B09_Attach_1_Statement_of_Work_20250429_AMENDED_0001.pdf
PDF 400 KB Posted
- Attached to
- GAOA BISHOP CAMPGROUND WATERLINE REPAIRS Federal contract opportunity
- Solicitation number
- 140L1225Q0010
About this file
This Statement of Work (SOW) details plumbing modifications for water systems at three Bureau of Land Management (BLM) campgrounds in California: Tuttle Creek, Horton Creek, and Crowley Lake, funded through the Great American Outdoor Act (GAOA). The project involves upgrading existing water infrastructure to address regulatory deficiencies and improve system reliability, with specific tasks including:
Key modifications include installing approximately 580-840 linear feet of 4-inch buried tank drain lines, adding tank outflow meters, implementing distribution system isolation valves, and replacing existing backflow prevention devices. The work will be completed between June 1 and September 30, with strict requirements for pipe installation, materials (meeting ANSI/NSF Standard 61 and AWWA standards), and water quality compliance. The contractor must maintain campground access during construction, provide proper erosion control, follow fire prevention protocols, and submit comprehensive documentation including site photographs and as-built drawings. A one-year warranty is required for all materials and workmanship.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B09_Prebid_Site_Visit_Questions_and_Answers_0001.pdf | ||
| Sol_140L1225Q0010_Amd_0001.pdf | ||
| Sol_140L1225Q0010.pdf | ||
| B08_Attachment_No__2_WD.pdf | ||
| B08_Attach_1_Statement_of_Work_20250402.pdf | ||
| B08_Attachment_No__3_Bid_Schedule.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work (SOW) Bishop Campgrounds’ Water Systems
SOW Page 1
PROJECT TITLE:
Bureau of Land Management (BLM)
Bishop Campgrounds Great American Outdoor Act (GAOA) Plumbing Modifications
Table of Contents SOW 1.0 Background on the Government’s Requirement
SOW 2.0 General Scope of Work
SOW 3.0 Overall Objectives
SOW 4.0 Specific Tasks
SOW 5.0 Delivery / Performance Schedule
SOW 6.0 Government-Furnished Property, Materials, Services
SOW 7.0 Security and Administrative Matters
SOW 8.0 Technical Definitions
SOW 9.0 Construction Drawings
SOW 10.0 Site Photos
SOW 11.0 General Requirements
SOW 12.0 As-Builts
SOW Page 2
SOW 1.0 Background on the Government’s Requirement
The Bureau of Land Management (BLM) Bishop Field Office manages drinking water systems at three campgrounds—Tuttle Creek, Horton Creek, and Crowley Lake. These systems require modernization to address regulatory deficiencies, improve reliability, and ensure consistently safe drinking water for public use.
Each water system is supplied by a dedicated groundwater well powered by a solar array.
During the day, these wells feed above-ground storage tanks that distribute water through gravity-fed PVC piping. The distribution networks extend throughout the campgrounds, providing water via multiple spigots and irrigation points.
Currently, these drinking water systems experience recurring maintenance challenges due to missing isolation valves and exposed drain lines. The primary issues include:
Exposed and Fragile Drain Lines: Existing tank drain lines are laid across the ground and constructed with small-diameter piping, making them prone to frequent breaks and leaks. The restricted pipe diameter also slows tank drainage, requiring excessive staff time for maintenance.
Lack of Isolation Valves: Each distribution system has only a single shutoff valve at the tank, preventing individual sections from being isolated for repairs.
Any maintenance requires shutting down the entire system.
Absence of Water Meters: Water meters are necessary to track usage and comply with regulatory reporting requirements, but none are currently installed.
To address these issues, the project will implement key upgrades, including burying and replacing tank drain lines, installing isolation valves, and integrating water meters at each campground. These improvements will enhance system reliability, reduce maintenance costs, and ensure compliance with the Safe Drinking Water Act (Title 40 CFR 141) and California’s Title 22 Drinking Water Standards.
SOW 2.0 General Scope of Work
The general scope of work is to address regulatory deficiencies, improve reliability, and ensure consistently safe drinking water for public use. The contractor’s proposal must include detailed specification sheets for all proposed replacement equipment to demonstrate:
Compatibility with existing equipment Compliance with Title 40 CFR 141 Safe Drinking Water Act and California’s
Title 22 Drinking Water Standards
1. Tank Drain Modifications
SOW Page 3
The contractor shall provide and install a total of approximately 580840 linear feet of 4-inch buried tank drain lines across the three campgrounds. Replace the drain line from the tank to the outlet. The new installation shall include a shutoff valve, tee, and cap located at the tank pad. The outlet shall be equipped with a screened air gap fitting sized to provide a vertical separation of at least two times the pipe diameter. Appropriate erosion control measures shall be installed below the outfall to prevent soil displacement.
Installing cover/buried drain lines will:
Improve system efficiency Reduce staff time required for startups and shutdowns Enhance overall water system performance
Refer to Section 4.0 of the Statement of Work (SOW) and Section 11 for specific drain line lengths and additional campground details.
2. Distribution Piping Modifications
The contractor shall provide and install the following distribution system modifications at all three campgrounds:
Tank Outflow Meters: Three 2-inch meters, each housed in a valve box, with a total of six isolation valves
Isolation Valves: Seven additional isolation valves, each in a valve box, to allow for sectional shutdowns and pressure zone isolation
Backflow Prevention: Replacement of one existing backflow device with a reduced-pressure backflow prevention device to ensure compliance with applicable plumbing codes at Tuttle Creek Campground
BLM staff will identify and mark the pipe locations for valve installation and will either leave the area uncovered or include a note indicating the pipe depth after reburial.
These modifications will enable targeted repairs, improve water use tracking, and enhance system efficiency while meeting regulatory and plumbing code requirements.
For additional details on specific tasks at each campground, refer to Section 4.0, Section 11, and Section 9 of this Statement of Work (SOW).
Construction will take place while the campgrounds remain open to the public. The contractor is responsible for maintaining a secure worksite and ensuring that at least one lane of traffic remains open around or through all work zones to allow safe public access.
Additional construction may be occurring at the wellheads and storage tanks during this project. The contractor is responsible for coordinating with other ongoing work to prevent delays to either contract. A construction schedule for the additional work will be provided upon award to assist in sequencing tasks accordingly.
SOW Page 4
PLACE OF PERFORMANCE:
The project sites are all located within Mono and Inyo counties in California and are accessible from U.S. Highway 395. Vehicles with four-wheel drive are recommended to access the well heads and tanks at all project sites.
Tuttle Creek Campground is located 3.5 miles West of Lone Pine, California.
Horton Creek is located 8.5 miles north of Bishop, California.
Crowley Lake is located 2 miles west of Crowley Lake Community, California.
See attached maps in Section 10 for the general location of each campground.
PROJECT SITE LOCATIONS:
Tuttle Creek Campground (36.565°, -118.127°) Directions from Highway 395, drive 3.5 miles west of Lone Pine on Whitney Portal Road, then 1.5 miles south on Horseshow Meadow Road, follow signs to the campground.
Horton Creek Campground (37.375995°, -118.578610°) Travel 8.5 miles north on U.S. Highway 395 from Bishop to Sawmill Road and turn left, take an immediate right onto South Round Valley Road and travel 3 miles, campground is on the left.
Crowley Lake Campground (37.569°, -118.768°) Follow US Highway 395 north from Bishop to Crowley Lake exit.
Proceed west through the Crowley Lake Community for 2 miles. Turn north (right) at Crowley Lake Drive and proceed for 2 miles. Follow sign to the campground.
PERIOD OF PERFORMANCE:
The Period of Performance for this work is expected to be June 1 through September 30th.
Contract work including the pre-work conference meeting, site visits and planning meetings, mobilization, construction, and de-mobilization must be completed within the authorized Period of Performance.
Off-site contract work including the pre-work conference meeting, site visits, planning meetings, and material ordering shall be completed after the Notice to Proceed and before the end of the Period of Performance
On-site work will be prohibited during the following holidays, holiday weekends, and specific time periods:
o June 19 o July 4 o September 2 o October 1 through April 30 o Whenever site conditions are below 40˚F ambient air temperature.
SOW Page 5
SOW 3.0 Overall Objectives
The purpose of this contract is to complete the following tasks at the Tuttle Creek, Horton Creek, and Crowley Lake BLM campgrounds:
Tasks 1, 3, & 5: Furnish and install covered/buried tank drain lines at each project site, as outlined in SOW 4.0, Section 11, and Section 9.
o Objective: Install drain lines either below-grade or fill to establish a stable berm (or embankment) over the pipeline for protection, load distribution, and surface drain lines tostabilization to protect the pipes from damage and improve drainage efficiency.
Tasks 2, 4, & 6: Furnish and install distribution system modifications at all three campgrounds, including meters, isolation valves, and one reduced-pressure backflow device, as outlined in SOW 4.0 Specific Tasks.
o Objective: Correct valve deficiencies, enable water use tracking for reporting compliance, and allow for isolation of distribution system segments in the event of breaks.
SOW 4.0 Specific Tasks
Notification Requirements:
The Contractor shall post public notices at each campground’s entrance kiosks and dump stations at least two weeks before construction begins, stating that no water will be available for the duration of the project. The notice shall include:
The proposed start date and estimated completion date:
A statement advising visitors to bring their own water Contact information for the Contractor or designated BLM representative for questions Any alternative water sources, if applicable
The notices shall be durable and weather-resistant to remain legible for the full duration of construction. If the construction schedule changes, the Contractor shall update and repost the notices promptly.
Additionally, the Contractor shall notify the Contracting Officer’s Representative (COR) in writing at least two weeks before starting work at each campground.
General Requirements:
Base requirements for the respective water system features are provided in Section 11: General Requirements and proposed drawings and specifications in Section 9 Construction Drawings.
Site-Specific Tasks
SOW Page 6
Tuttle Creek Campground Task 1: Tank Drain Modifications
The Contractor shall furnish and install approximately 580350 linear feet of drain line either buried or fill to establish a stable berm (or embankment) over the pipeline for protection, load distribution, and surface tank drain line in accordance with Section 9 and 11 of this SOW.
The Contractor shall replace the drain line from the tank to the outlet distance specified above. The new installation shall include a shutoff valve, tee, and cap located at the tank pad in accordance the specifications in Sections 9 and 11 of this SOW.
The tank drain system outfall shall be supported, screened outlet, air gap, and appropriate erosion control measures shall be installed below the outfall to prevent soil displacement.. The direction the outfall is facing shall be located installed at a location to ensure that no campsites are subject to flooding during operation.
There are two spots where the drain line crosses under roadways. These spots shall have sufficient cover to protect the pipe from vehicle traffic.
Up to two low points may occur along the drain line. Each low point must include an isolation valve, screened outlet, air gap, and erosion control measures at the outfall.
All existing tank drain line shall be secured at the site for BLM to pickup.
Task 2: Distribution System Modifications
The Contractor shall modify the existing tank outflow by furnishing and installing a new tank meter and two isolation valves to facilitate future meter replacement.
The installation shall be housed in a below-grade valve meter box on the tank outlet line.
The Contractor shall remove and replace the existing vacuum breaker valve (Serial #T209290) located at 36°33.823’ N, -118°7.859’ W with a reduced-pressure double check valve, as indicated in Section 10: Campground Facility Locations and Section 9: Construction Drawings.
The Contractor shall furnish and install three ball isolation valves at the locations specified in Section 9: Construction Drawings. The valve locations shall all be marked by a cone. BLM staff will locate the water pipe and either have it uncovered at the point for the valve installation or a note detailing the depth the pipe at that location.
All work shall be performed in accordance with the requirements set forth in Section 9 and 11 of this SOW.
Upon completion of work, the Contractor shall conduct a pressure and leak test in compliance with the specifications in Section 11 to confirm that any leaks do not exceed the allowable limits established by AWWA C600.
SOW Page 7
Horton Creek Campground Task 3: Tank Drain Modifications
The Contractor shall furnish and install approximately 220180 linear feet of drain line either buried or fill to establish a stable berm (or embankment) over the pipeline for protection, load distribution, and surface buried tank drain line, meeting the specifications outlined in Section 9 and 11 of this SOW.
The Contractor shall replace the drain line from the tank to the outlet distance specified above. The new installation shall include a shutoff valve, tee, and cap located at the tank pad in accordance the specifications in Sections 9 and 11 of this SOW.
The tank drain system outfall shall be supported, screened outlet, air gap, and appropriate erosion control measures shall be installed below the outfall to prevent soil displacement. The direction the outfall is facing shall be located installed at a location to ensure that no campsites are subject to flooding during operation.
All existing tank drain line shall be secured at the site for BLM to pickup.
Task 4: Distribution System Modifications
The Contractor shall modify the existing tank outflow by furnishing and installing a new tank meter and two isolation valves to facilitate future meter replacement.
The installation shall be housed in a below-grade valve meter box on the tank outlet line.
The Contractor shall furnish and install two ball isolation valves at the locations specified in Section 9: Construction Drawings. The valve locations shall all be marked by a cone. BLM staff will locate the water pipe and either have it uncovered at the point for the valve installation or a note detailing the depth the pipe at that location.
All work shall be performed in accordance with the requirements set forth in Sections 9 and 11 of this SOW.
Upon completion of work, the Contractor shall conduct a pressure and leak test in compliance with the specifications in Section 11 to verify that any leaks do not exceed the allowable limits established by AWWA C600.
Crowley Lake Campground Task 5: Tank Drain Modifications
The Contractor shall furnish and install approximately 540 linear feet of drain line either buried or fill to establish a stable berm (or embankment) over the pipeline for protection, load distribution, and surface buried tank drain line in accordance with the specifications in Sections 9 and 11 of this SOW.
The Contractor shall replace the drain line from the tank to the outlet distance specified above. The new installation shall include a shutoff valve, tee, and cap located at the tank pad in accordance the specifications in Sections 9 and 11 of this SOW.
SOW Page 8
The tank drain system outfall shall be installed supported, screened outlet, air gap, and appropriate erosion control measures shall be installed below the outfall to prevent soil displacement.. The direction the outfall is facing shall be located at a location to ensure that the existing adjacent road is not errored orno campsites are subject to flooding during drain operation.
All existing tank drain line shall be disconnect and secured at the site for BLM to pickup.
Task 6: Distribution System Modifications
The Contractor shall modify the existing tank outflow by furnishing and installing a new tank meter and two isolation valves to facilitate future meter replacement.
The installation shall be housed in a below-grade valve meter box on the tank outlet line.
The Contractor shall furnish and install two ball isolation valves at the locations specified in Section 9: Construction Drawings. The valve locations shall all be marked by a cone. BLM staff will locate the water pipe and either have it uncovered at the point for the valve installation or a note detailing the depth the pipe at that location.
All work shall be performed in accordance with the requirements set forth in Sections 9 and 11 of this SOW.
Upon completion of work, the Contractor shall conduct a pressure and leak test in compliance with the specifications in Section 11 to verify that any leaks do not exceed the allowable limits established by AWWA C600.
SOW 5.0 Delivery / Performance Schedule
Standards
Moving of Equipment and Supplies: The moving of equipment and supplies to the job site and between job sites shall be the responsibility of the Contractor. Care should be taken during high fire season to prevent any sparks.
Replacement of Equipment: Contractor shall provide quality equipment capable of safely performing the work under the terms of the contract. If equipment is rejected because it does not meet minimum requirements, including but not limited to safety and operability, or if it becomes inoperative, the Contractor shall correct the deficiencies or furnish replacement equipment meeting contract requirements within 2 calendar days. All repairs are the total responsibility of the Contractor.
Equipment Standards: Contractor shall make equipment available for inspection and approval before use. The Contractor must satisfy all applicable OSHA and DOT requirements or certifications for the operation of offered equipment. There will be no obligation to make payment for any equipment delivered that does not meet the Technical Specifications.
SOW Page 9
Existing Facilities: All existing facilities such as piping, signs, cattle guards, drainage structures and road surfacing damaged by the Contractor's operations shall be replaced or repaired by the Contractor at no cost to the Government.
Watershed Protection and Erosion Control: During all operations under this contract, the Contractor shall exercise reasonable measures to direct surface runoff water to stabilized waterways and to keep the drainage systems functioning effectively to prevent or minimize soil erosion and pollution of water and other resources. All refuse, including garbage, rubbish, and equipment maintenance areas shall be stored and collected in a sanitary manner and disposed of in a State-approved sanitary landfill, per local, State, and Federal regulations.
Oil from crankcases or gear boxes, equipment waste or spilled or excess fuel shall be placed in containers and removed from the work site and disposed of as approved and required by local, State, and Federal regulations.
Contractor shall undertake every reasonable measure to minimize erosion and soil damage in connection with any operations under this contract.
Contractor shall immediately discontinue any operations under this contract that due to weather or soil moisture conditions, such operations will cause excessive damage to the soil as determined by the Contracting Officer.
Equipment shall not be fueled nor fluids changed within 100 feet of waters of the state. Any equipment operated adjacent to state waters shall be maintained in a good state of repair and have no damaged hoses, fittings, lines, tanks, etc. that may release pollutants into the water. Waste oil and fluids shall not be stored on site. If any such material is released into the waters, the responsible person must make an effort to contain the spill and notify the Contracting Officer within 24 hours. If unable to contain spill, immediately notify the Contracting Officer and call the National Response Center (NRC) at 1-800-424-8802.
Emergency Spill Kit: Keep sufficient quantities of absorbent materials on the project site to absorb accidental fuel, hydraulic oil, or other petroleum produce spills. Use absorbent materials that are biodegradable, non-water absorbing and designed specifically for the types of spills associated with the Contractor’s operations.
Project site construction not completed during dry weather periods shall be winterized (along with Contractor’s approved onsite staging areas and storage sites) to minimize erosion and other damage to roadways, trails, watercourses, and sensitive habitat, as directed by the Contracting Officer.
Disposal of Debris: The Contractor shall transport and dispose of all debris and excess material off-site at an approved facility, per local, State, and
SOW Page 10
Federal regulations.
All debris, including food trash, that remains onsite must be stored in a secure manner that is not accessible to wildlife, to avoid attracting bears or ravens.
Any debris left onsite after the completion of the Contract shall become the property of the Contractor, and the Contractor shall be responsible for it.
Dispose of materials in a legal manner and payment of fees required is the Contractor's responsibility. Sale of material onsite is not allowed unless authorized in writing by the Contracting Officer. Burning of removed materials is not permitted on the work site.
Project Boundary: Prior to implementation of Contract deliverables, a pre-work meeting will be held at the project sites with the Contractor, Contracting Officer Representative (COR), and/or Project Inspector (PI).
The intent is to ensure the Contractor understands where the project sites are located, project site specifics and specifications of the contract, and review the Contractor’s plan of operations. It is encouraged that all potential Contractors complete a thorough site visit before bidding on the contract.
Access: Access to the project area is identified on the map. If roads or any type of access become subject to damage, because of adverse weather conditions or other natural causes, the Contracting Officer or COR will relay that information to the Contractor by phone, email, or in person and the contract could be delayed.
Notification of Cessation or Restart of work: The Contractor shall notify the Contracting Officer prior to ceasing operations for three or more days, and before re-starting operations after a shutdown of three or more days.
This can be done by phone, E- mail, or in person.
Protection of Cultural Resources: If objects of cultural value on the project area are discovered, the Contractor shall immediately suspend all operations in the vicinity of the cultural value and notify the Authorized Office of the findings.
Weed Prevention: To reduce the potential for introduction of noxious weeds to the contract area, the Contractor shall, prior to moving in motorized equipment to be used for construction, clean all such equipment to remove all dirt, plant parts and materials that may carry noxious weed seeds. All equipment, boots, vehicles, etc. must be clean of weeds and remain free of noxious weeds. All equipment is subject to inspection by the Contracting Officer.
Fire Prevention: Contractor shall take necessary measures for prevention
SOW Page 11 and suppression of fire on the contract area and other adjacent Government lands used or traversed by the Contractor in connection with operations as are required by applicable laws and regulations. Contractor shall comply with all applicable local, State, and Federal fire prevention regulations and standards. At all times during, each unit of powered equipment used in connection with this contract, including automobiles, trucks, tractors, etc., shall be equipped with serviceable tools and fire extinguishers as follows:
Fire extinguisher, dry chemical type of not less than 2-1/2 pound capacity with a 4 BC or higher rating or larger with an overall length of not less than 28 inches
Shovel, round point #0 lady or equal with an overall length of not less than 46 inches
Axe, 2 pounds or over, 26-inch minimum length, or one Pulaski
Contractor shall equip each internal combustion yarder, fuel truck, and loader with a fire extinguisher for oil and grease fires (4-A:60-B:C).
The Contractor shall comply with the following requirements during the fire precautionary period as defined by unit administering contracts unless waived in writing:
The Fire Precautionary Period is May 1st to November 15.
Contractor shall equip each operating tractor and any other internal combustion engine with a spark arrester, except for motor vehicles equipped with a maintained muffler as defined in C.P.R.C. Section 4442 or tractors with exhaust-operated turbochargers. Spark Arresters shall be a model tested and approved under Forest Service Standard 5100-1a as shown in the. National Wildlife Coordinating Group Spark Arrester Guide, Volumes 1 and 2.
REPORTING ALL WILDFIRES
o Contractor's employees shall report all fires as soon as possible but no later than 15 minutes after initial discovery to any of the following BLM facilities and/or personnel listed below, but not necessarily in the order shown:
o When reporting a fire, provide the following information: Your Name, Call back telephone number Project name, Location, Legal description (Township, Range, Section), Descriptive location (Reference point), Fire Information, Acres, Rate of Spread and Wind Condition in good operating condition.
Name
Office Address and/or telephone
Dispatch Center OVICC 760-873-2405
Nearest BLM Station Mono Basin Fire Station 760-647-6740
Inspectors Cheryl Parker, 831-277-6331, SOW Page 12
Jeff Coffman, 279- 977-2081
COR Cheryl Parker 831-277-6331 Field Manager Sherri Lisius 760-872-5022
Delivery
The Contractor shall complete all installations within the period of performance after notice to proceed. Due to permitting requirements for the protection of water quality and sensitive species, all mobilization, construction, and demobilization must occur once the campgrounds are open. When construction work is required within the campground sites, the contractor shall always maintain at least one lane open around the construction site to allow the public to pass.
Within 15 business days of the completion of work, the Contractor shall provide site-specific photographs clearly showing the before and after repair conditions to document compliance with applicable BMPs. The photographs should be clearly labeled with the project site name, date(s), and a description of what was being photographed. The photos shall be submitted to the BLM in a digital format and should be clearly organized and labeled.
Final Inspection and Acceptance
The Contracting Officer’s Representative or designated government representative will review all work. The Government’s final project inspections shall take place 1-3 business days following the Contractor’s written notification to the CO and COR of the completion of work. At the conclusion of the work, the Contracting Officer, or their representative, will inspect all sites for conformance with the specifications and requirements. Any deficiencies noted during the inspection will be corrected by the Contractor prior to release of final payment, at no additional cost to the Government. Prior to final payment the Contractor shall properly disposed of all waste materials including excess soil, completed site resurfacing and grooming of staging and storage areas, and submitted project photographs and project reports.
Work Schedule The schedule shall be submitted at the pre-work conference. When requested by the CO or COR, submit an updated work schedule within 3 calendar days. As a minimum, the estimated start and completion dates shall be shown in the estimate.
SOW 6.0 Government‐Furnished Property, Materials, Services
General: The Contractor shall furnish all personnel, materials, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform the work tasks defined in this Performance Work Statement, except for those items specified as government furnished.
SOW Page 13
Location site maps Site photos Record as-built drawings Existing equipment manufacturer specifications sheets
Facilities: The Government will provide access to the vault toilets nearest the area of work for use by the Contractor.
Applicable Publications (Current Editions):
State and Local Codes. This project will not require local building permits, or approvals, for construction. However, State, and local building codes including the California Residential Code shall be followed to the maximum extent practicable.
Safety and Health. The Contractor must adhere to the applicable requirements in the Occupational Health and Safety Administration (OSHA) regulations for construction (29 CFR 1926) and general industry (29 CFR 1910). Additionally, the Contractor shall abide by applicable State and local safety/health/sanitation/construction codes and standards. In case of conflict, the more stringent shall apply.
Code of Federal Regulations (CFR).
American Society for Testing and Materials (ASTM).
American Concrete Institute (ACI).
American Institute of Steel Construction (AISC).
41 U.S.C. Ch. 83, Section 8303- Buy American Act.
SOW 7.0 Security and Administrative Matters
Security:
The Contractor shall be responsible for safeguarding all Government property provided for Contractor use or under their control, including securing all facilities the Contractor may access after normal business hours.
All materials left on site shall be secured to prevent damage or loss due to high winds at the sites. Any materials damaged or lost due to wind prior to final installation are the responsibility of the Contractor to replace in-kind.
Contractor shall coordinate work schedule with Contracting Officers Representative to minimize public and employee ingress/egress to the building.
Safety:
The Contractor shall not require, or allow any employee, engaged in the performance of this Contract to work under conditions which are unsanitary, hazardous, or dangerous to his/her health or safety, as determined under safety and health standards promulgated by the Secretary of Labor under Section 107 of the Contract Work Hours and Safety Standards Act (40 U.S.C. 327 et seq.) as
SOW Page 14 amended and other Federal, State and applicable local government safety standards.
Department of Labor Code of Federal Regulations Title 29 and other Federal, State and local government safety standards will apply in its entirety to the Contractor.
Examples of applicable safety standards are OSHA 29 CFR 1910, OSHA 29 CFR 1926, California Title 19, "Public Safety", California Title 8, "General Industry Safety Orders", and 41 CFR, Subpart B, "Public Contracts, General Safety and Health Standards."
The contractor shall also use the “BLM SAFETY AND HEALTH STANDARDS” (The Yellow Book) for reference.
Should the contractor fail to comply with any of these standards and regulations, the contractor shall be found to have defaulted on the terms of the contract.
Emergency Response:
Response to emergency service calls outside of the normal business hours shall not exceed four (4) hours regardless of the time during the day or night, weekends or holidays.
Response to emergency service during normal business hours shall not exceed two
(2) hours.
Response is defined as having all personnel and equipment required to correct an emergency at the site of the emergency or at a pre-approved staging area, ready, willing, and able to perform the emergency work. The Contractor will provide a draft emergency response plan prior to Contract start date.
Emergency Services:
On occasion, services may be required to support an activation or exercise of contingency plans outside the normal business hours described above. The Contractor's responsibilities for emergency support will be in accordance with the contingency plan.
Hazardous Materials and Hazardous Response:
The Contractor will conform to all Bureau, Federal, State, and local regulations in the use and disposal of hazardous materials and hazardous waste. The Contractor will provide the appropriate response to any emergency involving hazardous materials at any of the facilities covered by this Contract. The Contractor will provide proof/certification of it's personnel qualified to work with hazardous materials and wastes to the Bureau. The Contractor will notify the Bureau immediately upon discovering a release of hazardous waste into the environment.
Public contact:
Contractor personnel may encounter adjacent landowners or members of the public during the performance of their work.
SOW Page 15
Contractor personnel will present a professional appearance and be able to provide appropriate identification, including display of proper identification by each employee.
All Contractor and subcontractor personnel shall comply with all Federal and State laws relative to citizenship.
Contractor personnel shall inform any trespassers along the right of way of hazards and, as necessary and appropriate, ask trespassers to leave fenced off or restricted areas.
If Contractor personnel may encounter emergency personnel, policemen, or firemen along the right of way, the Contractor personnel shall notify the On-Site Foreman
If Contractor personnel encounter the news media, they should refer all questions to the On-Site Foreman, who shall keep the COR informed of all news media contacts.
Government Observations:
Government personnel other than COR may from time to time observe, photograph, or otherwise record Contract operations.
However, these personnel will not interfere with Contractor performance.
Regular Work Hours:
The performance period established for this contract is based upon all work being conducted during regular working hours between 8:00am and 4:30pm, Monday through Friday, excluding government holidays.
If the Contractor desires to carry on work outside regular hours, including Saturdays, Sundays, and government holidays, a request must be submitted to the COR in sufficient time to allow satisfactory arrangements to be made for access to the work site.
Communications:
“Time” for communications received after 3:00pm, after 12:00 pm locally on Fridays, or after 12:00 pm locally prior to a holiday will not start until the next business day. All times are local Pacific Standard Time.
Federal Holidays:
The following Federal Legal Holidays are observed:
New Year’s Day Martin Luther King, Jr. Day President’s Day Memorial Day Juneteenth Independence Day Labor Day Veterans Day Columbus Day Thanksgiving Day
SOW Page 16
Christmas Day
Fire Danger Season:
If the Contracting Officer Representative (COR) allows the Contractor to continue work during periods of declared fire danger or season, the Contractor shall comply with all applicable state laws relating to fire prevention and with all special conditions of work as directed by the COR.
Drawings:
Typical Drawings: Any drawings titled typical are general only and dimensions of each structure will be fixed by the Contracting Officer to adapt the design to existing conditions at the structure location. Reduced Size Drawings: Any drawings identified as "REDUCED SIZE DRAWINGS" are photographically reduced in size. Accordingly, measurements and dimensions should not be taken or be based on any numerical scales shown. Prospective bidders desiring to review a copy of the full-size drawings may contact the Contracting Officer identified in the solicitation.
Preservation of Historical and Archeological Data:
The Historic and Archeological Data Preservation Act of 1974, provides for the preservation of historical and archeological data that might otherwise be lost as the result of alterations to the terrain caused by a federal or federally licensed activity or program.
If, in connection with operations under this contract, the Contractor, subcontractors, or the employees of any of them, discovers, encounters or becomes aware of any possible historical or archeological data, objects or sites of cultural value on the project area, such as historical ruins, graves or grave markers, fossils, or artifacts, the Contractor shall immediately suspend all operations in the vicinity of the cultural value and shall notify the Contracting Officer in writing, giving the location and nature of the findings. No objects of cultural resource value may be removed.
Where appropriate by reason of discovery, the Contracting Officer may order delays in the time of performance and/or changes in the work. If such delays and/or changes are ordered, the time of performance and contract price shall be adjusted in accordance with the Changes clause.
The Contractor will be responsible for protecting the cultural resources within the affected area from damage. In addition, the contractor will be liable for all damage to the identified cultural resources caused by their actions or the actions of their agents or representatives. The Contractor shall immediately notify the Contracting Officer or his representative if any damage occurs to any cultural resource and immediately suspend work in the area in which damage has occurred until authorized to proceed.
SOW Page 17
SOW 8.0 Technical Definitions
Standard Definitions:
Physical Condition The Physical appearance of Federal equipment or facilities that considers cracks, chips, dents, abrasions, rust, corrosion, general cleanliness, vibration, operating temperature, and discoloration and other items as identified by the COR. Physical condition may be determined by visual as well as diagnostic means.
Contracting Officer (CO) The Secretary of the Interior or designated authorized representative who is the only agent capable of signing a federal award or obligating funds.
Contracting Officer’s Representative (COR) The Contracting Officer’s designated representative as indicated in a delegation of authority letter.
Quality Assurance (QA) Surveillance of Contractor performance to determine performance requirements are met.
Quality Control Those actions taken by the Contractor to control the production of goods or services so that they meet the requirements of the performance work statement.
SOW Page 18
SOW 9.0 Construction Drawings
SOW Page 19
SOW 10.0 Site Locations and Photos
• Tuttle Creek Campground (36.566477°,-118.123671°)
• Horton Creek Campground (37.375995°,-118.578610°)
• Crowley Lake Campground (37.569640°,-118.771691°)
SOW Page 20
SOW 11.0 General Requirements
1. Tank Drain Line
a. Location
i. The Contractor shall install the drain lines at the respective campgrounds within the shaded locations and distances for the final outfall/discharge point as shown in Section 9.
ii. Contractor is responsible for field verification of outfall location that meets all the drain requirements stated within this document.
1. Tuttle Creek Campground drain discharge point is expected to run approximately 350 linear feet southeast of the well head.
2. Horton Creek Campground drain discharge point is expected to run approximately 180 linear feet southeast of the well head.
3. Crowley Lake Campground drain discharge point is expected to run approximately 50 linear feet north of the well head
4. At a minimum, the line shall continue 50-ft beyond the well head to allow for infiltration without affecting the well.
b. Installation
i. Contractor shall disconnect and remove the existing tank drain line at the tanks but maintain the existing tank drain plug valves and existing T-fitting.
ii. The existing T-fitting shall remain in place with the straight end capped to allow for cleaning procedures.
iii. The drain lines shall:
1. Maintain a minimum of a 0.8% draining slope at all times to ensure no low spots,
2. Maintain a minimum of 12-inches of cover/backfill,
3. Have an air gap as described below at the outlet,
4. Drain efficiently within the approved disturbance area, and
5. Avoid flooding any campsites when the drain is in operation.
iv. Drain line low spots:
1. Shall only be allowed at Tuttle Creek Campground with a maximum of two.
2. At each low spot
a. The pipe, valves, and outfall shall be supported.
b. there shall be a valve,
c. The outfall shall be screened and have an air gap height of at least twice the pipe diameter.
5.d.The outfall shall discharge onto large cobble
SOW Page 21 to dispate the energy and reduce erosion, native rock is suitable cobble.
c. Material
i. The drain line shall be of 4-inch schedule 40 PVC or equally suitable piping.
ii. All piping from the tank to the discharge point meeting the air gap must meet ANSI/NSF Standard 61, and applicable sections of AWWA Standards C104-A21.4-08 through C550-05 and C900-07 through C950-07, and California’s Title 22 Drinking Water Standard requirements.
d. Drain outlet.
i. The end of the tank discharge pipe shall be:
1. Straight or down turned,
2. Covered with a large No. 4 screen, and
3. Maintain an Air Gap which shall be a free fall drop from the bottom of the pipe end of a height two times the pipe diameter to the ground. See figure 1 below for details regarding the spacing to meet the air gap requirements.
Figure 1:Air Gap Requirements
2. Distribution
a. The as-built information of the water system the BLM has on file is located in Section 10: Campground Facility Locations. It is strongly recommended that the contractor complete utility pot holing to verify the location and size of the drinking water line as the BLM cannot guarantee the accuracy of the as-builts on file. The general location of all the facilities at each campground is also provided in the drawings of Section 9: NEPA Approved Disturbances Locations for Tank Drain Line and Distribution Modifications & Design Drawings.
3. Valves and Meters
a. Material
SOW Page 22
i. All pipe, fittings and materials that may come in contact with drinking water, shall conform to ANSI/NSF Standard 61, and applicable sections of AWWA Standards C104- A21.4-08 through C550-05 and C900-07 through C950-07, and California’s Title 22 Drinking Water Standard requirements.
ii. All piping above grade will be protected by frost with polyethylene foam pipe insulation wrap or equal.
ii.iii. All valves, joints, elbows on the tank drain lines shall be supported against water hammer.
b. Installation
i. The contractor’s proposal shall incorporate the provisions of the manufacturer's recommended installation procedures and the following applicable standards:
1. For PVC pipe, ASTM D2774, Recommended Practice for Underground Installation of Thermoplastic Pressure Piping and PVC Pipe and AWWA Manual of Practice M23;
2. For HDPE pipe, ASTM D2774, Recommended Practice for Underground Installation of Thermoplastic Pressure Piping and AWWA Manual of Practice M55;
3. Meeting California’s Title 22 Drinking Water Standard requirements.
ii. Meters shall be installed with isolation valves on each end to allow for meter replacements.
iii. Meters shall be placed at the locations as shown in the drawings within this SOW.
iv. All meters shall be in accordance with the California Plumbing Code.
v. The well meter shall be installed in the location shown in the drawings within this SOW to capture all water pumped, including pump to waste.
vi.v. The tank meter shall be installed in the location shown in the drawings within this SOW to minimize freeze damage and capture all future water flows to the campground.
vii.vi. Additional check valves and isolation valves should be installed as shown within the drawings of this SOW needed in accordance with the California Plumbing Code.
c. Well Discharge Piping
i. Contractor shall modify existing well discharge line to furnish and install the following distribution system modifications at all three campgrounds including:
ii. Replacement of well water line from the well to the tank to include:
1. Installation of check valve, well head meter with ball valves on either side, air release valve, and pump to
SOW Page 23 waste line that discharges 42-inch to be beyond the pipe centerline, as shown in Section 11.
2. Pipeline shall be reconnected to the two support columns embedded within the respective well and tank concrete pads.
d.c. Tank Meter
i. Installation of a tank meter with isolation valves on either side within a Polyolefin valve box of sufficient size to contain and allow access to all valves. The valve box shall have walls that extend to the surface with a cover, as shown in Section 9.
e.d. Distribution Isolation Valves
i. Installation of 2-inch isolation valves throughout the distribution system to allow easier repairs. See Section 9 for approved locations of isolation valves.
1. Three isolation valves at Tuttle Creek Campground as shown in Tuttle Creek drawing in Section 9.
2. Two isolation valves at Horton Creek Campground as shown in Horton Creek drawing in Section 9.
3. Two isolation valves at Crowley Campground as shown in Crowley Lake drawing in Section 9.
ii. All isolation valves shall be ball valves shall be below grade and contained within a Polyolefin valve box of sufficient size to contain the valves and allow easy access to the valve.
The valve box shall have a locking lid to maintain access from the surface.
f.e. Pipe Bedding & Backfill
i. Backfill/cover material shall be tamped in layers around the pipe and be sufficient height above the pipe to adequately support and protect the pipe. The backfill/cover material shall have a maximum particle size of ¾-inch to surround the pipe.
g.f. Sealing Pipe Ends During Construction.
i. The open ends of all pipelines under construction shall be covered and effectively sealed at the end of the day.
h.g.Flushing and Leak Test
i. The Contractor shall flush the entire system to all dead ends for the respective campgrounds after all the valves have been replaced meeting California’s Title 22 Drinking Water Standard requirements.
ii. The Contractor shall complete leak and pressure tests to ensure all modifications are secure prior to any backfill following AWWA C600.
1. The tests shall include filling the distribution system to operating pressure and allowed to sit for 2 hours.
2. The well shall be shut off and the system left on lockout to prevent any use.
SOW Page 24
3. After 2 hours the volume of water dropped in the tank shall be measured to determine the volume of any leaks.
4. Any leak shall not exceed the standards outlined in AWWA Series C600.
4. Warranty
Materials and equipment furnished under this Contract shall be covered by the most favorable commercial warranties given to customers for such materials or equipment. The rights or remedies provided herein are in addition to and do not limit rights afforded to the Government by other clauses of this Contract. With respect to warranties, expressed or implied, from manufacturers or suppliers for materials or equipment furnished under the Contract the Contractor shall:
i. Obtain warranties that would be given in normal commercial practices.
ii. Require warranties to be executed, in writing, for the benefit of the Government.
iii. Submit warranties to the Contracting Officer prior to the final inspection.
The contractor shall honor a one-year warranty for all materials and workmanship associated with execution of this contract. The date of final acceptance begins the one-year warranty period.
SOW Page 25
SOW 12.0 As‐Builts