DEMOLITION OF SIX STRUCTURES AT TLAS
Solicitation number
140G0226R0002
Issued by

About this file

This is an Amendment of Solicitation/Modification of Contract (Standard Form 30) issued by the USGS OAG Denver Acquisition Branch on March 20, 2026. The amendment addresses contractor questions and provides clarifications regarding a building demolition project involving three residential properties (identified as Q1, Q2, and Q50).

Key project details include a firm fixed price award type with a period of performance from May 1, 2026 to June 30, 2026. The amendment clarifies scope responsibilities: two of three buildings (Q2 and Q50) have completed asbestos surveys that will be provided; the contractor should assume similar asbestos results for Q1 (tan house) and maintain wet surfaces during demolition to reduce dust spread. The Government will coordinate removal of overhead electrical lines, while the contractor is responsible for tree and vegetation removal as needed to complete demolition. The driveway at Q2 must be removed and hauled away, while driveways at Q1 and Q50 shall remain in place. The contractor may deliver additional roll-off containers at all three properties and will receive property line maps from the Government. Contact information includes Technical POC Alex Gatch (agatch@usgs.gov), Admin POC Rhonda Aton (raton@usgs.gov), and Contract Specialist Philip Robinson (probinson@usgs.gov). The amendment is not extended and requires contractor acknowledgment prior to bid submission.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: is not is required copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7.ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

PAGESOF

Contractor

The hour and date specified for receipt of Offers to sign this document and return

Karen La Bouff-Kind

See continuation page

USGS OAG DENVER ACQUISITION BRANCH

PO BOX 25046

204 DENVER FEDERAL CENTER

DENVER CO 80225-0046

USGS OAG DENVER ACQUISITION BRANCH

PO BOX 25046

DENVER CO 80225-0046

GDB

GDB

140G0226R0002

03/20/2026

03/20/2026

1 3

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

NSN 7540-01-152-8067

140G0226R0002/0004

The purpose of this amendment is to address contractor questions and provide responses (Q4

- Q11).

Q4: Since a third party must perform hazardous material surveys and the asbestos surveys can't be done by the demolition contractor, will the

Government provide asbestos and lead-based paint survey reports for all 3 buildings prior to the bid due date?

A4: Two of the three houses already have completed asbestos surveys (Q50, Q2: white houses) and can be provided. Bids for demolition of Q1 (tan house not tested) should be prepared, assuming that similar results will be found as in residences Q2 and Q50. During demolition contractors will need to keep surfaces wet to reduce the spread of dust.

(Lead-Based Paint and Demolition | US EPA)

Q5: Will the Government remove trees and vegetation adjacent to the buildings prior to demolition, or should this be included in the contractor¿s scope of work?

A5: Removal of trees and vegetation should be included in the contractor¿s scope of work.

Q6: Will the Government disconnect, de-energize, and remove overhead electrical lines servicing the buildings prior to demolition, or is the contractor responsible for coordination and removal?

A6: The government will coordinate with the power supplier to remove the overhead lines servicing the buildings.

Q7: Does the driveway need to be removed, or can it be buried?

A7: The driveway at Q2 should be removed and hauled away. Driveways at Q1 and Q50 shall remain in place.

Q8: Can we deliver more roll-off containers if we stack them next to the driveway?

Continued...

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES

NAME OF OFFEROR OR CONTRACTOR

SUPPLIES/SERVICES

(B)

UNIT

(D)

UNIT PRICE

(E)

AMOUNT

(F)

OPTIONAL FORM 336 (4-86)

Sponsored by GSA FAR (48 CFR) 53.110

ITEM NO.

(A)

QUANTITY

(C)

NSN 7540-01-152-8067

140G0226R0002/0004

A8: Yes, there is plenty of space at all 3 properties for extra dumpsters.

Q9: Can you provide a map detailing the property line?

A9: Yes, we will provide a map detailing property lines.

Q10: Are the trees next to the houses to be removed?

A10: Remove trees as needed to complete the demolition.

Q11: Can we remove the trees?

A11: Yes, you may remove trees as needed.

Period of Performance: 05/01/2026 to

06/30/2026

AWARD TYPE: FIRM FIXED PRICE

TECHNICAL POC: ALEX GATCH, EMAIL:

agatch@usgs.gov

ADMIN POC: RHONDA ATON, Email: raton@usgs.gov

CONTRACT SPECIALIST: PHILIP ROBINSON, Email:

probinson@usgs.gov

Amendment of solicitation/modification of contract
Contract ID code
Amendment/modification number
Effective date
Requisition/purchase requisition number
Project number
Issued by
Code
Administered by
Code
Name and address of contractor
Code
Facility code
Amendment of solicitation number
Dated
Modification of contract/order number
Dated
This item only applies to amendments of solicitations
Accounting and appropriation data
This item applies only to modifications of contracts/orders.
This change order is issued pursuant to:
The above numbered contract/order is modified to reflect the administrative changes
This supplemental agreement is entered into pursuant to authority of:
Other
Important:
Description of amendment/modification
Name and title of signer
Contractor/offeror
Date signed
Name and title of contracting officer
Signature of Contracting Officer
Date signed
Previous edition unusable
Standard form 30 (rev. 11/2016)
Continuation sheet
Reference Number
Name of Offeror or Contractor
OPTIONAL FORM 336 (4-86))

Sponsored by GSA FAR (48 CFR) 53.110

File details come from the government source that posted it. Updated .