This is Amendment 0003 to Solicitation No. 140L3626R0002 for the Marcott Coulee Pipeline project, issued by the BLM MT-STATE OFC (Billings, Montana) on August 26, 2026, with an effective date of August 4, 2026. The solicitation is not extended. Bids must be submitted to Jorge by September 7th, with all questions due by August 28, 2026 at 1:00 PM. The period of performance runs from September 25, 2026 to April 15, 2028 (568 days), which accommodates a 9-month lead time for tank procurement and wildlife compliance requirements. Acknowledgment of this amendment must be received prior to bid opening through completion of items 8 and 15 on the form, by acknowledging receipt on each offer copy, or by separate letter/electronic communication referencing the solicitation and amendment numbers.

The amendment provides site visit attendee information, contractor pre-bid meeting notes, and answers to four previous questions regarding BABA/AIS requirements, tracer wire installation, curb box stationary rods, and curb box keys. Key technical specifications added include: flow restrictors of 2-inch diameter rated at 3 gallons per minute at each remote tap; wildlife escape ramps manufactured by Montana Fiberglass at each tank; construction work permitted only between July 15 and November 30, with all activities suspended March 15 through July 15; equipment pressure washing requirement prior to site entry; prohibition on soil ruts deeper than 3 inches; construction stakes set by the government with 25-foot deviation allowance; and water bar spacing based on slope percentage (200 feet for 2-4% slope, 100 feet for 5-9%, 50 feet for 10-25%, and 25 feet for slopes exceeding 25%). The government contact is John Hunter (jlhunter@blm.gov, 406-538-1935).

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: is not is required copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7.ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

PAGESOF

Contractor

The hour and date specified for receipt of Offers to sign this document and return

Jorge Alvarez

See continuation page

BLM MT-STATE OFC(MT935)

5001 SOUTHGATE DR.

BILLINGS MT 59101

BLM MT STATE OFC(MT935)

5001 SOUTHGATE DR.

BILLINGS MT 59101

LMA

LMA

140L3626R0002

08/26/2026

08/04/2026

1 7

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

NSN 7540-01-152-8067

140L3626R0002/0003

See amendment information below.

Period of Performance: 09/25/2026 to

04/15/2028

PROJECT DESCRIPTION: Marcott Coulee Pipeline Solicitation No. 140L3626R0002

Description of Changes - This amendment incorporates the following information:

1. The Government is providing the site visit attendee list, Questions received from interested offerors and the associated Answers provided by the Government, Wildlife Protection Stipulations, and additional conditions.

Acknowledgement - See Block 11 above regarding how to acknowledge this amendment. The Government must receive the acknowledgement at the place designated for receipt of offers (See Block 8 of the Standard Form 1442).

Third Party – If you have given a copy of the solicitation to someone else, please forward this amendment accordingly.

Attendee List for the Marcott Coulee Pipeline pre bid meeting

Comments Offered by John Hunter

Met at the Roy Post office at 10:00 AM

10:05 AM went over some specific issues associated with the solicitation

Comments on Pre-Bid Meeting and Solicitation Issues

• Meeting Logistics: The pre-bid meeting began at the Roy Post Office at 10:00 AM. This ensured all attendees were assembled before the discussion started.

• Solicitation Review: At 10:05 AM, specific issues regarding the solicitation were addressed, giving contractors clarity on project requirements and expectations.

• Period of Performance: The project allows for a 568-day period of performance. This extended timeline is due to a 9-month lead time for tank procurement from local vendors, as well as the need to comply with wildlife stipulations.

WYDAK ENERGY Chad Klaahsen 307-217-1391 bids@wyyodakenergy.com Youderian Const. Tyler Youderian 406-490-7708 Tyler@youderianconst.com Two Rivers Const Dave Jameson 406-366-1852 Dave.jameson80@gmwj CW Kananen Backhoe

CW Kananen 406-366-1852 cwkananen@yahoo.com

Kananen Excavation

Chad Kananen 406-380-0863 chadkananen@yahoo.com

RF Const. Faron Henderson 406-202-3368 faronhenderson@live.com Bishop Inc Ryan Schaner 406-344-2059 ryan@bishopincmt.com Lewistown FO Manager

Brett Blumhardt 406-538-1918 bblumhardt@blm.gov

Tech point of Contact and COR

John Hunter 406-538-1935 jlhunter@blm.gov

• Bid Submission Process: Bids must be submitted to Jorge by September 7th. Contractors are advised to call or email Jorge before 1:00 PM to confirm receipt and completeness of their bids.

• Questions Deadline: All questions should be sent to Jorge before 1:00 PM on August 28, 2026, to ensure timely responses and avoid last-minute confusion.

• Estimated Quantities: Some contract quantities are estimates and will be measured in the field for payment. Contractors should be aware of this when preparing their bids.

• Wage Requirements: The Davis Bacon wage requirement was discussed, including where to find the prevailing wage rates applicable to this project.

• Contract Clauses: Key clauses such as disputes and differing site conditions were reviewed to clarify procedures for handling unexpected issues.

• Utility Marking and Access Restrictions: Contractors must call before digging to have utilities marked.

• No new roads can be built for site access, and entry onto private or State of Montana land requires permission.

• Section M Importance: Section M of the contract is critical. Contractors must follow instructions precisely, especially regarding best value evaluation and the two main criteria used in this contract.

• Construction Stakes: The government will set construction stakes. Contractors may deviate up to 25 feet on either side without approval; deviations beyond that require government authorization.

• Pipe Joints and Pressure Testing: Pipe joints must remain open until the government accepts the pressure test, ensuring compliance and safety.

• Pipeline Alignment: Contractors must not enter or cross private or state land without permission.

• Site Visit: Most of the pipeline alignment was visited, except for the Whiskers Coulee crossing and the WT-7 tank location.

• Specific Contractor Questions: Several contractor questions were addressed, including permitted work periods, bedding materials, construction practices, drainpipe placement, and mowing the alignment. Responses emphasized following current specifications unless an addendum is issued.

Additional Flow Restrictor Installation Specification: At each remote tap, the contractor shall install one flow restrictor, each with a diameter of 2 inches and a rated flow of 3 gallons per minute (gpm).

Acceptable products include Dole or equivalent approved alternatives. The purpose of these restrictors is to maintain uniform water flow and prevent excessive usage at individual tap locations. All installations must comply with manufacturer instructions and project requirements.

To address contractor questions about permitted work periods, a revised clause is proposed for inclusion in the addendum, replacing the existing contract clause.

Work on this project is permitted between July 15th and November 30 during any calendar year to accommodate wildlife concerns. See wildlife Protection Stipulations below.

Wildlife Protection Stipulations 01009 page 5 section b.1: Permitted work period (Revised): OMITT CLAUSE No. B1 from section 1.08 section 01009, and change to: To comply with wildlife requirements outlined in the environmental analysis, all construction activities must be suspended from March 15 through July 15 each year. This pause ensures minimal disturbance to wildlife during sensitive periods.

The BLM resource folks requested that the following conditions be added to the addendum

Soil and Equipment Use Construction and maintenance work must not be performed when soil conditions are inadequate to support equipment and vehicles. If soil ruts deeper than 3 inches are observed, all construction activities must stop until the ground conditions improve to meet this standard.

Equipment Cleaning and Weed Prevention All equipment brought onto the project site must be pressure washed prior to entry. This measure is required to prevent the transfer of weed seeds from other locations, protecting the project area from invasive plant species.

Wildlife Escape Ramps Install wildlife escape ramps at each tank. These ramps must be manufactured by Montana Fiberglass or an equivalent supplier. Submit product details for approval prior to procurement and installation to ensure compliance with project standards.

Construction Specification: Water Bar Spacing The chart on Sheet 12 of 14 will be superseded to include the following chart, which specifies the required intervals between water bars based on the slope percentage.

Slope %* Water Bar Interval (feet)

2–4 200

5–9 100

10–25 50

25+ 25

*Slope percentages refer to the grade along the pipeline alignment where water bars are required.

Intervals must be measured along the slope, and water bars installed at the specified spacing to ensure compliance with erosion control measures.

Construction Specification: Pipeline Access and Travel Travel along the pipeline alignment shall be limited strictly to construction activities. Whenever feasible, construction crews should utilize existing dirt roads or two-track roads for accessing the pipeline alignment, in order to minimize disturbance to the surrounding area.

Previous Questions and Answers

1. Domestic Sourcing Requirements: Could you please confirm if this project falls under the Build America, Buy America (BABA) Act requirements or American Iron and Steel (AIS) provisions?

Yes, see FAR 52.225-9 and FAR 52.225-10.

2. Tracer Wire / Marking: Do the 2-inch HDPE water lines require tracer wire or detectable/warning tape above the pipe in the trench?

For the Marcott Coulee Pipeline project, tracer wire is not required on any of the 2-inch HDPE water lines. Contractors are not obligated to install tracer wire or detectable/warning tape above the pipe in the trench. All installation practices should follow standard procedures, but the inclusion of tracer wire or tape is not necessary for this scope of work.

3. Curb Boxes / Stationary Rods: In the specifications and drawing details, some 1" and 2" curb boxes depict/call for a stationary rod inside, while others do not. Please clarify whether all curb boxes require internal stationary rods or only specific locations.

For all curb boxes installed as part of the Marcott Coulee Pipeline project, any curb box with a depth greater than 24 inches must be equipped with a stationary rod. The stationary rod shall be sized and positioned so that the operator interface is brought to within 24 inches of the top of the curb box, ensuring ease of access for maintenance and operation. This requirement applies to both 1-inch and 2-inch curb boxes as indicated in the project specifications and drawing details. The stationary rod must be securely installed and compatible with the curb box key provisions specified for the project.

4. Curb Box Keys: Are the requested curb box keys intended solely for the top pentagon nut, or should they operate both the top pentagon nut and the stationary rods? If certain curb boxes do not require internal stationary rods, are contractors required to supply additional curb valve keys designed to directly operate the curb valves without stationary rods?

All curb box keys provided for the Marcott Coulee Pipeline project shall be constructed with dual functionality: each key must include a pentagon nut wrench for opening the top of the curb box, and a long end specifically designed to securely engage the top of the stationary rod. The pentagon nut wrench must be compatible with the standard pentagon nuts specified for the curb boxes, ensuring reliable access and operation. The long end of the key should be of sufficient length and strength to interface with stationary rods installed in curb boxes deeper than 24 inches, as required by project specifications. Keys must be fabricated from durable materials capable of withstanding routine field use and environmental conditions. All keys shall be tested for proper fit and function prior to delivery and installation.

Amendment of solicitation/modification of contract
Contract ID code
Amendment/modification number
Effective date
Requisition/purchase requisition number
Project number
Issued by
Code
Administered by
Code
Name and address of contractor
Code
Facility code
Amendment of solicitation number
Dated
Modification of contract/order number
Dated
This item only applies to amendments of solicitations
Accounting and appropriation data
This item applies only to modifications of contracts/orders.
This change order is issued pursuant to:
The above numbered contract/order is modified to reflect the administrative changes
This supplemental agreement is entered into pursuant to authority of:
Other
Important:
Description of amendment/modification
Name and title of signer
Contractor/offeror
Date signed
Name and title of contracting officer
Signature of Contracting Officer
Date signed
Previous edition unusable
Standard form 30 (rev. 11/2016)
Continuation sheet
Reference Number
Name of Offeror or Contractor
OPTIONAL FORM 336 (4-86))

Sponsored by GSA FAR (48 CFR) 53.110

File details come from the government source that posted it. Updated .