Questions_and_Answers_Part_1_of_2_0001.pdf

PDF 2 MB Posted

Attached to
CFO JANITORIAL SERVICES (5 YEAR)
Solicitation number
140L3926Q0031
Issued by

About this file

This is a Questions and Answers document (Part 1 of 2) for a federal janitorial services solicitation issued by the BLM-Nevada State Office for the Caliente Field Office and Fire Station (Solicitation Number: 140L3926Q0031).

The document addresses 23 questions from prospective offerors regarding solicitation requirements and processes. Key clarifications include: attendance at the November 5, 2026 site visit is not mandatory; the evaluation method is Lowest Price Technically Acceptable (LPTA); past performance is not an evaluation factor but debarment/suspension status is reviewed for all offerors; subcontractors need only provide their company name for disclosure; and offerors may submit subcontractor experience and references to support technical evaluation. Regarding labor standards, FAR 52.222-55 (Executive Order 14026) has been removed and the applicable minimum wage is Wage Determination 2015-5599, occupation code 11150 (Janitor) at $17.53 per hour. FAR 52.222-43 (Fair Labor Standards Act and Service Contract Labor Standards—Price Adjustment for Multiple Year and Option Contracts) applies, permitting price adjustments upon receipt of updated wage determinations before each option year exercise. Service Contract Labor Standards wage and fringe benefit requirements apply to all personnel, including subcontractor employees. Offerors should price future wage increases into their option year quotes. The seasonal fire station restroom/shower cleaning work should be included in the annual contract line-item price. Floor plans for both the Caliente Field Station Building and Caliente Fire Station have been added to attachments, along with photographs of various interior spaces showing flooring conditions.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Caliente Field Office and Fire Station Janitorial Services Issuing Office: BLM-NV State Office

Location: BLM-NV Caliente Field Office Solicitation Number: 140L3926Q0031

Questions and Answers Part 1 of 2

1. Please confirm whether attendance at the organized site visit on November 5, 2026 is a condition of eligibility for award. Is attendance at the November 5 site visit required to submit a quote? Will answers given at the site visit be incorporated into an amendment?

Answer: Attendance to the organized site visit on November 5, 2026 was not mandatory for submission of a quote for this solicitation. Questions and answers that occurred during the site visit will be incorporated into the next amendment 140L3926Q0031 P00002.

2. The quotation instructions identify the evaluation approach as Lowest Price Technically Acceptable (LPTA). However, the detailed evaluation language also describes a comparative best-value process under which an award may be made to an offeror other than the lowest-priced technically acceptable offeror.

Answer: The evaluation process will be based on lowest price technically acceptable. The best-value comparative evaluation verbiage has been removed from pages 25 and 26 of the provision packet.

3. Please confirm the option exercise process/timing, noting option year one shows an anticipated exercise date of 12/01/2027 while option years two-four show 10/01 dates, with performance periods beginning 12/01 each year.

Answer: The anticipated exercise date is the date for each option year that you will be notified if the customer desires to exercise the option year. You will be sent a Notice of Intent letter along with an updated wage determination. You generally have 30 days to request a price adjustment based on the new wage determination rates.

4. Past performance is requested in Part 1 but is not listed as an evaluation factor. Please confirm the basis of award, whether past performance will be evaluated, and whether past performance of a proposed subcontractor that will perform the work may be submitted. Will past performance be evaluated? If so, how many references, how recent, and in what format? May I submit the subcontractor’s past performance?

Answer: The request for past performance has been removed from page 25 of the solicitation packet. Key personnel for the project and their relevant experience has been removed as an evaluation factor from page 26. For future reference, offerors may submit a subcontractor’s past performance. When past performance is requested, you will be directed at that time as to required information.

*Please note that past performance in regard to debarment, suspensions, etc. are evaluated for every offeror.

5. Clause 52.222-42, Statement of Equivalent Rates for Federal Hires, is listed in Section 2 but the statement itself does not appear in the solicitation package. Please provide the applicable statement.

Answer: Clause 52.222-42 is incorporated by reference, and the full clause can be found at acquisition.gov.

https://www.acquisition.gov/far-overhaul/far-part-deviation-guide/far-overhaul-part-52

6. FAR 52.222-55 / EXECUTIVE ORDER 14026. Clause 52.222-55, Minimum Wages for Contractor Workers Under Executive Order 14026, is listed in Section 2. Executive Order 14026 was revoked by Executive Order 14236 on March 14, 2025, and the Department of Labor has stated it is no longer enforcing that order or its implementing rule at 29 CFR part 23. Please confirm that the applicable minimum wage floor for pricing purposes is the Wage Determination 2015-5599 rate for occupation code 11150 (Janitor), $17.53 per hour.

Answer: FAR 52.222-55 Minimum Wages for Contractor Workers Under Ex. Order 14026 has been removed. Occupation code 11150, Janitor, does apply.

7. Please clarify how changes to the applicable Service Contract Act wage determination and health and welfare fringe benefits will be handled during the four option years. Additionally, please confirm the intended applicability of FAR 52.222-55 in conjunction with the wage determination and FAR 52.222-62 included in the solicitation.

Answer: Please see 29 CFR § 13.5 or the department of labor website for fringe benefits. Before each option year is exercised, you will be sent a notice of intent as well as an updated wage determination. At that time, you will be able to request a price adjustment based on updated wage rates.

8. Will option-year prices be adjusted if the wage determination is revised? Section 2 incorporates labor-standard provisions but does not list FAR 52.222-43 or 52.222-44. Please confirm the intended mechanism for addressing revised wage determinations and related labor obligations during option periods.

Answer: FAR 52.222-43 Fair Labor Standards Act and Service Contract Labor Standards—Price Adjustment (Multiple Year and Option Contracts) is now incorporated by reference.

9. Should quoters price any future wage increases into the option years?

Answer: Yes, quoters should price future wage increases in their option year quotes.

10. Does FAR 52.219-14, Limitations on Subcontracting, apply to this set-aside?

Answer: FAR 52.219-14, Limitations on Subcontracting, is not part of this solicitation.

11. Section four requires the quote to include the subcontractor's company name, supervisor, and contact information. Could you confirm the expected format for this disclosure, and whether any additional subcontractor information (past performance, staffing) should be included with the technical quote?

Answer: No specific format is required for listing a subcontractor; simply provide the subcontractor's name.

12. Disclosure of any subcontractor is mandatory in the quote. What must be disclosed — the subcontractor's name only, or also its qualifications, insurance, and scope?

Answer: The subcontractor’s name is the only disclosure requested.

13. The SF-1449 references FAR 52.212-3 and 52.212-5 as attached, but they do not appear in the solicitation document. Please confirm which version applies or provide them.

Answer: FAR 52.212-3 and FAR 52.212-5 were removed during the Revolutionary FAR overhaul and is no longer applicable.

14. Is an estimated contract value or budget range available?

Answer: This information cannot be provided.

15. Is this a new requirement or a follow-on contract? If it is a follow-on, please provide the incumbent contractor, the current contract number, and the current annual contract value.

Answer: This contract is for a new requirement. The previous contract for this action was 140L3926P0031 and the information can be found on SAM.gov.

16. Please confirm the applicable workshare and subcontractor-disclosure requirements, and whether the performing subcontractor’s experience and references may support the technical evaluation.

Answer: Yes, you may submit the subcontractor’s experience and references to support the technical evaluation. FAR 52.219-14, Limitations on Subcontracting, is not part of this solicitation.

17. May offerors propose reasonable annual price increases for each of the four option years, or does the Government prefer consistent annual pricing?

Answer: Offerors make their own decision on price proposals.

18. Can you confirm whether the Service Contract Labor Standards wage and fringe benefit requirements apply to all personnel performing cleaning services, including subcontractor personnel?

Answer: Yes. The Service Contract Labor Standards (SCLS) wage and fringe benefit requirements apply to all service employees performing covered work under the contract, including employees of subcontractors.

19. Does the Government permit janitorial services to be performed through a third-party cleaning platform, provided the assigned personnel meet all security, labor, and performance requirements?

Answer: Yes, the Government permits contractors to use subcontractors or third-party staffing/cleaning platforms to perform janitorial services, provided all contract requirements are met.

20. If additional cleaning services are required beyond the Statement of Work, would those services be addressed through a contract modification?

Answer: No additional cleaning services will be required beyond the statement of work.

21. Should cleaning the seasonal work of the fire station restrooms/showers cleanings be included within the annual contract line-item price or priced separately?

Answer: The seasonal work should be included within the annual contract line-item. The bid schedule has been updated for clarification.

22. The Statement of Work references attached floor plans for Offices 1, 2, and 3; however, the solicitation posting does not include these attachments. Please provide the floor plans for the Caliente Field Office and Fire Station or amend the solicitation to include them.

Answer: The floor plans are now in the attachments listed as Caliente Field Station Building and Caliente Fire Station.

23. Can you please provide photos of the flooring?

Answer:

CFO Break Room

CFO Conference Room

CFO Floors NE

CFO Floors NE2

CFO Floors SE

CFO Lobby

CFO West Hallway

East Passway 1

East Passway 2

File details come from the government source that posted it. Updated .