This is a Questions and Answers (Q&A) document from a federal contract solicitation dated October 22, 2026, identified as Q&A140L1726R0001.

The document addresses three contractor inquiries regarding asbestos abatement work specifications. Question 1 asks whether contractors may use an existing asbestos report to prepare preliminary pricing estimates, assuming roof sealant is friable, or if a new survey is required before pricing; the answer directs contractors to Specifications section 02 82 10, paragraph 3.1. Question 2 inquires whether an updated survey is mandatory before obtaining the applicable Colorado asbestos abatement permit and commencing work; the same specification section and paragraph are referenced. Question 3 addresses the handling of cost or scope changes if additional testing reveals changes in material condition or identifies additional asbestos-containing materials; the answer references Specifications section 02 82 10, paragraph 1.2. The Q&A provides clarification on survey requirements and change order procedures related to asbestos abatement activities but does not contain information regarding pricing terms, response deadlines, or award dates.

View the file

Other files

Show all 24

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. Can the contractor use the existing report to prepare a preliminary estimate, assuming the roof sealant is friable, or must a new asbestos survey be completed before pricing?

a. See Specifications section 02 82 10, paragraph 3.1.

2. Is an updated survey required before obtaining the applicable Colorado asbestos abatement permit and beginning work?

a. See Specifications section 02 82 10, paragraph 3.1.

3. If additional testing identifies changes in the material’s condition or additional asbestos-containing materials, how should the resulting cost or scope changes be handled?

a. See Specifications section 02 82 10, paragraph 1.2.