Attch_13_Amend_0002_SF1510-56_Questions_Answers_0002.pdf
PDF 119 KB Posted
- Attached to
- FAIRBANK TRAIL ADA MAINTENANCE AND IMPROVEMENTS
- Solicitation number
- 140L0624R0039
About this file
This document is a Questions & Answers (Q&A) record related to a solicitation for the FAIRBANK TRAIL ADA MAINTENANCE AND IMPROVEMENTS project, Solicitation No. 140L0624R0039, Amendment 0002.
The key details are:
- The solicitation is issued by the Department of the Interior Bureau of Land Management National Office.
- The solicitation is for ADA maintenance and improvements to the Fairbank Trail.
- The Q&A addresses questions about site access, clearing and pruning requirements, staffing qualifications, performance period, and existing trail conditions.
- The government confirms the trail is open to the public for site visits and that the existing subgrade may not be level or consistent throughout the trail segments.
- There is no incumbent contractor, as this is a new requirement.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FAIRBANK TRAIL ADA MAINTENANCE & IMPROVEMENTS
Solicitation No: 140L0624R0039 – Amendment 0002 Questions & Answers
Form 1510-56 (December 1985)
UNITED STATES
DEPARTMENT OF THE INTERIOR
BUREAU OF LAND MANAGEMENT
SITE INSPECTION TOUR / PREBID CONFERENCE RECORD
Questions & Answers
1. Is it possible to go by the sight to look at the job?
A1: Yes, Fairbanks trail is open to the public. The Site Host is also aware of possible extra walking traffic from potential offerors.
2. In section 201.1 clearing and pruning it states that brush will be cleared and pruned back 10’ vertical and 10’ horizontal, and up to 14’ in wider sections. In section 201.3 (D) it states clear branches that hang over the road surface and shoulders to a height of 20’. Is there any way to clarify what parts need to be cleared to 10’ high, and what part to 20’ high?
A2: Removal of section 201.3 D.
3. Do the Superintendent, SSHO and QC Manager need to be 3 separate individuals?
A3: No.
4. Can the period of performance be extended after award once the material/equipment lead times are confirmed due to current market conditions for the equipment for this project?
A4: No.
5. Please confirm the existing subgrade is level and consistent to install 6" of surfacing with 1,650 tons of rock aggregate.
A5: BLM does not confirm the existing subgrade is level nor consistent throughout trail segments, it is expected/presumed throughout portions of trail segments to have poor to moderate, and ununiform subgrade. See:
Section 701.04 (The existing surface shall be prepared to provide a firm and uniform subgrade for placement of surfacing material).
6. Will the government please clarify if there is an incumbent providing service on this contract or is this level of effort a new need?
A6: This level of effort is a new need.