SNYDER CREEK DAM RECONSTRUCTION Federal contract opportunity
Solicitation number
140L0624R0060
Issued by
Department of the Interior Bureau of Land Management National Office

About this file

This document is a section of technical specifications related to the Snyder Creek Dam Reconstruction project. It covers contractor requirements for obtaining and complying with necessary environmental permits and licenses throughout the project duration. The key details are:

The contractor is responsible for obtaining all permits and licenses required to complete the work, including the Wyoming Pollutant Discharge Elimination System (WYPDES) General Permit for Discharges from Construction Activities. This includes the storm water discharge permit, Storm Water Pollution Prevention Plan, and construction site dewatering. The contractor must submit the draft permit and plan for government review within 10 days of the notice to proceed, and the final permit within 10 additional days. During construction, the contractor is responsible for all required monitoring, reporting, and maintenance of the pollution prevention plan. Once the work is complete, the government will file the Notice of Termination for the permit. Any contractor violations of permit terms may result in work stoppages at their expense. The contract bid price must include all costs associated with these permits, as no separate payment will be made.

View the file

Other files for this federal contract opportunity

Other files attached to SNYDER CREEK DAM RECONSTRUCTION, newest first.
File Type Posted
Sol_140L0624R0060_Amd_0002.pdf PDF
Attachment_0012_Q_A__2_0002.pdf PDF
Attachment_0009_Site_visit_roster_0001.pdf PDF
Sol_140L0624R0060_Amd_0001.pdf PDF
Attachment_0008_Q_A_0001.pdf PDF
Attachment_0010_Revised_Continuation_Pages_0001.pdf PDF
Attachment_0005_LPTA_SF1442_HowTo.pdf PDF
Attachment_0006_Lim_on_SubK_Breakout_23Jul2024.xlsx XLSX spreadsheet
Sol_140L0624R0060.pdf PDF
Attachment_0003_WY20240027_Wage_Determination.pdf PDF
Attachment_0004_Price_Breakout.pdf PDF
Attachment_0007_Vicinity_Map.pdf PDF
Attachment_0002_SnyderDam_Drawings.pdf PDF
Attachment_0001_SnyderDam_Specifications.pdf PDF
Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SNYDER CREEK DAM SECTION 01060

BLM PERMITS

Print Date: January 2022 01060-1 \\dowl.com\j\Projects\31\27075-01\81Specs\01060_Permits.docx

PART 1 - GENERAL

WORK INCLUDED:

This section covers Contractor requirements for providing environmental controls consistent with regulatory requirements throughout the duration of the project.

All costs associated with these permits are to be included as part of the Contract Bid Price and no separate payment will be made for these costs.

The CONTRACTOR is responsible for obtaining all permits and licenses necessary for the completion of the work, unless specifically designated as GOVERNMENT provided.

Except as otherwise noted, identify, obtain, maintain, and proceed in conformity with any and all additional required permits necessary for completion of the Work.

SUBMITTALS:

The CONTRACTOR shall supply to the GOVERNMENT a draft Storm Water Discharge General Permit and Storm Water Pollution Prevention Plan within 10 days after issuance of the Notice to Proceed. The GOVERNMENT will have 10 days to review and provide comments back to the CONTRACTOR. The CONTRACTOR then has 10 additional days to submit the final Storm Water Discharge Permit to the GOVERNMENT. Work may proceed after the final Storm Water Discharge Permit has been returned to the CONTRACTOR with an acceptance letter from the GOVERNMENT.

The CONTRACTOR shall perform all compliance testing required by all permits. Submit results of compliance testing directly to the appropriate review agency. Provide copies of all results to the GOVERNMENT. Submit copies of any additional required permits to the GOVERNMENT when they are acquired.

CONTRACTOR VIOLATIONS:

If noncompliance should occur, immediately (verbally) report noncompliance to the CO.

Submit specific written information within two days.

Violation of applicable Federal or local laws, orders, regulations, or water quality standards may result in the CO stopping unrelated site activities until compliance is achieved.

1. The Contractor will not be entitled to an extension of time, claim for damage, or additional compensation by reason of such a work stoppage.

In accordance with FAR 52.236-7, corrective measures required to bring activities into compliance and remediate environmental impacts will be at the Contractor's expense.

PERMITS

Contractor Obtained Permits

1. Wyoming Pollutant Discharge Elimination System (WYPDES) General Permit for

Discharges from Construction Activities:

a. The CONTRACTOR is responsible for obtaining all permits and licenses necessary for the completion of this Work. The CONTRACTOR is responsible

SNYDER CREEK DAM SECTION 01060

BLM PERMITS

Print Date: January 2022 01060-2 \\dowl.com\j\Projects\31\27075-01\81Specs\01060_Permits.docx for all permits relating to the discharge of water associated with construction activity under the WYPDES, including but not limited to the following: storm water discharge, Storm Water Pollution Prevention Plan, and construction site dewatering.

2. Other required permits and licenses not obtained by GOVERNMENT

CONTRACTOR RESPONSIBILITIES

Permits:

1. For the Stormwater Discharge Permit, the GOVERNMENT will designate the Contractor as the operator or holder of the Permit. The Contractor shall be responsible for associated fees.

2. Monitoring: Provide monitoring, reporting, and records as required by the permits.

Prepare, maintain, and proceed in conformity with Storm Water Discharge Permit/Storm Water

Pollution Prevention Plan as required by the Wyoming Department of Environmental Quality.

Once the CONTRACTOR prepares and submits the final permit to the GOVERNMENT, the GOVERNMENT will obtain this permit and pay all associated fees.

During construction the CONTRACTOR is responsible for all maintenance to the pollution prevention plan. When the CONTRACTOR has completed work on the project and has been issued the final payment, the GOVERNMENT will continue maintenance on the pollution prevention plan. When all criteria have been met, the GOVERNMENT will file the Notice of Termination for the permit.

Except as otherwise noted, identify, obtain, maintain, and proceed in conformity with any and all additional required permits necessary for completion of the Work.

PART 2 - PRODUCTS – NONE

Not Used.

PART 3 - EXECUTION – NONE

Not Used.

END OF SECTION 01060