This is a Division/Subdivision Price Breakdown Template for a Firm-Fixed-Price federal construction contract. The template is used for the Sherburne National Wildlife Refuge (NWR) South Loop Autotour Rehabilitation project under solicitation number 140FGA26R0024. Offerors are required to submit this pricing template as part of their price proposal and must ensure the total proposal price matches the Contract Line Item Number (CLIN) lump-sum total.

The template requires pricing breakdown across two primary divisions. Division 01 – General Requirements includes five subdivisions: Summary of Work (mobilization, demobilization, project management, traffic control, erosion and sediment control); Project Coordination (meetings, notifications, coordination activities); Submittals (submittal register, testing reports, delivery tickets, progress schedule); Definitions & Standards (permit compliance, safety and regulatory requirements); and Project Closeout (O&M manuals, warranties, record drawings, final cleanup). Division 02 – Site Construction encompasses Site Work (clearing and grubbing, temporary erosion controls, access maintenance); Dewatering (if used); Excavation Support & Protection (if used); Earthwork with a subtotal price requirement; and Lawns and Grasses (topsoil placement, seeding, erosion control blanket/mulch, two-year turf maintenance). Additionally, the template includes two unit price line items: Item 3 requires a unit price per cubic yard for Additional Authorized Excavation, and Item 4 requires a unit price per ton for Aggregate Surface. Offerors must provide lump-sum prices for each subdivision and unit prices where specified, with all prices aggregated to produce a total proposal price.

View the file

Other files for this federal contract opportunity

Other files attached to EO, newest first.
File Type Posted
Sol_140FGA26R0024_Amd_0002.pdf PDF
Pre-Bid_Site_Visit_Sign_In_0002.pdf PDF
Bidder_Instructions_-_Pricing_Clarification_0002.pdf PDF
Questions_and_Answers_Amendment_2_0002.pdf PDF
Sol_140FGA26R0024_Amd_0001.pdf PDF
SOW.pdf PDF
Drawings-Specs.pdf PDF
DOL_Wage_Determination.pdf PDF
Sol_140FGA26R0024.pdf PDF
Price_Schedule.pdf PDF
Notice_to_Offerors.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Division/Subdivision Price Breakdown Template - Amendment 2

Sherburne NWR South Loop Autotour Rehab

Solicitation # 140FGA26R0024 Contract Type: Firm-Fixed-Price

(To be submitted as part of the Offeror’s Price Proposal)

Division 01 – General Requirements 01100 – Summary of Work

• Mobilization / Demobilization

• Project Management / Supervision

• Traffic Control

• Erosion & Sediment Control

Price: $_____________

01310 – Project Coordination

• Meetings

• Notifications

• Coordination Activities

01330 – Submittals

• Submittal Register

• Testing Reports

• Delivery Tickets

• Progress Schedule

01420 – Definitions & Standards

• Permit Compliance

• Safety / Regulatory Requirements

01770 – Project Closeout

• O&M Manuals

• Warranties

• Record Drawings

• Final Cleanup

Division 02 – Site Construction 02100 – Site Work

• Clearing & Grubbing

• Temporary Erosion Controls

• Access Maintenance

02240 – Dewatering (If used)

• Dewatering System

• Pumping

• Monitoring

02260 – Excavation Support & Protection (If used)

• Shoring

• Bracing

• Safety Systems

02300 – Earthwork

• Subgrade Prep

• Proof Rolling

• Compaction

• Shoulders

Subtotal Price: $_____________

Item 3 – Additional Authorized Excavation (Unit Price Requirement)

• Unit Price per Cubic Yard (CY): $_____________/CY

• Estimated Quantity (If provided): __________ CY

• Extended Price (If applicable): $_____________

Item 4 – Aggregate Surface (Unit Price Requirement)

• Unit Price per Ton: $_____________/Ton

• Estimated Quantity (If provided): __________ Tons

• Extended Price (If applicable): $_____________

02920 – Lawns and Grasses

• Topsoil Placement

• Seeding (per planting windows)

• Erosion Control Blanket / Mulch

• Two-Year Turf Maintenance

Total Division 01 Price: $________________

Total Division 02 Price: $________________

TOTAL PROPOSAL PRICE (Must match CLIN lump-sum total):