This document is a set of Questions and Answers (Q&A) related to Amendment 3 of Solicitation 140G0124Q0236 for the BELVIDERE GAGE REMOVAL project.
The key details are:
- The project involves dismantling and removing a Belvidere Gage Data Collection Station located at 208 Depue Street in Belvidere, New Jersey.
- The contractor must provide all labor, material, tools, equipment, and supervision necessary to complete the project within 90 days of the notice to proceed.
- The Q&A clarifies that there is an intake pipe running from the stilling well to the river, and the well needs to be filled, with the walls removed below grade, and the yard graded and seeded to match the existing grade. The valve on the intake pipe is not operational.
- The solicitation is a small business set-aside with a NAICS code of 238910 and a size standard of $19.0 million. The magnitude of construction is less than $30,000.
- The anticipated award date is 08/01/2024 and quotes must be emailed to dparkin@usgs.gov by the due date of 07/29/2024.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140G0124Q0236_Amd_0006.pdf | ||
| B09_Attachment_11_Corrected_Updated_Statement_of_Work_0006.docx | DOCX document | |
| Sol_140G0124Q0236_Amd_0005.pdf | ||
| B09_Attachment_10_Updated_Statement_of_Work_0005.docx | DOCX document | |
| B09_Attachment_9_Questions_and_Answers_Amendment_5_0005.docx | DOCX document | |
| Sol_140G0124Q0236_Amd_0004.pdf | ||
| B09_Attachment_8_Questions_and_Answers_Amendment_4_0004.docx | DOCX document | |
| Sol_140G0124Q0236_Amd_0003.pdf | ||
| Sol_140G0124Q0236_Amd_0002.pdf | ||
| B09_Attachment_6_Questions_and_Answers_Amendment_2_0002.docx | DOCX document | |
| Sol_140G0124Q0236_Amd_0001.pdf | ||
| B03_Attachment_1_WD_NJ20230045.pdf | ||
| B08_Attachment_3_Form_DI-137_Release_of_Claims.pdf | ||
| B08_Attachment_5_SF1413_Statement_and_Acknowledgement_of_Subcontractor.pdf | ||
| B08_Attachment_2_Statement_of_Work.docx | DOCX document | |
| Sol_140G0124Q0236.pdf | ||
| B08_Attachment_4_Payroll_WH-347.pdf |
Show all 17
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
140G0124Q0236 Amendment 3 Q&A
Question# 1: Are the horizontal pipes leading from the river to the stilling well? Trying to determine if a flowable fill is appropriate for the filling the well.
Answer: Yes, there is an intake pipe running from the stilling well to the river. Likely one or two 2” pipe.
Question #2: Is the well-being filled and left opened, or capped/covered?
Answer: The well needs to be filled. If the question of capping is meant to be with concreter, no we are not requiring the well be capped with concrete after being filled, but will leave it up to the contractor.
Question #3: Assuming there is a pad underneath the structure, is this to be removed, and graded to match the surrounding are around the top of the well?
Answer: Yes, the well walls need to be removed to below grade, the well filled, and the yard graded and seeded to match existing grade.
Question #4: Regarding connection to the river/creek if there are horizontal pipes leading to the water, are there shut-off valves on the pipes, and are they/can they be closed?
Answer: There is a valve, but it’s not operational.
File details come from the government source that posted it. Updated .