B09_Questions_and_Answers_0001.docx
DOCX document 13 KB Posted
- Attached to
- INSTALL 2 WATER WELL PUMPS Federal contract opportunity
- Solicitation number
- 140P1324Q0031
About this file
This document contains questions and answers related to Solicitation 140P1324Q0031 for the installation of two water well pumps at Guadalupe Mountains National Park. The solicitation seeks to replace existing well pump equipment, with the new pumps to be installed at the Pine Spring/13/Glover and Dog Canyon/1/Sara Ann well sites. The key details provided include:
The existing pump equipment at Pine Spring/13/Glover was installed in 2015, while the Dog Canyon/1/Sara Ann equipment was installed around 2009. No significant issues have been reported with the existing equipment, and it is being replaced due to age and usage hours. The water quality is scale-forming, which may have affected the existing drop pipes, though the extent is unknown until the pipes are inspected. The length of the drop pipes is also unknown. The solicitation will require the contractor to inspect, splice (if necessary), and reinstall the existing pump wiring.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B09_Questions_and_Answers_3_0003.docx | DOCX document | |
| Sol_140P1324Q0031_Amd_0003.pdf | ||
| Sol_140P1324Q0031_Amd_0002.pdf | ||
| B09_Questions_and_Answers_2_0002.docx | DOCX document | |
| Sol_140P1324Q0031_Amd_0001.pdf | ||
| Sol_140P1324Q0031.pdf | ||
| B03_Wage_Determ.pdf | ||
| A04_scope_of_work.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Guadalupe Mountain NP Solicitation 140P1324Q0031 Install Well Pumps Responses to Questions Received and/or Additional Updates
April 2nd, 2024 – Amendment 1 The following questions were received, this amendment provides responses.
1. What is the age of installed equipment? Meaning the pump and cable that contractor is replacing?
Answer: Pine Spring/13/Glover equipment was installed in 2015.
Dog Canyon/1/Sara Ann equipment was installed in or around 2009
2. What are the issues the operators are seeing with the wells?
Answer: No issues, equipment is being replaced due to age and number of hours.
3. Has the raw water quality affected the drop pipe? Questions are to help give an idea of methods or precautions will have to use with the removal.
Answer: Unknown until the pipe is pulled. Based on water quality and Langelier index calculation, water is scale forming. Pipe might have mineral deposits.
4. The drop pipe length, is it 20-24 feet in length or 28-32 feet?
Answer: Unknown, the last company to pull the pumps was Well Service, Inc Artesia, NM.
5. Size of pump wire installed, is it the same as the provided equipment?
Answer: Pump wire will be spooled, inspected, and spliced (if necessary), and reinstalled.