This is Amendment 0002 to solicitation 140L3625Q0002 for the Great American Outdoors Act (GAOA) Pompeys Pillar Vault Toilet Replacement project in Montana, issued by the Bureau of Land Management. The amendment provides answers to two additional questions from interested offerors regarding power cable relocation and project completion timing.
The amendment clarifies that the awarded contractor must coordinate with Yellowstone Valley Electric Coop for relocating the power line running under the new vault toilet location. It also confirms that while Standard Form 1442 states 213 days for completion after notice to proceed, the final completion date is November 21, 2025, which includes final cleanup. The quotation due date remains 3:00 PM Mountain Time on March 10, 2025. The amendment includes acknowledgment instructions and notes that third parties who received the solicitation should be forwarded this amendment.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140L3625Q0002 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR
OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
LMALMA
BILLINGS MT 59101
5001 SOUTHGATE DR
BLM MT-STATE OFCMT935
03/04/20250002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)
Bureau of Land Management Attn: Christine Mundt (cmundt@blm.gov) 5001 Southgate Drive Billings, MT 59101
CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
02/06/2025
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Project Title: Great American Outdoors Act (GAOA) - Pompeys Pillar Vault Toilet
Replacement, Montana
See Page 2 of 4 for changes incorporated by this amendment.
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Christine Mundt
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
Solicitation No: 140L3625Q0002 PROJECT DESCRIPTION: GAOA - Pompeys Pillar Vault Toilet Replacement
Amendment No. 0002
Description of Changes - This amendment incorporates the following information:
1. The Government is providing the attached additional Questions received from interested offerors and the associated Answers provided by the Government.
Acknowledgement - See Block 11 above regarding how to acknowledge this amendment. The Government must receive the acknowledgement at the place designated for receipt of offers (See Block 8 of the Standard Form 1442).
Proposal Response Date - The hour and date for receipt of quotations remains 3:00 pm Mountain Time on Monday, March 10, 2025.
Third Party – If you have given a copy of the solicitation to someone else, please forward this amendment accordingly.
QUESTIONS AND ANSWERS
Amendment Number 0002 serves as BLM’s second response to the additional questions received from interested offerors.
Q13: With regards to the power cable running under the new vault toilet, can the government provide any information about the cable such as where it runs to and from and the size of the cable?
A13: Gary Saling at Yellowstone Valley Electric Coop is familiar with the scope of work for relocating the power line. The awarded contractor will be responsible for coordinating with Yellowstone Valley Electric Coop (406-384-4021) to ensure the relocation is handled properly. They will cut, splice, and relocate the line prior to construction to ensure it is not damaged or impacted during our project.
Q14: On Standard Form 1442 it states that the project must be completed within 213 days after the notice to proceed, but in Section F it states that the completion date is November 21, 2025. Please clarify the intention for the completion of work.
A14: The contractor shall complete the entire work ready for use not later than November 21, 2025. The time stated for completion shall include final cleanup of the premises.