and location of the demarc that is to be provided at the Temporary Visitor's Center.

140P2018R0026 AMENDMENT 3 DATED 8/10/18 PAGE 4

A12. Existing Telephone Data Service is located in Canteen / Snack Bar and shall be delivered to the Temporary building by overhead cable. Specification will be revised in a conformed set of Construction documents to be provided to the successful bidder.

Q13. Please advise if a temporary Fire Alarm System is to be furnished, installed and wired within the Temporary Visitor's Center. If required, please provide Specifications, One-Line Diagram, etc. of the Fire Alarm System that is to be provided. Also if required, does the temporary system need to be tied into the permanent campus system? (Location/requirements?)

A13. Temporary fire alarm system is not required.

Q14. Please identify on the Electrical Drawings the scope of work that is to be included in the price for Contract Line Item No. 4 - Option A - Ceilings and Lighting (reference PMIS # 248737).

A14. See architectural drawings for division of scope per PMIS.

Q15. Please identify on the Electrical Drawings the scope of work that is to be included in the price for Contract Line Item No. 5 - Option A - Interior Finishes, Furniture, Equipment and Building Signage (reference PMIS 248779).

A15. See architectural drawings for division of scope per PMIS.

Q16. The construction documents (Drawing AL.0) indicate TES and VC storage trailers.

After reviewing the existing conditions there does not appear to be adequate space to accommodate the fourteen (14) feet of compacted crushed stone bed for these trailers as shown on drawing AL. 1. Please clarify.

A16. Park will trim trees in order to accommodate the width of the trailers.

Q17. After review the existing conditions and the construction documents (Drawing AL.0), the stair and associated ramp shown on the South side of the Temporary Visitor Trailer appear to be in direct conflict with the existing Electric car charging station locations. The construction documents indicate that these charging stations as well as the parking lot signage and light poles are to remain. Please advise on how to proceed.

A17. Preliminary survey did not indicate a potential conflict. Per NOTE 2 and G1.1, Contractor shall verify all existing conditions prior to construction and report any discrepancies or conflicts to the Contracting Officer prior to proceeding with work.

Q18. Contractor were informed to ensure that all site Fire lanes were not blocked or restricted.

After careful examination of the existing site no fire lanes could be found. Please advise where the fire lane information can be found.

A18. Contractor is required to provide a site plan prior to Start of Construction. Emergency access to be coordinated with Authority Having Jurisdiction (see Note 2, Sub-sheet G1.5).

Q19. Please confirm that Specification Section 263100 Photovoltaic System is not part of this project.

A19. See response to Q6 above.

140P2018R0026 AMENDMENT 3 DATED 8/10/18 PAGE 5

Q20. Drawing A6.8 Furniture Schedule: Please clarify the responsibility for the Loose, 1st & 2nd Floor Furniture Schedule listed. (I.e Contractor Furnish &Contractor Install / Owner Furnish & Contractor Install / Owner Furnish & Owner install.)

A20. Contractor to furnish and install.

Q21. If furniture is contractor furnish: 1st and 2nd Floor Furniture Schedule Model No.

column stipulates “reff or approved equal.” It is not clear if the described design is custom or is a specific model. Please issue the specific model numbers or basis of design so we can accurately price.

A21. See drawing A6.8, Amendment #3.

Q22. In Outer Vault Room 112 receives new carpet & paint. This would mean some relocation of cabinets while finishes are installed (especially flooring). Please clarify the GC is not responsible for moving any cabinets with stored artifacts or we are to install new finishes around the cabinets and will remain in place at all times.

A22. Cabinets will be moved out by Park prior to Notice to Proceed.

Q23. We understand GC is responsible for setting up and moving equipment to temporary trailers. Please clarify if GC is responsible for moving equipment back into the building once project is completed.

A23. Yes. Specification Section 012700 - Definition of Contract Line Items, Part 3 - List of Contract line Items, 1.a.i & ii.

Q24. Please confirm the owner will appoint, retain and pay all costs associated with the commissioning agent(s) and the GC is to assist the commissioning agent as per the specification requirements.

A24. The Government is responsible for paying all costs associated with the services of the Commissioning Agent (CxA), who is provided by the Designer of Record. The GC is to assist the CxA as per the requirements set forth in Section 01 9114 Total Building Commissioning.

Q25. Please confirm Owner will accept phone, data and electric to the temporary trailers will be via aerial installation with poles and not installed underground.

A25. The government will accept phone, data and electric delivery to the temporary trailers via aerial installation with poles and not installed underground.

Q26. Key personnel confirmation A26. For this project the Onsite-Superintendent cannot be responsible for or perform the Quality Control responsibilities. The person responsible for Quality Control can perform other duties such as On-Site Safety Manager and or Environmental for Quality Control and Safety.

The persons proposed as key personnel are required to be the persons performing the work as proposed within 180 days.

Q27. Please provide a demo plan for the west roof and east roof areas.

A27. All existing roofing and system components shall be removed per Typical Removal Notes D1.1.

140P2018R0026 AMENDMENT 3 DATED 8/10/18 PAGE 6

Q28. Please provide the existing roof framing plan and structural details for the west roof and east roof area.

A28. Contractor shall verify all existing conditions prior to construction per contract requirements.

Q29. Please provide the structural design for the davit system as it appears to be incomplete in detail 4/A3.2. The steel sizes and spacing for steel members are not indicated.

The detail also does not appear to provide for adequate structural support of the lifeline system since it does not connect back to load bearing beams.

A29. Contractor shall provide engineered design per specification.

Q30. Archeology storage question from walk-thru.

A30. See CLARIFICATION 1, 2, 3 & 4 below.

Q31. Concerning the technical proposal submission, Volume I, TAB B has a limitation of 10, 8 ½ X 11 sheets yet it indicates that we are to provide a narrative as well as a full schedule for the project – the schedule alone in order to be readable will require a minimum of 20 sheets of letter size. Please advise how we are to comply with the conflicting requirements of this section.

A31. See Amendment 3, revised page # 145.

Q32. 1. Spec 230523, 2.6 High Performance Ball Valves: The specifications calls for "high performance ball valves of the stainless stell top-entry body" B. Provide high performance ball valves of the stainless steel top-entry body type, having a straight-through full port flow passage. Design to permit disassembly without removing body from line. 2. Body to be 2-piece screwed end. A quote could not be attained for the denoted on the valve list:

H.P. Ball - DeZurik Fig. No. 551. DeZurik makes a V Port (VPB) control ball valves.

Please advise if we should use these valves or provide a model number of a different ball valve. Please advise if we can use a valve kit by NuTech with stainless steel trim and full port ball valves, see manufacture product list.

A32. Response will be provided in a future Amendment.

Q33.What type glycol propylene or ethylene should we use?

A33. Response will be provided in a future Amendment.

Q34. Section 230523 2.9 Valve List: Please provide a NIBCO Fig. No. for ball valves sizes 2" and smaller with sweat ends. 2.2 Please advise if TACO or B&G circuit setter will be acceptable for balancing and throttling.

A34. Response will be provided in a future Amendment.

Q35. There is existing lighting (lightning?) protection on the two (2) towers of the visitor center at Valley Forge, the construction documents (drawings and specifications) do not include any details or scope in regards to removal, modification, or installation of any lighting (lightning?) protection system. Please review and advise what Lighting protection scope of work should be included.

140P2018R0026 AMENDMENT 3 DATED 8/10/18 PAGE 7

A35. Response will be provided in a future Amendment.

Q36. The Solar Panel Hot Water generator as shown on the documents, drawing P11, appears to be for a residential installation and the additional detail show mounting the unit in a vertical orientation. The roof where this is to be installed is a flat roof and no structure exist to mount this unit in a vertical orientation. Please review and advise as to how this unit is to be installed and mounted.

A36. Response will be provided in a future Amendment.

Q37. Drawing EO, keynote #1 & #2 - Keynote #1 on drawing EO states the 5KV cable will be provided by PECO and installed by the electrical contractor however on the “Temporary Building Power Connection” riser diagram key note #1 is intercepted by keynote #2 which states “furnish and install 5KV cable based on PECO recommendation”.

Unless this interception point occurs at a manhole “not shown” it would be much clearer if PECO was responsible to furnish the cable for installation by the electrical contractor from the overhead poles all the way into the Primary disconnect switch, please clarify.

A37. See Item #11 response above.

Q38. Drawing EO, keynote #2 - Keynote #2 states “furnish and install 5KV cable based on PECO recommendation”, please confirm the electrical contractor is responsible to furnish this cable as it contradicts with key note #1.

A38. See Item # 11 response above.

Q39. Drawing EO, keynote #3 - Keynote #3 states “4” PVE”, please confirm this should read

“PVC”.

A39. Response will be provided in a future Amendment.

Q40. Drawing EO, keynote #1 - Please confirm PECO will furnish and install the new 225KVA pad mounted transformer.

A40. See Item # 11 response above.

Q41. Drawing EO, keynote #1 - Who is responsible for the furnish and installation of the 225KVA transformer concrete pad?

A41. See Item # 11 response above.

Q42. Drawing EO, keynote #1 - Who is responsible for the furnish and installation of the additional electrical utility poles?

A42. See Item # 11 response above.

Q43. Contract Clause 52.211-10 - Reference page 15 of the Solicitation Document, Section F, FAR 52.211-10 Commencement, Prosecution, and Completion of Work (Apr 1984). This section states in part “complete the entire work ready for use 365 calendar days from the Notice to Proceed.” Upon review of the project document, it is clear that the scope of work includes provisions for construction and acceptance of significant temporary facilities, prior to starting renovations to the Visitors Center building. As such, adequate time will be required to perform

140P2018R0026 AMENDMENT 3 DATED 8/10/18 PAGE 8

both the temporary facilities scope of work and then the existing building renovations. Please confirm that the Notice to Proceed, that starts the 365 calendar day period, will be issued only after the temporary facilities are completed and the Park Service has fully vacated the existing Visitors Center.

A43. The period of performance remains as is as described in the solicitation. And includes the temporary facilities scope of work.

Q44. To allow for the review and incorporation of all project documents, including the significant number of Amendment 0001 revised drawings and specification on August 3, 2018, and ultimately development of our Best Value Technical and Price Proposal, please consider extending the current proposal due date by two (2) weeks to August 28, 2018.

A44. Amendment 2 extended the proposal due date to August 17, 2018.

Q45. Solicitation page 11, Specification 230923 – 1.14 – A - In the solicitation page 11, it lists the line items required. In Specification 230923 – 1.14 – A: Maintenance it states that an alternate price to perform complete preventative and emergency maintenance of the BMCS for a period of one year be offered. Is this still a requirement as it is not listed on the list of options on this solicitation page?

A45. This is not a requirement. Specification will be revised in a conformed set of Construction documents to be provided to the successful bidder.

Q46. Specification 233320 - Please clarify or confirm that per Specification 233320 (Duct Cleaning) all ductwork both new and existing systems shall be cleaned per specification therein.

(Our subcontractor reads this specification as the entire system) A46. Response will be provided in a future Amendment.

Q47. Specification Section 230593- 301 – C - Please clarify or confirm that per Specification Section 230593- 301 – C that the entire ductwork system both new and existing must be leak tested to specifications. (Not just a witnessed representative sampling) A47. Response will be provided in a future Amendment.

Q48. Mechanical and Plumbing Specifications - We have found spare parts listed for many items in our Mechanical and Plumbing Specifications with the exception of Fan Belts and Pump Seals are they required (One of our air handler vendors has supplied a quote for Belts as an add) A48. Response will be provided in a future Amendment.

Q49. "Pre-Bid Meeting Discussion - During the pre-bid meeting walkthrough, it was mentioned that the existing emergency generator was to be replaced under a separate project. There are three scope of work items listed on the drawing that this project is to include.

Tie in existing generator into new toilet exhaust. (listed on three of the drawings) Please confirm that this is still required in this scope of work.

140P2018R0026 AMENDMENT 3 DATED 8/10/18 PAGE 9

A49a. Yes, it is still required to tie the existing generator exhaust into the toilet exhaust. The generator project will connect from the unit exhaust to a stub left within 5 feet of the current generator.

Note 10 on sheet M4 states demolish and replace in-kind existing emergency generator automated louver damper. Please confirm that this is still required in this scope of work.

A49b. Yes, this is still required. The ductwork from the new generator to the damper is not part of this solicitation.

On sheet M25 it notes that the new BMCS shall monitor many points with regards to fuel oil system/ generator belly tank or day tank. If this scope of work is required is there any information at this time for the new generator / fuel oil system that could assist us with pricing this component of the project. If not as it is only monitoring status is it safe to assume that what will be in place will have the ability to meet this scope of work requirements.

A49c. The model and manufacturer are not known at this time but the new generator will use the existing fuel tank and supply line. There will be a new day tank, battery monitor, engine block heaters and battery warmer.

Q50. 01 50 00 2.2.-3.1 - Please clarify the individual heating requirements for the temporary visitor center and two office trailers.

The materials and performance chart under 2.3 indicates the use of electric through-wall heat/cool units for the visitors center.

2.6 HVAC Equipment- calls for liquid-propane-gas or fuel-oil heaters.

3.1 Heating and Cooling- provide heating/cooling units needing only electrical power for operation.

A50. Specification 01 50 00, 2.6/B defines heating equipment as intended for use in TEMPORARY CONTRACTORS FIELD OFFICE as defined in section 01 50 00, 2.5.

Q51. 01 50 00 - Please confirm that an HVAC system specifically made for modular buildings, such as those manufactured by Bard will be acceptable for use in the temporary visitor center.

A51. Any proposed system shall be required to meet the performance and design requirements of the contract documents. All systems will require submission for review and approval.

Q52. 01 50 00 2.2-D - Logistics Plan and 01 50 00 does not show public restrooms for the temporary visitor’s center. Please confirm that contractor is not responsible for providing public restroom facilities for the temporary visitor center.

A52. Contractor is not responsible for providing public restroom facilities for the temporary visitor center. Public restroom facilities are available in the adjacent Canteen Building.

Q53. 01 50 00 2.2-D - Section 2.2 indicates separate toilet facilities for men and women. Are these facilities within the Contracting officers field office, or external portable toilets?

140P2018R0026 AMENDMENT 3 DATED 8/10/18 PAGE 10

A53. The Park has indicated that they can find space for the CO/CMR office within one of the existing buildings. Contractor is not required to provide a trailer for CO/CMR trailer. No separate toilet facilities for men and women are required.

Q54. 01 50 00 Para. 2.3, E0 - The Materials and Performance Table in Specification Section 01 50 00 Paragraph 2.3 identifies a 60A panel for the Temporary Visitor Center. The Power Riser Diagram on Drawing E0 shows 100A and 120A panels for the units. Please clarify the required panel size for the Temporary Visitor Center modular units.

A54. Response will be provided in a future Amendment.

Q55. Section 238413 - Steam Humidifiers: Please advise if steam humidifiers should be installed. If required please provide steam humidifiers schedule, installation locations on the drawings and piping layout.

A55. Response will be provided in a future Amendment.

Q56. Drawing M6 & M7: Please clarify a meaning for symbol CHW/1 in upper left corner. Is this indacte of the CHW riser?

A56. Response will be provided in a future Amendment.

Q57. Drawing A4.2 MDF Room 117 shows a woven wire metal partition:

a. There is no specification or basis of design listed. Please issue.

b. Is there a wire mesh top/ceiling to complete enclose the area or does it just stop at a certain height per the elevation.

A57a. Basis of design for metal mesh is defined on drawing 4/A4.2 previously issued.

A57b. See drawing A4.2 issued with Amendment #3. Provide horizontal lateral bracing as indicated.

There is no top /ceiling enclosure.

Q58. Spec 093013.A & B Ceramic Tile: TL-2 & 3 do not have a basis of design product.

Ceramic Tile pricing can range greatly depending on product. Please clarify which product from Daltile for TL-2 & 3.

A58. See Specification 09 30 13 / 2.3 for product line as previously issued.

Q59. Drawing A9.3 Education Center 301 shows a folding partition. There is no specification issued and no detail showing the folding partition. Furthermore there is no information found on the structural drawings showing how this folding partition is to be supported. Please submit a specification or a basis of design for the folding partition and details for structural support.

A59. The existing movable partition is to remain. See sheet D1.3.

Q60. Is this project Pa Act tax exempt or totally tax exempt?

A60. See solicitation clause 52.229-3 Federal, State and Local Taxes starting on page 109.

Q61. Drawing A1.1: Please provide a specification for the fluid-applied waterproofing.

140P2018R0026 AMENDMENT 3 DATED 8/10/18 PAGE 11

A61. Fluid applied waterproofing as noted on A1.1 will be deleted from the project scope. Concrete topping slab will be applied directly over existing slab on grade.

Q62. Section 220002 Plumbing Special Conditions, 3.1 Fees, C. references Contract Line Item No. 3-PMIS 248737. Please confirm that the costs for all Plumbing work for this project should be entered under Contract Line Item Number 1 Building Rehabilition PMIS # 211497. Also, please confirm that the same holds true for all Fire Protection and HVAC work for this project.

A62. Response will be provided in a future Amendment.

Q63. Sections 21 08 00, 22 08 00 and 26 08 00 for Fire Protection, Plumbing and Electrical Systems Commissioning have been included in the Specifications for Divisions 21, 22 and 26. Is there a Section 23 08 00 Commissioning of HVAC Systems that should be issued for Division 23 HVAC? Please clarify A63. Response will be provided in a future Amendment.

Q64. Is cleaning of new duct systems required per Section 233320 Duct Cleaning if SMACNA Duct Cleanliness for New Construction Guidelines is implemented and adhered to throughout all phases of the construction process? Please advise.

A64. Response will be provided in a future Amendment.

Q65. Drawing A3.5 & A3.6 shows a handicap railing. There is no specification for this railing so we don’t know what type and material this railing is. Please issue a specification or clarify railing detail.

A65. See specification section 05 52 13 PIPE and TUBE RAILINGS as previously issued.

Q66. Drawing A4.1 & A4.3 Bathroom Walls: Demolition Notes say to remove all fixtures, vanities and finishes. New Work drawings shows existing drywall in most areas where demolition occurs. By the time the demolition is done on the walls intended to remain existing, they will have large holes, etc and may or may not support new ceramic tile. We recommend removing all the GWB walls in the bathrooms and installing new GWB and backboard to existing studs. Please advise.

A66. This is Contractor Means and Methods.

Q67. Please provide a demo plan for the west roof and east roof areas.

A67. See response to #27 above.

Q68. Please provide the existing roof framing plan and structural details for the west roof and east roof area.

A68. See response to #28 above.

Q69. Please provide the structural design for the davit system as it appears to be incomplete in detail 4/A3.2. The steel sizes and spacing for steel members are not indicated. The detail also does not appear to provide for adequate structural support of the lifeline system since it does not connect back to load bearing beams.

140P2018R0026 AMENDMENT 3 DATED 8/10/18 PAGE 12

A69. See response to #29 above.

Q70. Will CO/CMR office be provided by the Park?

A70. The Park has indicated that they can find space for the CO/CMR office within one of the existing buildings. Contractor is not required to provide a trailer for CO/CMR trailer. No separate toilet facilities for men and women are required.

Q71. 1. Acoustical ceiling spec for CL-2: Tile #1942 is for 2'x2' ceiling tile. I believe he is looking for #1945. Please confirm. 2: Acoustical ceiling spec for CL-4: Line 13 - Fixture trim FTP4ZW. This is only for the 4" wide part fo the light. Are these continbuous lights or are they 4' long? It appears on the reflected ceiling print that these are continuous. They also show them crossing each other near corridoer #303 which cannot be done. If they are continuous, they only make the trims up to 96" long. There will be a gap. The trim PCS only comes in BLIZZARD WHITE and they call for STD white grid. Should the grid be changed to BLIZZARD WHITE to match? Also, with the cancelled tile in this room, it needs support. How ae the linear diffusers being installed? Are the(y) spanning over top of the grid on both sides?

A71. 1. Acoustical ceiling spec for CL-2 should be item #1945 (2'x4' tile). 2. The light fixtures are not continuous. They are 4ft long per specifications. Ceiling grid to accommodate 4” fixture. Where fixture does not exist, provide 4” ceiling tile. Light fixtures, controls and wiring associated with zones 13b and 03b are eliminated from scope. Final color to be selected from standard manufacturers colors. Contractor to provide samples per specifications. Linear diffuser to be installed flush with finish surface of the ceiling system.

Q72. 1- Drawing D1.3 indicates remove & replace pavers ( 25x) Please provide size and material for pavers

A72. The dimensions for the 25 pavers to be replaced are shown in a note on drawing A1.3 (24" x 24"). Replacement for tiles is "match existing."

Q73. Room finish schedule - Rooms 306 & 307 call for FL3 ( WALK OFF MAT). Drawing- A7.3 Rooms 306 & 307 indicate Carpet, Please clarify carpet or walk off matt.

A73. The room finish schedule is incorrect in this instance. The entrance vestibules 306 & 307 have the same carpet (CP-2) as the adjacent rooms inside. There is no walk off mat in these locations.

Q74. Plastic laminated wood locker spec 101523. Where on drawings are they indicated ?

A74. The plastic laminated wood lockers are located in the first floor Interpretive Office 101 (see sheet A6.1) and in the second floor Break Room 315 (see sheet A6.3). There ae ten (10) full height lockers in Room 101 and five (5) 3-tier (3 doors) lockers in Break Room 315.

CLARIFICATION 1: Contractor shall move the storage cabinets that are to remain on the mezzanine floor above the Inner and Outer Vaults (see sub-sheets A1.1 & A1.2) as needed to facilitate contract work. Contractor shall provide appropriate cover or enclosure to protect the cabinets from damage during construction. Upon completion of work, Contractor shall uncover cabinets and return them to their original positions. All materials currently on or about the cabinets, but not contained

140P2018R0026 AMENDMENT 3 DATED 8/10/18 PAGE 13

within them, will be removed by the Park prior to Notice to Proceed. Park has confirmed that archeological items remaining within the cabinets can remain there without any HVAC required.

CLARIFICATION 2: Specification Section 012700 – DEFINITION OF LINE ITEMS, PART 3 – LIST OF CONTRACT LINE ITEMS, 1.a.i revised to read as follows: “Contractor to provide all necessary packing materials and for moving equipment and furnishings from existing Visitor Center to spaces identified within the Park.” Note that park employees will pack items into boxes provided by Contractor.

CLARIFICATION 3: Specification Section 012700 – DEFINITION OF LINE ITEMS, PART 3 – LIST OF CONTRACT LINE ITEMS, 1.a.ii to read as follows: “Contractor to dispose of all provided packing materials and for moving equipment and furnishings from the storage spaces that were identified within the Park back into the rehabilitated Visitor Center.” Note that park employees will unpack items from boxes provided by Contractor.

CLARIFICATION 4: The items to be moved by Contractor from the Visitor Center to designated storage areas, and then returned to the Visitor Center upon completion of the Rehabilitation work, consist of boxed items and furniture, fixtures and equipment. For bidding purposes for this particular work, assume the following:

One (1) flat-bed truck rental for a total of three (3) days Five (5) laborers for a total of three (3) days = 15 man-days = 120 man-hours.

Solicitation Template date 4/25/18

Document No.

140P2018R0026

Document Title

VAFO 211497 – REHABILITATE VISITOR CENTER

D. VOLUME 1 - TECHNICAL PROPOSAL SUBMISSION REQUIREMENTS

TAB A – FACTOR 1 EXPERIENCE/PAST PERFORMANCE

SUBFACTOR 1.A – EXPERIENCE OF THE PRIME CONTRACTOR

Complete the attached Experience Form for up to three (3) substantially completed contracts that the offeror has self-performed within the last five (5) years that can be considered to be relevant to this requirement. For each contract additional information beyond the experience form may be provided as long as the page limit for this factor is not exceeded.

Experience considered relevant includes: Federal contracts, contracts involving construction, rehabilitation, moving collections and office spaces. Contracts requiring the management and coordination of multiple subcontractors, multiple schedules and logistical needs. Contracts involving logistical challenges. Contracts involving construction on sites that are open to the public presenting additional safety and security challenges.

To be considered self-performed for prime contractor experience, the contractor must be have been the prime contractor on the contract and self-performed at least 15% of the cost of the contract, not including the cost of materials, with its own employees.

Contracts considered substantially complete are completed enough to determine performance on all phases.

The submission for this factor should not exceed 9 pages, 12 font, 8 ½ * 11 page size.

NOTE: For purposes of evaluating Prime Contractor experience, the Prime Contractor is defined as the contractor identified in Block 14 of the Standard Form 1442. If more than one contractor is listed in Block 14, then a signed joint venture (JV) must be submitted with the proposal and the JV shall be registered as such in the System for Award Management (SAM). However, each party of the JV must submit their own DUNS number with the JV proposal, list the DUNS numbers in Block 14 with the DUNS number for the JV. Contracts performed by other contractors than the offeror, such as teaming partners or subcontractors, will not be evaluated for prime contractor experience, unless those other contractors are part of a JV offeror as demonstrated by a signed JV agreement. If the Offeror represents the combining of two or more companies as a JV for the purpose of this RFP, each company in the JV may submit project examples, but the total submitted by the JV shall not exceed three (3) contracts.

SUBFACTOR 1.B – PAST PERFORMANCE OF THE PRIME CONTRACTOR

For each contract provided under the experience tab, offeror shall submit the contact information for the customer/client representative that was responsible for the contract and would have the most knowledge of the past performance. In addition, the offeror shall have the reference complete the Past Performance Questionnaire and email it directly to Philip Robinson and Pamela Mault at philip_robinson@nps.gov and pamela_mault@nps.gov.

TAB B – FACTOR 2 TECHNICAL APPROACH

Submit a narrative that describes how the following activities will be executed: site layout including park employee and visitor access, construction of the temporary visitor center, packaging and moving of offices and interpretive spaces, rehabilitation of the Visitor Center, the return of the offices and collections, de-construction of the temporary Visitor Center and site cleanup.

Describe the required labor, materials and equipment for the project.

Describe any known challenges and proposed solutions specific to this project.

Provide a schedule that clearly identifies required activities, major milestones and critical path. The proposed schedule shall be within the period of performance identified in this solicitation.

With the schedule provide a supporting narrative that describes the rationale for the sequencing of the required activities.

The narrative for the technical approach and the schedule’s supporting narrative should not exceed 7 pages, minimum 12 font, 8 ½ * 11 page size.

The submission for the chart schedule and the narrative under this factor shall not exceed 10 pages, 12 font, 8 ½ * 11 page size. should use 11*17 size paper and has no page limit.

140P2018R0026 AMENDMENT 3 DATED 8/10/18 PAGE 15

General Decision Number: PA180123 08/10/2018 PA123

Superseded General Decision Number: PA20170123

State: Pennsylvania

Construction Type: Building

County: Montgomery County in Pennsylvania.

BUILDING CONSTRUCTION PROJECTS (does not include single family homes or apartments up to and including 4 stories).

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.35 for calendar year 2018 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January

1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.35 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year

2018. The EO minimum wage rate will be adjusted annually.

Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

140P2018R0026 AMENDMENT 3 DATED 8/10/18 PAGE 16

Modification Number Publication Date

0 01/05/2018

1 01/12/2018

2 04/20/2018

3 05/04/2018

4 05/11/2018

5 06/01/2018

6 06/08/2018

7 06/15/2018

8 06/22/2018

9 06/29/2018

10 07/20/2018

11 07/27/2018

12 08/10/2018

ASBE0014-002 05/01/2018

Rates Fringes

ASBESTOS WORKER/HEAT & FROST

INSULATOR (MECHANICAL- Duct, Pipe & Mechanical System

Insulation)......................$ 49.30 35.64

BOIL0013-008 03/01/2018

Rates Fringes

BOILERMAKER......................$ 45.89 33.39

BRPA0001-016 05/01/2014

140P2018R0026 AMENDMENT 3 DATED 8/10/18 PAGE 17

Rates Fringes

BRICKLAYER (Including

Pointing, Caulking, and

Cleaning)........................$ 36.41 23.80

MASON - STONE....................$ 36.48 23.77

BRPA0001-017 05/01/2014

Rates Fringes

TILE FINISHER....................$ 20.93 22.09

TILE SETTER......................$ 38.36 22.72

CARP0167-002 05/01/2018

Rates Fringes

CARPENTER (Includes, Acoustical Ceiling

Installation, Batt

Insulation, Drywall Hanging, Metal Stud Installation, Firestopping, Form Work, Gutter Installation, Metal

Flashing Installation, Scaffold Building and Siding

Installation- Metal, Aluminum, and Vinyl).............$ 39.85 27.59

CARP0219-005 05/01/2018

140P2018R0026 AMENDMENT 3 DATED 8/10/18 PAGE 18

MILLWRIGHT.......................$ 43.93 31.79

CARP0251-004 05/01/2018

Rates Fringes

CARPENTER (Floor Laying -

Hardwood, Carpet and Vinyl

Only)............................$ 43.11 28.09

CARP0441-004 05/01/2018

Rates Fringes

PILEDRIVERMAN....................$ 43.45 34.47

ELEC0098-010 04/29/2018

Rates Fringes

ELECTRICIAN (Includes Alarm

Installation, Solar Panel

Wiring and Installation and

HVAC/Temperature Controls

Installation; Excluding Low

Voltage Wiring and

Installation of Sound and

Communications Systems)..........$ 46.89 43.48%+15.46

ELEC0126-008 05/28/2018

140P2018R0026 AMENDMENT 3 DATED 8/10/18 PAGE 19

LINE CONSTRUCTION

Lineman.....................$ 53.64 29.25%+11.25

ELEV0005-002 01/01/2018

Rates Fringes

ELEVATOR MECHANIC................$ 55.76 32.645+A+B

FOOTNOTES FOR ELEVATOR MECHANICS:

A. PAID VACATION: Employer contributes 8% of basic hourly rate for 5 years or more of service or 6% for 6 months to 5 years of service.

B. Eight Paid Holidays (provided employee has worked 5 consecutive days before and the working day after the holiday): New Years's Day; Memorial Day; Independence Day;

Labor Day; Veteran's Day; Thanksgiving Day and the Friday after Thanksgiving Day, and Christmas Day.

ENGI0066-004 06/01/2014

Rates Fringes

POWER EQUIPMENT OPERATOR

Mechanic....................$ 32.59 18.10

140P2018R0026 AMENDMENT 3 DATED 8/10/18 PAGE 20

ENGI0542-040 05/01/2017

POWER EQUIPMENT OPERATOR

Crane, Gradall, Bulldozer, Bobcat/Skid Steer/ Skid

Loader, Loader, Paver

(Asphalt, Aggregate, and

Concrete), Backhoe/

Excavator/ Trackhoe, Boom, Concrete Pump, Crusher, Drill Rig Caissons, Milling Machine, Forklift

(all types).................$ 44.62 27.07

Hoist (Single Drum).........$ 40.53 25.87

Hoist (With Two Towers).....$ 44.62 27.07

Mechanic....................$ 44.62 27.07

Oiler, Articulating Truck

Operator....................$ 37.52 24.98

Pump........................$ 38.51 25.27

Roller......................$ 40.53 25.87

IRON0401-006 07/01/2017

Rates Fringes

IRONWORKER (Reinforcing and

Structural)......................$ 47.30 32.50

LABO0135-003 05/01/2017

140P2018R0026 AMENDMENT 3 DATED 8/10/18 PAGE 21

LABORER (Mason Tender- Brick, Cement/Concrete).................$ 29.17 24.65

LABO0413-008 05/01/2017

Rates Fringes

LABORER

Concrete Worker.............$ 28.65 24.65

PAIN0021-029 05/01/2016

Rates Fringes

PAINTER (Includes Brush, Roller, Spray, and Drywall

Finishing/Taping)................$ 36.80 24.03

* PAIN0252-007 05/01/2018

Rates Fringes

GLAZIER..........................$ 43.32 31.59

PLAS0008-003 05/01/2018

Rates Fringes

PLASTERER........................$ 37.42 29.84

140P2018R0026 AMENDMENT 3 DATED 8/10/18 PAGE 22

PLAS0592-037 05/01/2018

CEMENT MASON/CONCRETE FINISHER...$ 37.50 32.06

PLUM0420-012 05/01/2018

Rates Fringes

PIPEFITTER (Including HVAC

Pipe and HVAC Unit

Installation)....................$ 56.37 34.09

PLUM0420-013 05/01/2018

Rates Fringes

PIPEFITTER

Mechanical Equipment

Serviceman (HVAC Pipe and

Unit Installation Only).....$ 56.37 34.09

PLUM0690-011 05/01/2018

Rates Fringes

PLUMBER..........................$ 53.45 33.24

ROOF0030-013 05/01/2017

140P2018R0026 AMENDMENT 3 DATED 8/10/18 PAGE 23

ROOFER (Includes

Waterproofing, Excludes Metal

Roof Installation)...............$ 36.15 29.76

SFPA0692-003 05/01/2018

Rates Fringes

SPRINKLER FITTER (Fire

Sprinklers)......................$ 55.75 27.02

SHEE0019-020 05/01/2017

Rates Fringes

SHEET METAL WORKER (Includes

HVAC Duct Installation)..........$ 46.42 38.71

FOOTNOTE: Paid Holiday: Election Day

SUPA2011-057 08/20/2014

Rates Fringes

CARPENTER (Metal Roof

Installaton Only)................$ 32.34 0.00

ELECTRICIAN (Installation of

Sound and Communication

Systems Only)....................$ 41.44 20.88

140P2018R0026 AMENDMENT 3 DATED 8/10/18 PAGE 24

ELECTRICIAN (Low Voltage

Wiring Only).....................$ 41.61 20.52

IRONWORKER, ORNAMENTAL...........$ 36.55 24.48

LABORER: Common or General......$ 23.85 19.77

OPERATOR: Drill.................$ 28.55 15.78

OPERATOR: Grader/Blade..........$ 30.46 0.00

TRUCK DRIVER: Dump Truck........$ 21.31 0.00

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the

Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is

140P2018R0026 AMENDMENT 3 DATED 8/10/18 PAGE 25

like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses

(29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate

(weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or

"UAVG" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198

140P2018R0026 AMENDMENT 3 DATED 8/10/18 PAGE 26

indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

140P2018R0026 AMENDMENT 3 DATED 8/10/18 PAGE 27

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010

08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it.