This is an amendment to a Request for Quotation (RFQ) for spray foam installation services at Glacier National Park's Many Glacier Cabins 2 and 3. The solicitation number is 140P1426Q0012, issued by the Department of the Interior National Park Service Intermountain Region. Quoters must submit a single firm fixed-price quotation that is all-inclusive of supervision, labor, materials, supplies, travel, transportation, and delivery for stem wall spray foam installation. The contract price schedule requires line-item pricing with detailed cost breakdowns. Quotes are due by February 26, 2026, at 2:00 PM Mountain Time, submitted via email to the Contracting Officer Sally Leitch. The anticipated award date is March 15, 2026, and quote prices must remain valid for a minimum of 180 days. Questions must be submitted in writing by noon on February 11, 2026.
The evaluation uses simplified acquisition procedures and will assess three factors: price, technical capability, and past experience. Technical capability submissions must include a detailed narrative explaining how the quoter will meet SOW requirements, meet delivery dates, provide warranty information, and supply product documentation—copying the government's SOW or merely restating ability to perform will render the quote ineligible. Past experience documentation must include two examples of similar projects completed within the past three years. All quotes must be submitted in PDF format (8" x 11") with 11-point minimum font, include a completed SF 18 form, completed Provision 52.204-24, quoter contact data, and all amendments if applicable. Late quotes may not be accepted, and the contracting officer retains sole authority to determine quote acceptability. Service Contract Labor Standards apply with Wage Determination 2015-5397 for Glacier County. No site visits will be conducted.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P1426Q0012_Amd_0002.pdf | ||
| Sol_140P1426Q0012_Amd_0001.pdf | ||
| Continuation_SF_30_-_140P1426Q0012_-_Amendment_A00001_0001.docx | DOCX document | |
| Sol_140P1426Q0012.pdf | ||
| B08_RFQ_-_Attachment_1_-_Wage_Determination_2015-5397_Rev_27_Dated_12_3_2025_-_Glacier_County.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Continuation of SF 30 – RFQ 140P1426Q0012 – Amendment A00002 The additional changes to the evaluation information and submission instructions are listed below in Red:
EVALUATION PROCEDURES
This procurement will use Simplified Acquisition Procedures (SAP) in accordance with FAR 13.106-1(a)(2) and FAR 13.106-2(b). Evaluation procedures in FAR 13.106 provide broad discretion in establishing suitable evaluation procedures. Using price and other related factors listed below the contracting officer shall ensure that eligible quotations can be evaluated in an efficient and minimally burdensome fashion using comparative evaluation procedures. Comparative evaluations encourage the use of “best value,” and are not required to state the relative important of evaluation factors or subfactors. This solicitation will evaluate:
1. Price.
2. Technical Capability: A narrative that addresses in the quoter’s own words how they will meet the state requirements of the Statement of Work. This narrative shall contain sufficient information to conduct meaningful evaluations and be based on the requirements and type of work being solicited. Copying the government’s SOW, simply stating your firm can meet the requirements, or just providing a capability statement shall cause the firm’s quote to be ineligible for award and not further considered.
a. At a minimum the quoter shall provide:
i. How the quoter will meet the requirements of the SOW in detail.
ii. How the quoter will meet the required delivery date.
iii. Warranty information
iv. Documentation on the product being installed.
3. Past Experience: Quoter shall provide relevant past performance via factual documentation or narrative of a firm’s experience, qualifications, and capability, along with providing two examples of their firm’s most recent projects within the past three years of similar size and scope.
All eligible quotes shall be evaluated in accordance with the factors described herein. The evaluation factors used in this RFQ are technical, past experience and price. Award will be made to the quoter who is determined to be the overall best value to the Government by using comparative evaluation. A comparative evaluation is where each quote will be compared side-by-side with other quotes to determine the overall best value to the Government.
Quoters are reminded to include their best technical and price terms in their initial quote and not to automatically assume they will have an opportunity to participate in discussions.
Revised quotes will not be accepted.
Quoters may submit more than one quote by the due date and time of quote submission or withdraw in writing the previously submitted quote. If withdrawing the previously submitted quote, it shall be done in writing and a completely new quote is submitted.
All quotes shall be submitted to the CO by the due date and time listed below. As a reminder any quote that is date/time stamped by the CO’s email shall determine the date and time received (not sent by the quoter).
Quotes will receive a preliminary review to determine whether the quote contains sufficient information, as required by the solicitation to be eligible for evaluation. If the results of the preliminary review indicate that the quote lacks sufficient information to allow a meaningful evaluation to be conducted, the Contracting Officer, as the sole deciding authority, may determine a quote as ineligible and may remove the quote from further evaluation and consideration for an award.
Quoters shall not copy the Scope of Work and state the firm can meet the requirement. Nor shall the Quoter copy the Scope of Work and add comments to specific areas. Quoters should submit in their own words their technical approach in how they will complete and comply the requirements of the SOW.
The contracting officer shall conduct the price evaluation, and the technical evaluator(s) will evaluate the technical and past experience portion of the quotes and make a recommendation of award to the contracting officer. If all quotes are determined to be technically equal, the award will be made to the lowest priced quote. Additional details on the evaluation process are detailed below.
In accordance with FAR 9.104 a determination of contractor responsibility or non-responsibility will be made by various systems including but not limited to SAM, CPARS, and FAPIIS.
The following factors shall be used to evaluate quotes for technical and past experience:
Factor 1: Technical Capability
Technical Capability will be initially rated by the technical evaluator(s) as either “Acceptable” or “Unacceptable.” An “Unacceptable” rating shall deem the quoter ineligible for award using comparative evaluations.
| Acceptable |
| Information provided demonstrates the quoter has the technical capability of all contractual requirements of the solicitation, portrays a clear and technical understanding of the project requirements, and has provided all the submission requirements. |
| Unacceptable |
| Information provided does not demonstrate that the quoter has the technical capability of all contractual requirements of the solicitation, does not portray a clear and technical understanding of the project, and did not provide all the required submission requirements. |
The technical evaluators will take the remaining technically acceptable quotes and compare them to one another to determine what quote is the overall best value to the government and make their technical recommendation for award based on this side-by-side evaluation based on the established requirement and information provided in the quoters quote.
Quoter shall provide the following:
Technical Criteria
A narrative that addresses in the quoter’s own words how they will meet the state requirements of the Statement of Work. This narrative shall contain sufficient information to conduct meaningful evaluations and be based on the requirements and type of work being solicited. Copying the government’s SOW, simply stating your firm can meet the requirements, or just providing a capability statement shall cause the firm’s quote to be ineligible for award and not further considered.
a. At a minimum the quoter shall provide:
i. How the quoter will meet the requirements of the SOW in detail.
ii. How the quoter will meet the required delivery date.
iii. Warranty information
iv. Documentation on the product being installed.
Factor 2: Past Experience
Past Experience will be initially rated by the technical evaluator(s) as either “Acceptable” or “Unacceptable.” An “Unacceptable” rating shall deem the quoter ineligible for award using comparative evaluations.
| Acceptable |
| Information provided demonstrates the quoter has the technical capability of all contractual requirements of the solicitation, portrays a clear and technical understanding of the project requirements, and has provided all the submission requirements. |
| Unacceptable |
| Information provided does not demonstrate that the quoter has the technical capability of all contractual requirements of the solicitation, does not portray a clear and technical understanding of the project, and did not provide all the required submission requirements. |
Quoter shall provide the following:
Past Experience
Quoter shall provide relevant past performance via factual documentation or narrative of a firm’s experience, qualifications, and capability, along with providing two examples of their firm’s most recent projects within the past three years of similar size and scope.
The following factor shall be used to evaluate price fair and reasonableness:
Factor 3: Price
All line-item Pricing shall be a firm fixed-price, shall be valid for a minimum of 180 days, and include at minimum supervision, all labor, materials/supplies, travel/transportation/delivery, and other direct costs.
Quoters shall submit their quoted pricing using the Price Schedule found in the checklist below and attach a detailed breakdown for all line-items. Failure to submit pricing and a breakdown for all items will remove the quote from further consideration for award.
The Contracting Office will review the pricing for fair and price reasonableness. For price to be reasonable, it shall represent a price to the Government that a prudent person would pay in the conduct of competitive business.
Service Contract Labor Standards:
The Service Contract Labor Standards Act applies to this procurement. Wage Determination 2015-5397 for Glacier County is attached.
Site Visit:
There will not be a site visit. Quoters are encouraged to review Google Maps, or any other way to understand the area and work prior to submitting their quote. Modifications to adjust pricing shall not be entertained as related to the work required in the SOW.
INSTRUCTIONS TO QUOTERS
Quotes shall be in accordance with and must be in the order detailed in this section. Failure to submit quotes according to the instructions provided within the solicitation may result in the respondent’s quote being determined ineligible and not being considered further for evaluation and award.
Please note the time listed is the time by which all quotes shall be received by, not sent by. Emails will have a received date and time that will show when the quote is received into the contracting officers email box. Quotes submitted after the closing date and time may not be accepted.
Please Note to All Quoters: Adjustments are not allowed to the quote once received. It is the quoters responsibility to follow these instructions if the instructions are not followed the quote may not be considered acceptable and could be removed from further consideration. The CO is the deciding authority if the instructions are followed. This procurement follows FAR Parts 12 & 13.
A quote that merely reiterates or promises to accomplish the requirements of the RFQ will be considered incomplete and not considered further for award. A Quote that is orderly, provides all required items in the submission checklist, and is sufficiently documented will enable the Government to perform meaningful and fair evaluations. Quotes that fail to address any of the items listed in the submission checklist shall be deemed incomplete, and the Quote will not be further considered for award.
If a Quoter believes that the requirements in these instructions contain an error, omission, or are otherwise unsound, the Quoter shall immediately notify the Contracting Office in writing (email is the preferred method) and shall include supporting rationale. All concerns shall be submitted to the Contracting Officer, Sally Leitch at Sally_Leitch@nps.gov. The contracting officer shall make the decision whether or not, based on supporting evidence, if a change is needed.
By submission of its Quote, the Quoter accepts all solicitation requirements, including terms and conditions, representations and certifications, and technical requirements. Quoters shall clearly identify any exception to the solicitation and conditions and provide complete accompanying rationale.
Redlines or changes in the Terms and Conditions shall not be accepted.
Quotes shall be valid for a minimum of 180 days.
Questions:
All questions shall be submitted in writing by Noon (12:00 PM, Mountain Time (MT)) on 2/11/2026, via email to the CO, sally_leitch@nps.gov. Phone calls shall not be accepted.
Quote Due Date & Time:
Quoters shall submit a quote to the CO via email to sally_leitch@nps.gov by the closing date and time of 2/26/2026, at 2:00 PM (MT). Late quotes may not be accepted.
Late Quotes:
Quotes received after the closing date and time may not be accepted. The determination in accordance with FAR 52.212-1(f)(2)(ii), Late Submissions to accept a late quote will be made solely by the Contracting Officer. It is the responsibility of the quoter to ensure that the entire quote is received, not just sent. If attachments do not open may render the quote unacceptable and may not be further considered for award. All quotes received have a date and time received into the contracting officer’s email. This date and time will be the determination if a quote is late.
Anticipated award date: 3/15/2026.
Quoters shall submit the following information in its entirety in PDF format via email:
Format for Quotes:
1. Quotes shall be 8 ½” x 11” .pdf format
2. A page is defined as one face of a sheet of paper containing information
3. Typing shall not be less than 11 pitches (Times New Roman/Ariel/etc., narrow border, no artistic script for readability).
4. Elaborate formats, bindings, or color presentations are not desired or required
5. Email(s) cannot exceed 10mbs
Overview of Acceptability Submission Requirements (in the order listed below):
· Submission Checklist
· SF 18, completed and signed
· Amendments, if applicable, completed and signed.
· Completed Provision 52.204-24
· Completed Quote Contact Data
· Contract Price Schedule
· Quote Technical Information
· Quote Past Performance Information
SUBMISSION CHECKLIST:
Submission Checklist
Quote Submission Requirements
Completed and signed SF 18 Sections:
8a-f, 13a-f, & 14 - 15 on page 1 of this document
| ☐ |
| Completed Provision: (Entire Provision) |
52.204-24 pages 22 - 24 with highlighted portions on page 23 filled out.
| ☐ |
| Completed Amendments, if amendments are posted, it is the quoters responsibility to ensure they have returned all amendments |
Blocks 8 and 15a-c
| ☐ |
| Complete and Return: |
Quoter Contact Data Quoters Name:
Address:
City/State/Zip:
Quoters POC:
Quoters email:
Quoters Phone:
Quoters SAM ID:
Quoters Cage Code:
Quoters Business Size:
| ☐ |
| Contract Price Schedule |
Complete and Return:
Pricing shall not be referenced anywhere else in the quoter’s Quote submission.
Solicitation Number: 140P1426Q0012
GLAC Many Glacier Cabins 2 & 3 Spray Foam Installation Services
QUOTER NAME:
Notice: Pricing is all-inclusive and shall be a firm fixed price, shall be valid for a minimum of 180 days, and shall include at minimum supervision, all labor, materials/supplies, travel/transportation/delivery, and other direct costs.
Contractor shall include a breakdown of all associated costs in the total price to assist with fair and reasonable price determination.
In case of error in summation, the total of the corrected amounts governs. Round totals and extended prices to whole dollars.
Quoters shall submit their quoted pricing using the Price Schedule found in the checklist below and attach a detailed breakdown for all line-items as an attachment. Failure to submit pricing and a breakdown for all items will remove the quote from further consideration for award.
The Contracting Office will review the pricing for fair and price reasonableness. For price to be reasonable, it shall represent a price to the Government that a prudent person would pay in the conduct of competitive business.
Quoter acknowledges by presenting the proposed pricing herein that all pricing shall be held firm for 180 days from the date and time the Quotes are due.
| Line-Item Number |
| Contract Line-Item Title |
| Quantity |
| Unit of Measure |
| Line-Item Price |
| 10 |
| Spray Foam Installation at MG 2&3 cabin stem walls |
Price shall be all inclusive.
All work shall be in accordance with the SOW.
| 1 |
| By Dollars |
| $ |
| Total Firm Fixed Price |
| $ |
All invoices shall be submitted through the IPP invoicing platform.
| ☐ |
| Required Technical |
A narrative that addresses in the quoter’s own words how they will meet the state requirements of the Statement of Work. This narrative shall contain sufficient information to conduct meaningful evaluations and be based on the requirements and type of work being solicited. Copying the government’s SOW, simply stating your firm can meet the requirements, or just providing a capability statement shall cause the firm’s quote to be ineligible for award and not further considered.
a. At a minimum the quoter shall provide:
i. How the quoter will meet the requirements of the SOW in detail.
ii. How the quoter will meet the required delivery date.
iii. Warranty information
iv. Documentation on the product being installed.
Required Past Experience
| Quoter shall provide relevant past performance via factual documentation or narrative of a firm’s experience, qualifications, and capability, along with providing two examples of their firm’s most recent projects within the past three years of similar size and scope. |
| ☐ |
(End of Addendum)
File details come from the government source that posted it. Updated .