About this file
This document comprises specifications for the Willow Beach National Fish Hatchery (NFH) Hatchery Building HVAC Upgrade project, a federal construction contract managed by the U.S. Government.
The specifications establish comprehensive administrative and execution requirements for project delivery. Section 01 32 01.00 (Project Schedule) requires the contractor to submit an Initial Project Schedule within 21 calendar days of award, demonstrating a reasonable and realistic sequence covering the entire contract performance period. The schedule must serve as both a forward planning and project monitoring tool, with activity cost loading that is reasonable and without front-end loading. Mandatory activities include submission and approval of preconstruction submittals, design packages, O&M manuals, as-built drawings, contractor and government pre-final inspections, punch list corrections, and final inspection. Cost loading requirements specify minimum allocations of 1 percent of contract value for government punch list corrections and for as-built drawings (if no separate CLIN exists) and O&M manuals. Weekly progress meetings with the Government are required to jointly review actual versus planned progress. Section 01 33 00 (Submittal Procedures) governs all submittals, requiring contractor and Designer of Record approval before submission to the Government. Submittals designated with "G" classification require Government approval; others are for information only. The contractor must use the R2EN-021 transmittal form and provide submittals in PDF format with electronic bookmarks for files exceeding 30 pages. Key submittal types include SD-01 Preconstruction Submittals, SD-06 Test Reports, SD-07 Certificates, SD-10 Operation and Maintenance Data, and SD-11 Closeout Submittals. Section 01 35 26 (Governmental Safety Requirements) mandates compliance with NFPA 70, NFPA 70E, NFPA 241, Federal and State OSHA regulations, and ANSI/ASSP A10.44 standards. Contractors must apply for utility outages at least 3 days in advance, establish a Hazardous Energy Control Program (HECP), and obtain energized work permits when de-energizing introduces additional hazard. Electrical work must be conducted in a de-energized state as the preferred method.
Section 01 45 00 (Quality Control) requires the contractor to establish and maintain an effective QC system compliant with FAR 52.246-12, with QC costs included in bid pricing. The contractor is responsible for quality of all work, including subcontractor work, covering both onsite and offsite operations. QC procedures must include field verification of dimensions and component characteristics prior to Government submittal. Completion inspections include contractor punch-out inspection, Government pre-final inspection, and final acceptance inspection (with notification required 14 days in advance). Section 01 78 00 (Closeout Submittals) requires operation and maintenance manuals and as-built drawings marked with red, green, and blue color coding for deletions, additions, and special items respectively, maintained as hard copies on site throughout construction. Section 01 78 23 (Operation and Maintenance Data) specifies that the O&M manual be assembled as an electronically bookmarked PDF containing seven parts: Facility Design and Construction, Facilities/Systems/Assemblies Information (including manufacturer specifications and approved drawings), Wiring and Control Diagrams, Warranty Information, Facility Operations (testing and performance data), Training materials, and Commissioning reports. Comprehensive training must be provided to hatchery management and maintenance personnel, with 95 percent of instruction time devoted to operation and maintenance data, covering start-up, normal operation, shutdown, troubleshooting, safety issues, system interactions, maintenance, and tenant interaction issues. Training validation requires signed class rosters and a validation letter documenting attendee participation, systems covered, trainer information, training dates and locations.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Willow Beach NFH – Hatchery Building HVAC Upgrade
SECTION 01 32 01.00 Page 1 of 4
SECTION 01 32 01.00
PROJECT SCHEDULE
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" classification.
Submittals not having a "G” classification are for information only.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Initial Project Schedule; G
PART 2 PRODUCTS
NOT USED
PART 3 EXECUTION
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15 Schedules for Construction Contracts. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of design and construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development. Designers, Subcontractors, and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is forward planning as well as a project monitoring tool.
3.2 BASIS FOR PAYMENT AND COST LOADING
The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a Contract Line-Item Number (CLIN) must equal the value of the CLIN.
3.2.1 Activity Cost Loading
Activity cost loading must be reasonable and without front-end loading.
Activities with negative cost loading are not allowed. The Government reserves the right to request additional documentation to demonstrate reasonableness.
3.2.2 Cost Loading of Submittals
No costs are to be assigned to activities for the preparation, review, or approval of submittals, except as described under paragraph COST LOADING OF
SECTION 01 32 01.00 Page 2 of 4
CLOSEOUT ACTIVITIES, paragraph AS-BUILT DRAWINGS, paragraph design submittals, and paragraph O&M MANUALS.
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
3.3.1 Level of Detail Required
Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:
3.3.2 Activity Durations
Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.
3.3.3 Design Activities
Include design activities with the necessary conferences and follow-up actions and design package submission dates. Include the design schedule in the project schedule, showing the sequence of events involved in carrying out the project design tasks within the specific contract period.
Provide a detailed level of scheduling sufficient to identify all major design tasks, including those that control the flow of work. Also include review and correction periods associated with each item.
3.3.4 Procurement Activities
Include in the schedule activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.
3.3.5 Mandatory Activities
Include the following activities in the initial project schedule and all updates.
a. Submission, review and acceptance of SD-01 Preconstruction Submittals (individual activity for each).
b. Submission, review and acceptance of design packages.
c. Submission and approval of O & M manuals.
d. Submission and approval of as-built drawings.
e. Contractor's pre-final inspection.
f. Correction of punch list from Contractor's pre-final inspection.
g. Government's pre-final inspection.
SECTION 01 32 01.00 Page 3 of 4
h. Correction of punch list from Government's pre-final inspection.
i. Final inspection.
3.3.6 Government Activities
Show in schedule, Government activities that could impact progress. These activities include, but are not limited to approvals, acceptance, and design reviews .
3.3.7 Percent Complete
Update the percentage complete for each activity started, based on the realistic assessment of earned value.
3.3.8 Remaining Duration
Update the remaining duration for each activity based on the number of estimated workdays it will take to complete the activity. Remaining duration may not mathematically correlate with percentage found under paragraph entitled Percent Complete. The remaining duration for unstarted activities are not to be less than its original duration.
3.3.9 Cost Loading of Closeout Activities
Cost load the "Correction of punch list from Government pre-final inspection" activity(ies) not less than 1 percent of the present contract value. Activity(ies) may be declared 100 percent complete upon the Government's verification of completion and correction of all punch list work identified during Government pre-final inspection(s).
3.3.9.1 As-Built Drawings
If there is no separate contract line item (CLIN) for as-built drawings, cost load the "Submission and approval of as-built drawings" activity not less than 1 percent of the present contract value. Activity will be declared 100 percent complete upon the Government's approval.
3.3.9.2 O & M Manuals
Cost load the "Submission and approval of O & M manuals" activity not less than 1 percent of the present contract value. Activity will be declared 100 percent complete upon the Government's approval of all O & M manuals.
3.4 PROJECT SCHEDULE SUBMISSIONS
Provide the submissions as described below. If the Contractor fails or refuses to furnish the information and schedule updates as set forth herein, the Contractor will be deemed not to have provided an estimate upon which a progress payment can be made.
Review comments made by the Government on the schedule(s) do not relieve the Contractor from compliance with requirements of the Contract Documents.
3.4.1 Initial Project Schedule Submission
SECTION 01 32 01.00 Page 4 of 4
Submit the Initial Project Schedule for approval within 21 calendar days after notice of award. The schedule must demonstrate a reasonable and realistic sequence of activities which represent all work through the entire contract performance period. Cover in the initial project schedule the entire construction effort with as much detail as is known at the time. As the design proceeds and design packages are developed, fully detail the remaining construction activities. Constrain construction activities by Government acceptance of associated designs.
3.5 WEEKLY PROGRESS MEETINGS
Conduct a weekly meeting with the Government for the purpose of jointly reviewing the actual progress of the project as compared to the as planned progress and to review planned activities for the upcoming two weeks. Use the current approved schedule update for the purposes of this meeting and for the production and review of reports. At the weekly progress meeting, address the status of RFIs, RFPs and Submittals.
3.6 OWNERSHIP OF FLOAT
Float available in the schedule, at any time, belongs to the Project and is available for Contractor and Government use. This includes activity and project float. Activity float is the number of workdays that an activity can be delayed without causing a delay to the "End Project" finish milestone. Project float (if applicable) is the number of work days between the projected early finish and the "End Project" finish.
-- End of Section --
SECTION 01 33 00 Page 1 of 10
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 SUMMARY
1.1.1 Submittal Information
The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections. Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.
Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.
The Contractor and the Designer of Record (DOR), if applicable, are to check and approve all items before submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as: Contractor's, manufacturer's, or fabricator's drawings;
descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders;
samples; O&M manuals (including parts list); certifications; warranties;
and other such required submittals.
1.1.2 Submission of Submittals
Schedule and provide submittals requiring Government approval before acquiring the material or equipment covered thereby.
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
Submittal requirements are specified in the technical sections. Examples and descriptions of submittals identified by the Submittal Description (SD) numbers and titles follow:
SD-01 Preconstruction Submittals
Submittals that are required prior to or at the start of construction (work) or the next major phase of the construction on a multiphase contract.
Preconstruction Submittals include schedules and a tabular list of locations, features, and other pertinent information regarding products, materials, equipment, or components to be used in the work.
Certificates Of Insurance
Surety Bonds
List Of Proposed Subcontractors
SECTION 01 33 00 Page 2 of 10
Submittal Register
Schedule Of Values
SD-06 Test Reports
Report that includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation. Investigation reports
Daily logs and checklists
Final acceptance test and operational test procedure
SD-07 Certificates
Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that the product, system, or material meets specification requirements. Must be dated after award of project contract and clearly name the project.
Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor. The purpose of the document is to further promote the orderly progression of a portion of the work by documenting procedures, acceptability of methods, or personnel qualifications.
SD-10 Operation and Maintenance Data
Data provided by the manufacturer, or the system provider, including manufacturer's help and product line documentation, necessary to maintain and install equipment, for operating and maintenance use by facility personnel.
Data required by operating and maintenance personnel for the safe and efficient operation, maintenance and repair of the item.
Data incorporated in an operations and maintenance manual or control system.
SD-11 Closeout Submittals
Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.
Special requirements necessary to properly close out a construction contract. For example, As-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.
1.2.2 Approving Authority
Office or designated person authorized to approve the submittal.
SECTION 01 33 00 Page 3 of 10
1.2.3 Work
As used in this section, on-site and off-site construction required by contract documents, including labor necessary to produce submittals, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction. In exception, excludes work to produce SD-01 submittals.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" classification.
Submittals not having a "G" classification are for information only.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Submittal Register; G
1.4 SUBMITTAL CLASSIFICATION
1.4.1 Government Approved (G)
Government approval is required for any variations from the Solicitation or the Accepted Proposal and for other items as designated by the Government.
Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, submittals are considered to be "shop drawings."
1.4.2 Design-Build Submittal Classifications
1.4.2.1 Designer of Record Approved (DA)
Designer of Record (DOR) approval is required for extensions of design;
critical materials; any variations from the Solicitation, the Accepted Proposal, or the completed design; equipment whose compatibility with the entire system must be checked; and other items as designated by the Contracting Officer. Provide the Government with the number of copies designated hereinafter of all DOR approved submittals. The Government may review any or all Designer of Record approved submittals for conformance with the Solicitation, the Accepted Proposal, and the completed design.
The Government will review all submittals designated as varying from the Solicitation or Accepted Proposal, as described below.
1.4.2.2 Government Conformance Review of Design (CR)
The Government will review all intermediate and final design submittals for conformance with the technical requirements of the Solicitation.
Review will be only for conformance with the applicable codes, standards, and contract requirements.
1.4.2.3 Designer of Record Approved/Government Conformance Review (DA/CR)
1.4.2.3.1 Variations from the Accepted Design
SECTION 01 33 00 Page 4 of 10
DOR approval and the Government's concurrence are required for any proposed variation from the accepted design that still complies with the contract before the Contractor is authorized to proceed with material acquisition or installation. If necessary to facilitate the project schedule, before official submission to the Government, the Contractor and the DOR may discuss with the Contracting Officer's Representative a submittal proposing a variation. However, the Government reserves the right to review the submittal before providing an opinion. In any case, the Government will not formally agree to or provide a preliminary opinion on any variation without the DOR's approval or recommended approval. The Government reserves the right to reject any design or variation.
1.4.2.4 Designer of Record Approved/Government Approved (DA/GA)
In addition to the above-stated requirements for proposed variations to the accepted design, both DOR and Government Approval and, where applicable, a contract modification are required before the Contractor is authorized to proceed with material acquisition or installation for any proposed variation to the contract, that constitutes a change to the contract terms. The Government reserves the right to accept or reject any such proposed variation.
1.4.3 For Information Only
Submittals not requiring Government approval will be for information only.
Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, they are not considered to be "shop drawings."
1.5 PREPARATION
1.5.1 Transmittal Form
Use the R2EN-021 transmittal form for submitting both Government-approved and information-only submittals. This form will be furnished to the Contractor. Properly complete this form by filling out all the heading blank spaces and identifying each item submitted. Exercise special care to ensure proper listing of the specification paragraph and sheet number of the contract drawings pertinent to the data submitted for each item.
1.5.2 Submittal Format
1.5.2.1 Format of SD-01 Preconstruction Submittals
When the submittal includes a document that is to be used in the project, or is to become part of the project record, other than as a submittal, do not apply the Contractor's approval stamp to the document itself, but to a separate sheet accompanying the document. Provide data in the unit of measure used in the contract documents.
1.5.2.2 Format for SD-02 Shop Drawings
Prepare drawings to accurate size, with scale indicated. Ensure drawings are suitable for reproduction and of a quality to produce clear, distinct lines and letters, with dark lines on a white background.
a. Dimension drawings, except diagrams and schematic drawings. Prepare drawings demonstrating interface with other trades to scale. Use the
SECTION 01 33 00 Page 5 of 10 same unit of measure for shop drawings as indicated on the contract drawings. Identify materials and products for work shown.
Submit an electronic copy of drawings in PDF format.
1.5.2.3 Format of SD-03 Product Data
Present product data submittals for each section. Include a table of contents, listing the page and catalog item numbers for product data.
Indicate, by prominent notation, each product that is being submitted;
indicate the specification section number and paragraph number to which it pertains.
1.5.2.3.1 Standards
Where equipment or materials are specified to conform to industry or technical-society reference standards of such organizations as the American National Standards Institute (ANSI), ASTM International (ASTM), National Electrical Manufacturer's Association (NEMA), Underwriters Laboratories (UL), or Association of Edison Illuminating Companies (AEIC), submit proof of such compliance. The label or listing by the specified organization will be acceptable evidence of compliance.
1.5.2.3.2 Data Submission
Collect required data submittals for each specific material, product, unit of work, or system into a single submittal that is marked for choices, options, and portions applicable to the submittal. Mark each copy of the product data identically. Partial submittals will not be accepted. Submit the manufacturer's instructions before installation.
1.5.2.4 Format of SD-05 Design Data
Provide design data in a format that allows information to be appropriately reviewed. Clearly label and indicate the data presented.
1.5.2.5 Format of SD-06 Test Reports
By prominent notation, indicate each report in the submittal. Indicate the specification number and paragraph number to which each report pertains.
1.5.2.6 Format of SD-08 Manufacturer's Instructions
Present manufacturer's instructions submittals for each section. Include the manufacturer's name, trade name, place of manufacture, and catalog model or number on product data. Also include applicable federal, industry, and technical-society publication references. Submit the manufacturer's instructions before installation.
1.5.2.7 Format of SD-09 Manufacturer's Field Reports
By prominent notation, indicate each report in the submittal. Indicate the specification number and paragraph number to which each report pertains.
SECTION 01 33 00 Page 6 of 10
1.5.2.8 Format of SD-10 Operation and Maintenance Data (O&M)
Comply with the requirements specified in Section 01 78 23 OPERATION AND MAINTENANCE DATA for O&M Data format.
1.5.2.9 Format of SD-11 Closeout Submittals
When the submittal includes a document that is to be used in the project or is to become part of the project record, other than as a submittal, do not apply the Contractor's approval stamp to the document itself, but to a separate sheet accompanying the document. Provide data in the unit of measure used in the contract documents. 1.5.3 Source Drawings for Shop
Drawings
1.5.3.1 Source Drawings
There are no source drawings available. Red-line markups are acceptable in lieu of computer drafted shop drawings.
1.5.4 Electronic File Format
Provide submittals in electronic format. Compile the submittal file as a single, complete document, to include the Transmittal Form described within. Electronic files must be of sufficient quality that all information is legible. Use PDF as the electronic format, unless otherwise specified or directed. Generate PDF files from original documents with bookmarks so that the text included in the PDF file is searchable and can be copied. If documents are scanned, optical character resolution (OCR) routines are required. Index and bookmark files exceeding 30 pages to allow efficient navigation of the file. When required, the electronic file must include a valid electronic signature or a scan of a signature.
1.6 INFORMATION ONLY SUBMITTALS
Submittals without a "G" designation must be certified by the QC manager and submitted for information-only. Approval is not required on information only submittals. A mark of "no action" will be provided on information only submittals. The Government reserves the right to return unsatisfactory submittals and require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Government from requiring removal and replacement of nonconforming material incorporated in the work.
1.7 PROJECT SUBMITTAL REGISTER
A sample Project Submittal Register showing items required by the specifications is provided as "Attachment A - Submittal Register." This sample only shows Division 01 submittals. Once the remaining technical specifications are developed the Contractor will incorporate them as appropriate to the Submittal Register. This sample is not required, but all information shown must be included regardless of format.
SECTION 01 33 00 Page 7 of 10
1.7.1 Submittal Management
Prepare and maintain a submittal register, as the work progresses. This list may not be all-inclusive and additional submittals may be required.
1.7.2 Design-Build Submittal Register
The Designer of Record develops a complete list of submittals during design and identify required submittals in the specifications and use the list to prepare the Submittal Register. The approved submittal register will serve as a scheduling document for submittals and will be used to control submittal actions throughout the contract period. Coordinate the submit dates and need dates with dates in the Contractor prepared progress schedule. Submit monthly or until all submittals have been satisfactorily completed, updates to the submittal register showing the Contractor action codes and actual dates with Government action codes. Revise the submittal register when the progress schedule is revised and submit both for approval.
1.8 VARIATIONS
Variations from contract requirements require Contracting Officer approval pursuant to contract Clause FAR 52.236-21 Specifications and Drawings for Construction and will be considered where advantageous to the Government.
1.8.1 Considering Variations
Discussion of variations with the Contracting Officer before submission will help ensure that functional and quality requirements are met and minimize rejections and resubmittals. For variations that include design changes or some material or product substitutions, the Government may require an evaluation and analysis by a licensed professional engineer hired by the contractor.
Specifically point out variations from contract requirements in a transmittal letter. Failure to point out variations may cause the Government to require rejection and removal of such work at no additional cost to the Government.
1.8.2 Proposing Variations
1.8.3 Warranting that Variations are Compatible
When delivering a variation for approval, the Contractor warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.
1.8.4 Review Schedule Extension
In addition to the normal submittal review period, a period of 14 calendar days will be allowed for the Government to consider submittals with variations.
1.9 SCHEDULING
SECTION 01 33 00 Page 8 of 10
Schedule and submit concurrently product data and shop drawings covering component items forming a system or items that are interrelated. Submit pertinent certifications at the same time. No delay damages or time extensions will be allowed for time lost in late submittals.
a. Coordinate scheduling, sequencing, preparing, and processing of submittals with performance of work so that work will not be delayed by submittal processing. The Contractor is responsible for additional time required for Government reviews resulting from required resubmittals. The review period for each resubmittal is the same as for the initial submittal.
b. Submittals required by the contract documents are listed on the submittal register. If a submittal is listed in the submittal register but does not pertain to the contract work, the Contractor is to include the submittal in the register and annotate it "N/A" with a brief explanation.
1.9.1 Government Reviewed Design
The Government will review design submittals for conformance with the technical requirements of the Solicitation. Government review is required for variations from the completed design. Review will be only for conformance with the contract requirements.
1.10 GOVERNMENT APPROVING AUTHORITY
When the approving authority is the Government, it will:
a. Note the date on which the submittal was received.
b. Review submittals for approval within the scheduling period specified and only for conformance with project design concepts and compliance with contract documents.
c. Identify returned submittals with one of the actions defined in paragraph REVIEW NOTATIONS and with comments and markings appropriate for the action indicated.
If the Government performs a conformance review of other Designer of Record approved submittals, the submittals will be identified and returned, as described above.
1.10.1 Review Notations
Submittals will be returned to the Contractor with the following notations:
a. Submittals marked "approved" authorize proceeding with the work covered.
b. Submittals marked "approved as noted" authorize proceeding with the work covered provided that the Contractor takes no exception to the corrections.
SECTION 01 33 00 Page 9 of 10
c. Submittals marked "disapproved" or "revise and resubmit" indicate incomplete submittal or noncompliance with the contract requirements or design concept. Resubmit with appropriate changes. Do not proceed with work for this item until the resubmittal is approved.
d. Submittals marked "no action" indicate that submittals have been received by the Government. This applies only to "information-only submittals" as previously defined.
1.11 DISAPPROVED SUBMITTALS
Make corrections required by the Contracting Officer. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications, give notice to the Contracting Officer as required under the FAR clause titled CHANGES.
The Contractor is responsible for the dimensions and design of connection details and the construction of work. Failure to point out variations may cause the Government to require rejection and removal of such work at the Contractor's expense.
If changes are necessary to submittals, make such revisions and resubmit in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.
1.12 APPROVED SUBMITTALS
The Contracting Officer's approval of submittals is not to be construed as a complete check, and indicates only that the general method of construction, materials, detailing, and other information are satisfactory and the design, general method of construction, materials, detailing, and other information appear to meet the Solicitation and Accepted Proposal.
Approval or acceptance by the Government for a submittal does not relieve the Contractor of the responsibility for meeting the contract requirements or for any error that may exist, because under the Quality Control (QC) requirements of this contract, the Contractor is responsible for ensuring information contained within each submittal accurately conforms with the requirements of the contract documents.
After submittals have been approved or accepted by the Contracting Officer, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.
1.13 CERTIFICATION OF SUBMITTAL DATA
Certify the submittal data as follows on Form ENG 4025: "I certify that the above submitted items had been reviewed in detail and are correct and in strict conformance with the contract drawings and specifications except as otherwise stated. ______NAME OF CONTRACTOR ______ SIGNATURE OF
CONTRACTOR
PART 2 PRODUCTS
SECTION 01 33 00 Page 10 of 10
Not Used
PART 3 EXECUTION
Not Used
SECTION 01 35 26 Page 1 of 3
SECTION 01 35 26
GOVERNMENTAL SAFETY REQUIREMENTS
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN SOCIETY OF SAFETY PROFESSIONALS (ASSP)
ANSI/ASSP A10.44 (2020) Control of Energy Sources (Lockout/Tagout) for Construction and Demolition Operations
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 70 (2026; TIA 26-1; ERTA 26-1; TIA 26-2; TIA
26-3; TIA 26-4; TIA 26-5; TIA 26-6; TIA
26-7; ERTA 26-2; ERTA 26-3) National
Electrical Code
NFPA 70E (2024) Standard for Electrical Safety in the Workplace
NFPA 241 (2022; ERTA 22-1) Standard for Safeguarding Construction, Alteration, and Demolition Operations
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
29 CFR 1910 Occupational Safety and Health Standards
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
3.1 CONSTRUCTION AND OTHER WORK
Comply with NFPA 70, NFPA 70E, NFPA 241, Federal and State OSHA regulations, and other related submittals and activity fire and safety regulations. The most stringent standard prevails.
PPE is governed in all areas by the nature of the work the employee is performing. Use personal hearing protection at all times in designated noise hazardous areas or when performing noise hazardous tasks. Safety glasses must be worn or carried/available on each person.
SECTION 01 35 26 Page 2 of 3
3.1.1 Unforeseen Hazardous Material
Contract documents identify materials such as PCB, lead paint, and friable and non-friable asbestos and other OSHA regulated chemicals (i.e., 29 CFR Part 1910.1000). If material(s) that can be hazardous to human health upon disturbance are encountered during demolition, repair, renovation, or construction operations, stop portions of work that would disturb the material and notify the Contracting Officer immediately. Within 14 calendar days the Government will determine if the material is hazardous.
If material is not hazardous or poses no danger, the Government will direct the Contractor to proceed without change. If material is hazardous and handling of the material is necessary to accomplish the work, the Government will issue a modification.
3.2 UTILITY OUTAGE REQUIREMENTS
Apply for utility outages at least 3 days in advance. At a minimum, the written request must include the location of the outage, utilities being affected, duration of outage, any necessary sketches, and a description of the means to fulfill energy isolation requirements.
In accordance with NFPA 70E, work on energized electrical circuits must not be performed without prior Government authorization. Energized work permits are considered only when de-energizing introduces additional or increased hazard or when de-energizing is infeasible.
3.3 CONTROL OF HAZARDOUS ENERGY (LOCKOUT/TAGOUT)
Provide and operate a Hazardous Energy Control Program (HECP) in accordance with 29 CFR 1910, ANSI/ASSP A10.44, NFPA 70E.
3.3.1 Lockout/Tagout Isolation
Where the Utility performs equipment isolation and lockout/tagout, the Contractor must place their own locks and tags on each energy-isolating device and proceed in accordance with the HECP. Before any work begins, both the Contractor and the Utility must perform energy isolation verification testing.
3.3.2 Lockout/Tagout Removal
Upon completion of work, conduct lockout/tagout removal procedure in accordance with the HECP. Each lock and tag must be removed from each energy isolating device by the authorized individual or systems operator who applied the device. Provide formal notification to the Government confirming that steps of de-energization and lockout/tagout removal procedure have been conducted and certified through inspection and verification. Utility locks and tags used to support the Contractor's work will not be removed until the authorized Government employee receives the formal notification.
3.4 ELECTRICAL WORK
Electrical work is to be conducted in a de-energized state unless there is no alternative method for accomplishing the work. In those cases, obtain
SECTION 01 35 26 Page 3 of 3 an energized work permit from the Contracting Officer. The energized work permit application must be accompanied by an Activity Hazard Analysis and a summary of why the equipment/circuit needs to be worked energized.
Cables that will be cut must be positively identified and de-energized prior to performing each cut. Plan so that work near energized parts is minimized to the fullest extent possible. Use of electrical outages clear of any energized electrical sources is the preferred method.
SECTION 01 45 00 Page 1 of 2
SECTION 01 45 00
QUALITY CONTROL
PART 1 GENERAL
1.1 PAYMENT
Separate payment will not be made for providing and maintaining an effective Quality Control program. Include all associated costs in the applicable Bid Pricing Schedule item.
1.2 GENERAL REQUIREMENTS
Establish and maintain an effective quality control (QC) system that complies with FAR 52.246-12 Inspection of Construction. QC is comprised of plans, procedures, and organization necessary to produce an end product that complies with the Contract requirements. The QC system covers all design and construction operations, both onsite and offsite, and must be keyed to the proposed design and construction sequence. The Prime Contractor is responsible for the quality of work, including work performed by all sub-contractors.
1.3 SUBMITTAL AND DELIVERABLES REVIEW AND APPROVAL
Procedures for submission, review and approval of submittals are described in Section 01 33 00 SUBMITTAL PROCEDURES. Procedures must include field verification of relevant dimensions and component characteristics by the QC organization prior to submittal being sent to the Contracting Officer.
The CQC organization is responsible for certifying that all submittals and deliverables are in compliance with the Contract. When Section 01 91
00.15 BUILDING COMMISSIONING are included in the Contract, the submittals required by those sections have to be coordinated with Section 01 33 00 SUBMITTAL PROCEDURES to ensure adequate time is allowed for each type of submittal required.
1.4 COMPLETION INSPECTIONS
1.4.1 Punch-Out Inspection
Near the completion of all work or any increment thereof, established by a completion time stated in the Contract Clause entitled "Commencement, Prosecution, and Completion of Work," or stated elsewhere in the specifications, the QC Manager must conduct an inspection of the work and develop a "punch list" of items which do not conform to the approved drawings, specifications, and Contract. Include in the punch list any remaining items on the "Deficiency/Rework Items List", that were not corrected prior to the Punch-Out Inspection as approved by the Contracting Officer in accordance with the paragraph DEFICIENCY/REWORK ITEMS LIST.
Include within the punch list the estimated date by which the deficiencies will be corrected. Provide a copy of the punch list to the Contracting Officer.
The QC Manager, or staff, must make follow-on inspections to ascertain that all deficiencies have been corrected. All punch list items must be confirmed as corrected by the QC Manager and concurred by the Contracting
SECTION 01 45 00 Page 1 of 2
Officer. Once this is accomplished, notify the Government that the facility is ready for the Government "Pre-Final Inspection".
1.4.2 Pre-Final Inspection
The Government and QC Manager will perform this inspection to verify that the facility is complete and ready to be occupied. A Government "Pre- Final Punch List" will be documented by the QC Manager as a result of this inspection. The QC Manager will ensure that all items on this list are corrected and concurred by the Contracting Officer prior to notifying the Government that a "Final" inspection with the Client can be scheduled.
All items noted on the "Pre-Final" inspection must be corrected and concurred by the Contracting Officer in a timely manner and be accomplished before the Contract completion date for the work, or any increment thereof, if the project is divided into increments by separate completion dates unless exceptions are directed by the Contracting Officer.
1.4.3 Final Acceptance Inspection
Notify the Contracting Officer at least 14 calendar days prior to the date a final acceptance inspection can be held. State within the notice that all items previously identified on the pre-final punch list will be corrected and acceptable, along with any other unfinished Contract work, by the date of the final acceptance inspection. The Contractor must be represented by the QC Manager, the Project Superintendent, and others deemed necessary. Attendees for the Government will include the Contracting Officer, other Government QA personnel, and personnel representing the Client. Failure of the Contractor to have all Contract work acceptably complete for this inspection will be cause for the Contracting Officer to bill the Contractor for the Government's additional inspection cost in accordance with the Contract Clause entitled "Inspection of Construction."
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
SECTION 01 78 00 Page 1 of 3
SECTION 01 78 00
CLOSEOUT SUBMITTALS
PART 1 GENERAL
1.1 DEFINITIONS
1.1.1 As-Built Drawings
As-built drawings are the marked-up drawings, maintained by the Contractor on-site, that depict actual conditions and deviations from the Contract Documents. These deviations and additions may result from coordination required by but not limited to: contract modifications; official responses to submitted Requests for Information (RFI's); direction from the Contracting Officer; design that is the responsibility of the Contractor, and differing site conditions. Maintain the as-builts throughout construction as red-lined hard copies on site.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" classification.
Submittals not having a "G” classification are for information only.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-10 Operation and Maintenance Data
Operation and Maintenance Manuals; G
SD-11 Closeout Submittals
As-Built Drawings; G
1.3 QUALITY CONTROL
Additions and corrections to the contract drawings must be equal in quality and detail to that of the originals.
PART 2 PRODUCTS
2.1 REDLINES AND MARKUPS
Provide PDFs of the current working redlines and/or markups complying with the as-builts drawing and markup requirements contained in this specification.
2.2 AS-BUILT RE-SUBMISSION REQUIREMENTS
If elements of an as-built submittal is rejected, provide the following for each re-submission, in addition to any information required in Section 01
33 00 SUBMITTAL PROCEDURES:
a. Re-submit all components required under paragraph As-Builts.
SECTION 01 78 00 Page 2 of 3
b. Provide a copy of all Government review comments.
c. Provide a response to each Government review comment for a back-check of the re-submission deliverable.
PART 3 EXECUTION
3.1 AS-BUILT DRAWINGS
Provide and maintain one black line print copies of the PDF contract drawings for As-Built Drawings. Maintain the as-builts throughout construction as red-lined hard copies on site.
3.1.1 Markup Guidelines
Make comments and markup the drawings complete without reference to letters, memos, or materials that are not part of the As-Built drawing.
Show what was changed, how it was changed, where item(s) were relocated and change related details. These working as-built markup prints must be neat, legible and accurate as follows:
a. Use base colors of red, green, and blue. Color code for changes as follows:
(1) Special (Blue) - Items requiring special information, coordination, or special detailing or detailing notes.
(2) Deletions (Red) - Over-strike deleted graphic items (lines), lettering in notes and leaders.
(3) Additions (Green) - Added items, lettering in notes and leaders.
b. Provide a legend if colors other than the "base" colors of red, green, and blue are used.
c. Add and denote any additional equipment or material facilities, service lines, incorporated under As-Built Revisions if not already shown in legend.
d. Use frequent written explanations on markup drawings to describe changes. Do not totally rely on graphic means to convey the revision.
e. Use legible lettering and precise and clear digital values when marking prints. Clarify ambiguities concerning the nature and application of change involved.
f. Wherever a revision is made, also make changes to related section views, details, legend, profiles, plans and elevation views, schedules, notes and call out designations, and mark accordingly to avoid conflicting data on all other sheets.
g. For deletions, cross out all features, data and captions that relate to that revision.
h. For changes on small-scale drawings and in restricted areas, provide large-scale inserts, with leaders to the applicable location.
SECTION 01 78 00 Page 3 of 3
i. Indicate one of the following when attaching a print or sketch to a markup print:
(1) Add an entire drawing to contract drawings
(2) Change the contract drawing to show changes on the drawing.
(3) Provided for reference only to further detail the initial design.
j. Incorporate all shop and fabrication drawings into the markup drawings.
3.1.2 As-Built Drawings Content
Keep working as-built markup drawings current on a weekly basis and at least one set available on the jobsite at all times. Changes from the contract drawings which are made during construction or additional information which might be uncovered in the course of construction must be accurately and neatly recorded as they occur by means of details and notes.
3.2 OPERATION AND MAINTENANCE MANUALS
Provide project operation and maintenance manuals as specified in Section 01 78 23 OPERATION AND MAINTENANCE DATA. Provide one electronic copy of the Operation and Maintenance Manual files.
SECTION 01 78 23 Page 1 of 4
SECTION 01 78 23
OPERATION AND MAINTENANCE DATA
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" classification.
Submittals not having a "G" classification are for information only.
Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES: SD-10 Operation and Maintenance Data
Training Content
Operation And Maintenance Manual; G
SD-11 Closeout Submittals
Validation of Training Completion; G
1.2 OPERATION AND MAINTENANCE MANUAL MEDIA
Assemble Operation and Maintenance Manual into an electronically bookmarked file using the most current version of Adobe Acrobat or similar software capable of producing PDF file format.
1.3 O&M MANUAL CONTENT
Organize the bookmarked Operation and Maintenance Manual into the following Parts.
1.3.1 Part 1: Facility Design and Construction
1.3.1.1 Contract Documents, RFP, Amendments, and Modifications
Provide the contract construction documents complete, to include specifications, drawings, Request for Proposal, amendments, and modifications.
1.3.2 Part 2: Facilities, Systems, and Assemblies Information
1.3.2.1 Manufacturer's Operations and Maintenance Data
Provide a copy of all manufacturer specifications and cutsheets. Provide text-searchable, high-quality document files from the manufacturer's online or electronic documentation. Color documents are preferred.
Provide documents specific to the product(s) installed under this Contract. Provide identification and coverage for the parts of each component, assembly, subassembly, and accessory of the end items subject to replacement. When possible, do not submit document files containing multiple product catalogs from the same manufacturer, or product data from multiple manufacturers in the same files. Provide documents directly from the manufacturer whenever possible. Do not provide scanned copies of
SECTION 01 78 23 Page 2 of 4 hardcopy documents. Provide identification and coverage for the parts of each component, assembly, subassembly, and accessory of the end items subject to replacement. Provide clear and legible illustrations, drawings, and exploded views to enable easy identification of the items.
When illustrations omit the part numbers and description, both the illustrations and separate listing must show the index, reference, or key number that will cross-reference the illustrated part to the listed part.
Parts data may cover more than one model or series of equipment, components, assemblies, subassemblies, attachments, or accessories, such as typically shown in a master part catalog.
1.3.2.2 Approved Coordination/Shop Drawings
Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work. Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project. Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.
1.3.3 Part 3: Wiring Diagrams and Control Diagrams
Provide point-to-point drawings of wiring and control circuits including factory-field interfaces. Provide a complete and accurate depiction of the actual job specific wiring and control work. On diagrams, number electrical and electronic wiring and pneumatic control tubing and the terminals for each type, identically to actual installation configuration and numbering.
1.3.4 Part 4: Warranty Information
List and explain the various warranties and clearly identify the servicing and technical precautions prescribed by the manufacturers or contract documents in order to keep warranties in force. Identify if replacement of a subassembly, attachment or accessory requires the entire assembly to be replaced. Include warranty information for primary components of the system. Provide copies of warranties required by Section 01 78 00
CLOSEOUT SUBMITTALS.
List all warranties for products, equipment, components, and sub-components whose duration exceeds one year. For each warranty listed, indicate the applicable specification section, duration, start date, end date, and the point of contact for warranty fulfillment. Also, list or reference the specific operation and maintenance procedures that must be performed to keep the warranty valid. Provide copies of warranties required by Section 01 78 00 CLOSEOUT SUBMITTALS.
1.3.5 Part 5: Facility Operations
1.3.5.1 Testing and Performance Data
Include completed pre-functional checklists, functional performance test forms, and monitoring reports. Include recommended schedule for retesting and blank test forms. Provide final set points.
SECTION 01 78 23 Page 3 of 4
1.3.5.2 Approved Field Test Reports and Manufacturer's Field Reports
Compile and provide approved Field Test Reports (SD-06) and Manufacturer's Field Reports (SD-09) submittals.
1.3.6 Part 6: Training
Provide a copy of training plans used for each type of equipment along with training materials used, arranged in specification sequence. Provide a copy of training records, sign-in sheets, and agendas. Include training and documentation on the updating and continued use of the O&M Manual.
1.3.7 Part 7: Cx Project Report
Provide the final Cx Plan and complete Cx reports with evaluation and testing forms and records for each building system. Include relevant commissioned system assemblies test reports including installers checklists of assemblies. Provide all Cx Progress Reports, issues and resolutions logs with resolution or status of each item, and a list of any open items and seasonal or additional testing required.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
3.1 TRAINING
Prior to acceptance by the Government, provide comprehensive training for the systems and equipment specified in the technical specifications. The training must be targeted for the Hatchery Manager and building maintenance personnel. Instructors must be well-versed in the particular systems that they are presenting. Address aspects of the Operation and Maintenance Manual submitted in accordance with Section 01 78 00 CLOSEOUT SUBMITTALS. Training must include field lectures based on the system operating requirements.
3.1.1 Training Content
The core of this training must be based on manufacturer's recommendations and the operation and maintenance information. Spend 95 percent of the instruction time during the presentation on the OPERATION AND MAINTENANCE DATA. Include the following for each system training presentation:
a. Start-up, normal operation, shutdown, unoccupied operation, seasonal changeover, manual operation, controls set-up and programming, troubleshooting, and alarms.
b. Relevant health and safety issues.
c. Interactions with other systems.
d. Special maintenance and replacement sources.
e. Tenant interaction issues.
SECTION 01 78 23 Page 4 of 4
3.1.2 Unresolved Questions from Attendees
If, at the end of the training course, there are questions from attendees that remain unresolved, the instructor must send the answers, in writing, to the Contracting Officer for transmittal to the attendees.
3.1.3 Validation of Training Completion
Ensure that each attendee at each training session signs a class roster daily to confirm Government participation in the training. At the completion of training, submit a signed validation letter that includes a sample record of training for reporting what systems were included in the training, who provided the training, when and where the training was performed, and copies of the signed class rosters.
This is the start of the file's text. The full file is on GovTribe.