Amendment_1_Q_As_0001.docx

DOCX document 15 KB Posted

Attached to
DINO QUARRY AREA FUELS SYSTEM UPGRADE Federal contract opportunity
Solicitation number
140P1423R0016
Issued by
Department of the Interior National Park Service Intermountain Region

About this file

This document is an amendment to a solicitation providing questions and answers regarding Solicitation Number 140P1423R0016 to replace above ground fuel storage tanks at Dinosaur National Monument. The amendment accepts moving the completion date to no later than May 30, 2024 to accommodate current manufacturer lead times. It also allows asphalt replacement work to occur in spring 2024. A combination pin and card system is preferred over the specified PV100 system, and a PV200 would be acceptable. The contractor shall provide a minimum of 100 gallons of each fuel type for testing and training rather than the park providing fuel.

View the file

Other files for this federal contract opportunity

Other files attached to DINO QUARRY AREA FUELS SYSTEM UPGRADE, newest first.
File Type Posted
Sol_140P1423R0016_Amd_0001.pdf PDF
Attachment_8_-_Limitation_on_Subcontracting_Worksheet.docx DOCX document
Attachment_5_-_SECTION_312317_TRENCHING_UTILITIES.docx DOCX document
Sol_140P1423R0016.pdf PDF
Attachment_1_-_Scope_of_Work.docx DOCX document
Attachment_6_-_SECTION_321600_PAVEMENT_AND_WALKS.doc DOC document
Attachment_3_-__Wage_Determination.pdf PDF
Attachment_2_-_Bollard_Detail.pdf PDF
Attachment_7_-_Past_Performance_Questionnaire.doc DOC document
Attachment_4_-_SECTION_033000_CAST_IN_PLACE_CONCRETE.DOC DOC document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

July 25, 2023

AMENDMENT 1

Solicitation #140P1423R0016 Replace Above Ground Fuel Storage Tanks, Dinosaur National Monument

Questions and Answers:

Question 1: The project documents state a completion date of Nov 31st. We do not anticipate it being possible based on current manufacturer lead times to have new tanks by then. Would it be possible to procure the tanks over the winter, and do the work spring of 2024?

Response 1: This is acceptable to the National Park Service. Work shall be completed no later than May 30, 2024.

Question 2: Additionally, this project would likely require asphalt replacement, which would need to be done in conjunction with tank work, and also move to spring. Is that acceptable?

Response 2: This is acceptable as long as the removal and replacement are done in a reasonable time frame. The asphalt cannot be left unrepaired over the winter.

Question 3: The project documents require a card reader system (a PV100 with 81 cards). The PV100 does not take cards. If cards are required, we would suggest a PV200 or maybe a Fuelmaster system. Are cards a requirement, and if so, should Contractor change to a card compliant system, or stick with the system specified?

Response 3: A combination pin with card system is preferred per Section 5.0-12.a. of the SOW. If a PV200 accomplishes the intent of this section, it would be acceptable.

Question 4: Typically, at completion of the installation, the Park (or customer entity) will fill the fuel tank via an existing contract that the park already has, versus the contractor charging the park to get fuel from the same source. Is there a known entity providing fuel to the park, and if so can their name/any contact info be provided? Would the park rather provide fuel at completion of the work to avoid the installing Contractor's markup?

Response 4: The contractor shall provide 100 gallons of each fuel type, or the minimum required by the equipment manufacturer for testing and training, whichever is greater.

END OF AMENDMENT 1