140P2018R0008 x x
3 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
PDS
Denver CO 80225-0287 P.O. Box 25287 12795 W. Alameda Pkwy NPS, DSC Contracting Services Div
PORE 14946903/01/20180002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
02/05/2018
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Solicitation 140P2018R0008 / Amendment 0001
Point Reyes National Seashore
Project Title: Restore the Historic Point Reyes Lighthouse and Enhance Visitor Services and
Interpretation
PORE 149469
The purposes of Amendment 00002 are to:
1) Change the proposal due date to March 13, 2018 at 10:00am Mountain Daylight Time (MDT).
2) Provide contractor questions and government responses.
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Jason Longshore
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
NSN 7540-01-152-8070
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 8
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140P2018R0008/0002
3) Delete and replace 'Attachment 3_Construction
Wage Rates' in its entirety.
All other terms and conditions remain unchanged.
NOTE: The question deadline of March 1, 2018 at
12noon Mountain Time (MT) has passed.
Legacy Doc #: NPS
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
Question and Answer
Spreadsheet
140P2018R0008 /
PORE 149469
Question No. Sheet or Reference Question Response Amendment Answered
During the site visit it was stated that the National Park Service had data regarding the peak visitor times, and presumably seasons. Since the technical proposal is to address public access, can this information be provided?
Total Visitation per year:
2015 ‐ 2,501,106
2014 ‐ 2,433,944
2013 ‐ 2,641,808
2012 ‐ 2,412,663
2011 ‐ 2,129,116
Reference the park website at this address for more information:
https://www.nps.gov/pore/pl anyourvisit/hours.htm
Can the proposal submission date of
March 7th be delayed until at least
March 14th so that a comprehensive proposal can be provided?
The proposal due date remains unchanged as March
7, 2018 at 2pm Mountain
Time. 0001
At at least two locations it was noted during the site visit that there were overhanging trees at the road at several locations that were sufficiently low enough to prevent the use of most trucks(see photo below). Note 6 on sheet L‐1 specifically notes that these branches cannot be cut, and that written permission will be required for bringing trucks or equipment within 18” of the branches. Can a plan be submitted for general use to bring the clearance within 18” or will individual requests be required for each vehicle move?
A Truck Transit plan will be required as a Division 1
Submittal and will be reviewed by the Park for compliance for the protection of the trees.
Specification 01 50 00 paragraph 2.2.a
Specification 01 50 00 paragraph 2.2.a references that the contractor is to supply a 300 square foot office trailer.
There is no area visible on the plans where a trailer this size can be accommodated without impeding the work. Is a trailer required, and if so, can it be located at the main parking lot?
Contractor's means and methods, the park has offered the garage as a potential location for a construction office
Section H, Special Clause 2 Section H special clause 2 of the solicitation references key personnel, Superintendent/Safety Officer and
Quality Control. If the superintendent is qualified, can the role of Quality Control
Manager be included within that position?
No, the QC needs to be separate from the
Superintendent and Safety
Officer. Reference Spec
Section 01 40 00, QUALITY
REQUIREMENTS, 1.5B
Can the Fog Signal Equipment Building be used to store the lens during the lighthouse restoration and during restoration of the lens itself?
The Fog signal building is available for the contractor to coordinate with the lens and clockworks scope with any renovation work that will be conducted in the building.
Can the pedestal and clockworks remain in place during restoration of the lighthouse?
This should be described within the proposal criteria for project approach i.e. means and methods.
What is the anticipated start date for this project?
Proposals are due on March 7, 2018. Anticipate 30 days for review and award. Division 1
Submittals from the selected contractor will be due within
30 days of award. Notice to
Proceed will be provided upon completion of approved
Division 1 Submittals.
Is there a last day to submit questions for this project?
The question deadline is
March 1, 2018 at 12noon
Mountain Time. All questions shall be submitted in writing to sarah_clemmens@nps.gov and jason_longshore@nps.gov.
Contractor questions and
Government responses will be posted via an amendment to
FBO.GOV.
It was mentioned in at the Pre‐Proposal
Conference that use of the Park's wench
& trailer may be possible.
PLEASE NOTE: The wench and trailer will not be available for use by the selected contractor. Government furnished equipment will not be provided under this contract.
It was mentioned at the Pre‐Proposal
Conference that the options would be exercised in a particular order of importance.
PLEASE NOTE: Per the
Contract Price Schedule in
Section B (page 12) of the RFP, "Options may be exercised in any combination, order, or grouping deemed in the judgment of the Contracting
Officer to offer the best value to the Government."
Please confirm the large equipment in the Fog Signal Equipment Building can remain in place during their restoration process. These items include:
Air Compressor Tank
Generator & Batteries
Two Air Compressors
Panel Board
Diaphone Amplifier with Stand
Yes, they may remain in place.
Will the light source replacement be a part of this project?
Contract documents require that contractor "survey and assess (e) conditions to verify scope of necessary repairs."
To "clean and restore historic lens, lamp, and clockworks. At project completion objects shall be restored and fully operational. Reference
Drawing A8.1.
Is the Bid Bond form required? Yes, as indicated in the RFP on page 1 of the SF1442, Block
13B, an offer guarantee is required. Please see the provided SF24_Bid Bond form and coordinate with a surety company to provide a bid bond with your proposal package.
Are there any forms that are not required as part of the submission package?
The document entitled
'E15_Deliverables_LmtOnSubc onRpt_REQD' was provided on
FBO.GOV, but it will not be needed at the time of proposal submission. It is a form that will be utilized by the selected contractor at the time of contract invoicing.
Section 09 96 50 paragraph 1.5.a.1 calls for the metallizing applicator to be certified to SSPC QP3, while paragraph
1.5.a.2 calls for certification to SSPC QP6 for the supervisor. Companies are certified, not individuals, and there are only three companies in the United
States with SSPC QP6 certification.
Additionally, the SSPC QP3 certification references shop applied coatings, given the intent is to recoat the lighthouse in place this requirement is contradictory, should this be changed to QP1 for field applied?
This question will be addressed in an upcoming amendment.
Is there any requirement for California
SHPO review of plans per section 106?
If so which plans will need to be reviewed and approved by SHPO?
All communication with the
SHPO will be conducted through the park staff. The contractor will not be involved with any issues related to
SHPO communications.
Amendment 1 RFI 8 response indicated that the notice to proceed would be based upon approval of the Division 1 submittals. Given that for items such as the lenses, historic concrete, metals, and clockwork, condition reports need to be provided under this contract, restoration plans created, provided, and approved by the National Park Service and possible California SHPO, it is likely that several months could pass before work could be performed. Can the notice to proceed be based upon approval of those plans?
The items identified in the question are not part of
Division 1 submittals from the
Contractor. Please refer to the Submittal Checklist after
Submittal Procedures 01 33
23. SHPO review will not be within the contractors SOW.
Section 01 33 23 lists no submittal requirements for the lens and clockwork restoration, and no specifications are provided for any of these items. Can a list of required submittals and requirements be provided for these items?
This question will be addressed in an upcoming amendment
Amendment 1 RFI response 1 did not provide any information on peak traffic flows and seasons in order to help address the technical proposal requirement regarding planning for public access. Will this information be provided before the bid?
Oct to March are the peak times due to whale watching, as shown on the website provided. In addition, yearly visitation was provided in the response to Question 1, Amendment 0001.
A conditions report was provided that indicated an array of possible repairs to the fog signal equipment, but the plans only reference removal of paint and providing new coatings. What is the scope of work for the fog signal equipment?
Refer to drawing A2.3 for Fog
Signal Equipment scope of work.
Project boundary: During the pre‐bid visit, NPS suggested a forthcoming amendment to the current solicitation documents would be provided showing this project’s start location was at the new ADA parking area and westward.
All scope east of the of the new ADA parking area was not included in this contract.
a. Please confirm project boundary and scope.
b. Please provide construction schedule for the project (by others) to assist in access, coordination, etc.
a. The base project is only the
Lighthouse, Lens, and
Clockworks. Bid Alternate A contains the Site Work identified on drawings C1, C2, and C3.
b. The contractor must provide a construction schedule as part of your proposal
Quality Control Supervisor duties:
Specification section 01 40 00, paragraph 1.5B.1 states the Contractor’s designated Quality Control Supervisor may also perform other duties.
Amendment 1, question 5 states the QC needs to be separate from the
Superintendent and Safety Officer.
Please clarify conflicting statements.
The Quality Control Supervisor and the Superintendent must be separate roles. However, the Quality Control Supervisor may assist in other tasks.
Subcontractor Reference Sheet: The provided “Subcontractor Reference
Sheet” says to use form to list certain subcontractors identified in Section L.
Section L does not state key subcontractor requirements. Please confirm key subcontractors shall be in accordance with Section M (lens and clockwork personnel).
Correct, Section L instructs offerors to include the subcontractor reference form in Volume I of the proposal.
Correct, key subcontractors shall be identified in Section M of your proposal.
Bid date: The Questions and Answers element is important each bidder’s proposal. Per Amendment 1, questions are due Thursday, 3/1. The proposal due date did not change with
Amendment 1. As an effort to provide a responsive proposal, please provide an extended bid due date to allow for bidder’s to incorporate responses into the proposals.
The Q and A deadline was
Thursday, March 1, 2018 at
12noon Mountain Time (MT) and has passed. Per
Amendment 0002, the proposal due date is hereby extended to March 13, 2018 at
10:00am Mountain Daylight
Time (MDT).
Is registry in the System for Award
Management (SAM) required with submission of the proposal?
Offerors shall be registered in
SAM no later than the time of award.
Does the SF30 form for each amendment have to be signed?
Please see the SF1442 document in the RFP package.
The first half of Page 2 is the
Offeror section to be populated. Specifically, Block
19 is where each amendment shall be listed. The offeror shall sign Block 20a on the
SF1442 which shall be considered authorization of the proposal amount (Block
17) as well as acknowledgement of the amendments issued during the solicitation process.