Attch_13_Amend_0002_SF1510-56_Questions_Answers_0002.pdf

PDF 121 KB Posted

Attached to
NWO DISTRICT HVAC IMPROVEMENTS
Solicitation number
140L0624R0041
Issued by

About this file

This document is a Questions and Answers (Q&A) record related to the Northwest Oregon District Office HVAC System Improvements solicitation, Solicitation No: 140L0624R0041, Amendment 0002. The Q&A addresses inquiries about providing alternative controls to the specified Johnson Controls Metasys DDC system, contact information for the existing controls and fire alarm contractors, and details about the existing roofing system. The Q&A also clarifies that no excavation work is required, the building will remain occupied during construction, and the period of performance will not be extended after award due to current market conditions and equipment lead times. The solicitation is being issued by the Department of the Interior, Bureau of Land Management National Office for HVAC system improvements at the Northwest Oregon District Office. No other details about the required products, services, response dates, set asides, or pricing terms are provided in this Q&A document.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NORTHWEST OREGON DISTRICT OFFICE HVAC SYSTEM IMPROVEMENTS

Solicitation No: 140L0624R0041– Amendment 0002 Questions & Answers

Form 1510-56 (December 1985)

UNITED STATES

DEPARTMENT OF THE INTERIOR

BUREAU OF LAND MANAGEMENT

SITE INSPECTION TOUR / PREBID CONFERENCE RECORD

Questions & Answers

1. Have there been any inquiries about providing a controls alternative to the Johnson Controls Metasys DDC? Based on the spec verbiage I’m not expecting much, but I wanted to make sure.

A1: No alternatives to the Metasys DDC are permitted.

2. Who would be a good person to reach out to if Siemens wanted to get involved earlier in the design process for future

Oregon projects?

A2: The design team would reach out to varying manufacturers.

3. Do the Superintendent, SSHO and QC Manager need to be 3 separate individuals?

A3: There needs to be a competent individual on site for each position, at all times. If one person is handling all three positions, then a competent alternate needs to be designated in advance if the individual is not available.

4. Can the period of performance be extended after award once the material/equipment lead times are confirmed due to current market conditions for the equipment for this project?

A4: The building will be occupied, and all work will need to be meticulously scheduled with the Salem Office maintenance staff and COR to minimize impact on operations and allow the contractor to optimize their performance.

There will be from 50 to 100 employees in the office, depending on the day of week and time of day.

There are no temporary heating/cooling requirements, however the work shall be coordinated to provide the least impact on the building climate.

5. Can the period of performance be extended after award once the material/equipment lead times are confirmed due to current market conditions for the equipment for this project?

A5: No. Contract terms changes will be governed by the relevant FAR authorities and will be up to CO discretion.

6. Are soil boring reports available? If not, it will be assumed that excavation will be clear of rocks and obstructions.

A6: No excavation should be taking place. Please provide what reference infers that excavation is necessary. Note, the building is surrounded with fill material.

7. Please provide the contact information for the control’s contractor.

A7: Northwest Control Company is the contractor that has been servicing the existing Symmetry system: 503-656-9205.

8. Please provide the contact information for the fire alarm company.

A8: Sonitrol is the monitoring contractor: 503-223-5822.

Western States Fire Protection Company is the repair contractor: 503-657-5155.

9. Please confirm the manufacturer of the existing roofing system and who carries the current warranty of the roofing system.

A9: Records indicate the existing roof is a Hypalon material membrane that was installed in early 2000’s.