Questions_and_Answers_Nov_10_0005.xlsx

XLSX spreadsheet 18 KB Posted

Attached to
NHOTIC AV SYSTEM REPLACEMENT
Solicitation number
140L4326Q0126
Issued by

About this file

This is a Questions and Answers document for the NHOTIC AV System Replacement solicitation issued by the Department of the Interior Bureau of Land Management Oregon-Washington. The document addresses clarifications on existing equipment, system specifications, installation responsibilities, and operational requirements for upgrading audiovisual systems at the facility.

Key technical clarifications include confirmation that existing Atlas/Soundolier 15-watt speakers (approximately 35 years old) may be reused if operational, and that integrated touchscreen solutions such as Mimo displays are acceptable alternatives to separately specified ELO Touch displays and BrightSign players, provided they meet required functionality. The Government confirmed power and data are available at exhibit locations with existing conduit, and the contractor is responsible for supplying low-voltage conduit/raceway, electrical work, and post-demolition finish work including drywall repair, patching, and painting. Installation of reader rails, kiosks, and touchscreen monitors in Section C.3 will be performed by the Government; the contractor supplies only these items. Regarding hearing assist systems, the contractor should design and propose a system meeting facility needs rather than adhering strictly to the specified Listen LT800 transmitter. The Government will provide Oregon Trail imagery, so physical printed backdrops are not required. For payment, the contract uses IPP.gov with invoicing by contract line item for accepted delivered items in accordance with the Prompt Payment Act, and a 24-month warranty from project completion is required. The contractor may propose a phased room-by-room installation approach, use existing conduits, place secure storage (conex) in the upper parking lot, and work during normal business hours Monday through Sunday with limited winter closures on Mondays and Tuesdays. Bonds and specific insurance requirements beyond standard workers' compensation are not mandated for this fixed-price contract.

View the file

Other files

File Type Posted
Sol_140L4326Q0126_Amd_0005.pdf PDF
Sol_140L4326Q0126_Amd_0004.pdf PDF
Questions_and_Answers_Oct_28_0004.xlsx XLSX spreadsheet
Plan_of_Center_Rooms_0004.pdf PDF
Sol_140L4326Q0126_Amd_0003.pdf PDF
Questions_and_Answers_Oct_7_0002.xlsx XLSX spreadsheet
Sol_140L4326Q0126_Amd_0002.pdf PDF
B03_Wage_Determination_0002.pdf PDF
AV_Images_0002.zip ZIP file
Sol_140L4326Q0126_Amd_0001.pdf PDF
Sol_140L4326Q0126.pdf PDF
B03_Wage_Determination.pdf PDF
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

QuestionAnswer
1. Existing Paging Speakers
Please confirm, if available:
Existing speaker wattage/ratingThe speakers are atlas/Soundolier VARI-TAP 15 Watt Speakers
Approximate age of the speakersThey are approximately 35 years old.
Whether the existing paging speakers are intended to be reused under the replacement system or replacedThe Speakers can be reused if the contractor determines they are in working order
2. Orientation Gallery – ELO Touch / BrightSign Configuration
Would BLM accept an integrated Mimo touchscreen with BrightSign Built-In in place of the separately specified ELO Touch display and BrightSign player, provided the integrated unit meets the required touchscreen, media playback, control, accessibility, and performance requirements?Yes we would accept an alternative touchscreen such as Mimo, the goal is the functionality, specs are to show the level of function we are requesting and proposal should have equivalent functionality, but does not need to be the listed brand or item.
3. Display / Interactive Mounting Locations
For the displays and touchscreen interactives, can BLM identify which units are intended to be:
Wall mountedThe two touch screens for the info desk and fee desk are wall mounted
Installed on a standThe touch screens in the three galleries are to be mounted on stands
Installed within a kiosk/exhibit enclosureThe touch screens will be installed in the exhibit halls.
4. Power and Data Availability – Exhibit Locations
Please confirm whether power and data are currently available at the locations associated with:
Section C.2.8Power and data are present and conduit is run to then to add more if needed.
Section C.2.9Power and data are present and conduit is run to then to add more if needed.
Section C.3 – Leo Adler TheaterPower and data are present and conduit is run to then to add more if needed.
Sections C.3.1, C.3.2, C.3.3, and C.3.4Power and data are present and conduit is run to then to add more if needed.
Where additional AC power is required, is BLM expecting new receptacles to be installed as part of this contract? If so, should those receptacles be wall-mounted, floor-mounted, or coordinated based on the final exhibit location?Section C.3.1-4 is requesting the vendor supply these items, the BLM will handle install at a later date since content for these will be developed under a different contract.
5. 34-Inch Reader Rail Interactive Displays – Power
The six 34-inch Reader Rail interactive displays require standard AC power rather than PoE. Please confirm the intended power source at each reader-rail location and whether existing receptacles are available.AC power, The BLM will install these at a later date.
6. Existing Ideum Systems
Are there currently any Ideum touchscreen/table/interactives operating at NHOTIC? If so, please identify the applicable exhibit/location and whether any existing mounting, power, data, or infrastructure is intended for reuse.Currently there are not Ideum touchscreen interactives operating at the site.
7. Hearing Assist / Audio Description – Items 014 and 015
The equipment list identifies:
014 Hearing Assist Tx – Listen LT800 hearing-assist transmitter
015 Audio Des. Tx – Listen LT800 hearing-assist transmitter
Please confirm whether the use of the same LT800 transmitter for both functions is intentional or whether one of these listings is a typographical error.This looks to be a Typo, NHOTIC currently does not have a hearing assist system, the goal is to have the contractor provide a hearing assist for the center as part of the contract. We would request the contractor design and propose a system that meets our needs, and does not have to be locked in on number or type.
If the LT800 is no longer available as a current-production product, may the contractor propose a current-production Listen Technologies successor/equivalent, such as the LT-84 if technically appropriate, subject to meeting the required functionality?Yes.
8. Leo Adler Theater Lighting – Diffusion Frame Quantity
The equipment schedule identifies:
001 Front Lights – Spot: ETC ColorSource Spot Jr., Deep Blue, Black, CSSPOTJRDB2550 – Qty. 6
002 Front Lights – PAR: ETC ColorSource PAR Deep Blue, Black Body, CSPARDB – Qty. 4
003 Narrow Diffusion Frame: 7.5-inch Narrow Round Diffusion Frame, SELRN-7.5 – Qty. 4
Please confirm whether the Qty. 4 diffusion frames is intentional and intended only for the four PAR fixtures, or whether additional diffusion frames are required for the six Spot fixtures.They are not needed for the six spots under the proposed specs, however the contractor can propose a system with equivalent functionality that includes them if they think it best for overall use of the lights.
9. Green Screen Studio – Backdrops
The requirement currently identifies one set of three to five printed pull-down backdrops related to the Oregon Trail.
Please confirm whether BLM specifically requires physical printed pull-down backdrops, or whether an electronically displayed/projected backdrop solution using Government-provided Oregon Trail imagery would satisfy the intended requirement. BLM previously clarified that the Government will provide the imagery/artwork and that artwork creation is not part of the contractor’s scope.This requirement was inadvertently left in the final SOW and is not needed.
Who is responsible for conduit/raceway for low-voltage cabling — the AV contractor, electrical contractor, or owner?Contractor
Who is responsible for electrical work required to support the AV systems?Contractor
Who is responsible for post-demolition finish work (drywall repair, wall patching, painting, fire-stopping)?Contractor
Will parking be provided for the contractor's crew and vehicles? What is the distance from the jobsite building?Yes, contractor may park in the parking lot adjacent to the building, approximate 150 feet from the center, and can also use the loading dock to deliver supplies.
Can equipment be delivered to the site prior to the installation period? Is there a designated person to receive deliveries?Yes, the project COR would be the designated person
Will secure on-site storage be available for AV equipment, tools, and materials during (and before) installation?There is limited space to store items in the admin space in the center, the contractor may place a conex in the upper parking lot to securely store items.
What are the approved working hours (e.g., standard business hours, after-hours, weekends)? Are there restrictions such as holidays or alternate Fridays?The center is staffed 7 days a week, staff is on site from 8 am to 5 pm in the summer, at 8 am to 4 pm in the winter. Work can be done during normal business hours, there is no restriction on Friday work, however during the winter, the center is closed to the public Monday and Tuesday, but staff is on site. If a federal holiday falls during the winter on Monday or Tuesday the center may be closed, if it falls on the rest of the week it will likely be open, except for Thanksgiving, Christmas, and New Years.
What is the required maintenance period after installation, and what frequency is expected (annual, bi-annual, quarterly, monthly)?We are looking to gauge the approximate annul maintenance cost as part of our determination to make sure we can afford the upkeep on the proposed system.
What warranty period is required for equipment (manufacturer pass-through warranty)?We are requesting a 24 month warranty from completion of the project.
What warranty period and response times are required for contractor service (email/call response time, on-site response time)?We do not have a set expectation, we would expect it to fall in industry standards to response.
Will remote access to the AV system be permitted for ongoing support? If so, what are the access requirements and approval process?Depending on the system and if IT sees no security risks the system can be remotely accessed, it will have to be cleared with IT security.
Most of the theater seem have an "One auto/manual button" requirement. Are we allowed to offer a wall button controller with audio IO with it?Yes
In the Theaters, same with the other spaces, it seems it does not have a rack cabinet requirement. Is there an existing rack we will be reusing?The Leo Adler Theater has an existing rack, the three small theaters do not. They were originally run from a central AV closet, and the racks were removed about 8 years ago. The contractor may propose reusing the central AV closet, if so racks would be needed. There is no space for a rack to be placed in the 3 small theaters.
Any existing device per room/space you want us to integrate/reuse?No
For the rooms with projector and projector screens, was the screen size verified in relation to the throw distanceYes, the current screen is 4:3 Ratio and we would like to shift to a 16:9 ratio
Please let us know the existing controller /dimmer of the site lighting system. This is to verify with processor the controlsCurrent dimmers are Radia Lighting Control System by AMX Corperation
Are we allowed to use existing conduits?Yes
Are there any specific cable requirements (i.e. Plenum rated, Fire Rated, etc)None as far as I know.
Will the Brigthsign media player storage/ SD Card included on our proposal? If on us, what is the side and Specification of it?We would request the vendor provide the SD cards, we would defer to the vendor on the specs to make sure it is compatible with the selected media player.
Any UPS - Unerupted Power Supply Requirement?We did not speck any UPS in the scope, however we would defer to the contractor on functionality and if they would recommend them as part of their proposal.
Are there any IT restrictions that we should know?The preference is to have the system independent of the secure DOI network, if it need to go on the DOI network it would need IT security review.
Please confirm that you require only "HD" Media player? Only at High Definition resolution? or are you looking at 4k resolution?We are looking for HD or better for any of the video players, the vendor can recommend a 4K player as part of their design. The listed specs are the minimum functionality we are looking for.
Section C.1.1 (Amendment 0002, page 4) allows the Contractor to request a payment schedule of smaller lump sums as timeline milestones are achieved, and the IPP clause in Section G (page 30) calls for invoices billed by contract line item. May that schedule be set by Section B line item (0010 through 0050) or by installation phase, so that each item is invoiced once it is installed and accepted rather than at completion of the whole project? Should quoters propose the milestone schedule in the quote, or will it be set with the Contracting Officer and COR after award, as the October 7 Questions and Answers (row 77) indicate?The invoicing schedule can be discussed after contract award. The contract permits payment for items accepted by the Government.
Section L.2.1, Evaluation Factor 2 (Amendment 0002, page 41), asks for recent contracts of similar scope, and provision 1510-52.213-70 (page 43) allows past performance to be based on "other reasonable basis." UA LLC will subcontract the AV integration and installation to a small business AV integrator, which will be named in the subcontractor list required by Section C.1.2 (page 5). May the quote submit that integrator's recent contracts of similar scope as past performance under Factor 2, and will they be considered in evaluating UA LLC's quoteYes
Section C.3 (Amendment 0002, page 14) says the reader rails, kiosk and touch screen monitors will be installed, and the October 7 Questions and Answers (row 71) say the kiosk and monitors will be mounted in a stud wall and the table bolted to the floor. However, row 40 of the same Questions and Answers says installation is not needed for these touch screen devices. For Item 2, Touch Screen Interactive (line item 0020), should quoters price supply, delivery, setup and testing only, or also mounting and installation of the six reader rails, the kiosk, the table and the two monitors?This was missed in the review, at this stage the BLM will do the install of the items listed in section C.3. The vendor is only requested to supply the items.
Equipment Staging and Storage
Will secure on-site space be available for staging and storing AV equipment and installation materials during performance? If not, may the contractor place a portable storage unit on the property, and are there any restrictions regarding location, access, size, or placement?The contractor may place a conex in the upper parking lot and use it as secure storage throughout the project. There is limited space in the facility to store equipment and supplies.
Display Accent Lighting
May the contractor include replacement of existing display accent lighting throughout the facility where it supports the overall AV presentation and exhibit aesthetics, or should lighting work be limited strictly to the fixtures and systems specifically identified in the solicitation?Yes the contractor may propose updates to accent lighting as part of their proposal
Wall/Ceiling Access and Finish Restoration
Where wall or ceiling access is required for cabling and equipment installation, please clarify the contractor’s restoration responsibilities. Are there established requirements for drywall repair, ceiling repair, texture matching, painting, paint colors/sheens, flooring restoration, or other finish work? Are there any areas or finishes that require special approval or handling before being disturbed?The Contractor would be responsible, there are no finishes that would require special approval, when working on updates to the three exhibit areas the contractor would need to coordinate with the curator on any concerns.
Room-by-Room Installation Approach
Would the Government accept a phased room-by-room installation approach in which each area is completed as fully as possible—including installation, testing, patching, finish repair, texture matching, and painting—before work begins in the next area, with the goal of minimizing disruption and maintaining museum operations?Yes a phase approach world be ideal.
Sequencing and Operational Access
Are there any required room sequences, restricted work areas, visitor-hour limitations, or other operational constraints that should be incorporated into the contractor’s installation schedule beyond the work-hour requirements already stated in the solicitation?Work should be able to proceed during normal business hours Monday to Sunday. Federal Holidays in the winter that fall on Monday or Tuesday lead to no staff being available to be on site.
What is the payment method/terms for this contract (Net 30, Net 45, progress payments, WAWF, etc.)?Payment will be made via IPP.gov. Payment shall be made for items accepted by the Government that have been delivered to the delivery destinations set forth in the contract. The Government will make payment in accordance with the Prompt Payment Act (31 U.S.C. 3903) and prompt payment regulations at 5 CFR part 1315.
Are bid, performance, and/or payment bonds required? If so, what percentage of contract value applies to each?Bonds are not required.
What insurance is required (Workers' Compensation, Commercial General Liability, Auto Liability, Umbrella), and what are the required coverage limits?The Government is not ordinarily concerned with the contractor’s insurance coverage when the contract is a fixed-price contract. Contractors are required to comply with applicable Federal and State workers’ compensation and occupational disease statutes.

File details come from the government source that posted it. Updated .