About this file
This is an Amendment of Solicitation/Modification of Contract (Standard Form 30) for Fish and Wildlife Service (FWS) under the General Services Administration (GSA). The amendment extends the quote submission deadline for Solicitation No. 140FGA26Q0041 to July 22, 2026 at 12:00 p.m. Eastern time, with a period of performance from August 1, 2026 to October 15, 2026. The contracting office is located at 5275 Leesburg Pike, Falls Church, VA 22041, with Sanford Carson as the named contracting officer.
The solicitation involves material delivery and road spreading services, specifically requiring tailgate spreading of aggregate material to a 4-inch depth along road surfaces. Contractors must estimate quantities based on approximately 1,370 tons per mile for uncompacted 1-inch minus material or 1,740 tons per mile if compacted. Material will be delivered loose and compacted by station personnel, with grading and rolling completed by Refuge staff. The government assumes responsibility for road closures and traffic control; no contractor flagging or signage is required. Bonding requirements follow federal thresholds: no bond for projects under $35,000; payment bond required (performance bond optional) for $35,000-$150,000; and both performance and payment bonds required at 100% of contract price for awards exceeding $150,000. No liquidated damages apply to this project, and labor rate reporting is not expected unless the award exceeds approximately $350,000. The project is not tax exempt. All other terms and conditions of the original solicitation remain unchanged.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amedment_2_mingo_0002.pdf | ||
| Sol_140FGA26Q0041_Amd_0002.pdf | ||
| Amedment_1_mingo_0001.pdf | ||
| B03_WageDetermination_MO20260001.pdf | ||
| Sol_140FGA26Q0041.pdf | ||
| B08_SOW__final.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: is not is required copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7.ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
PAGESOF
Contractor
The hour and date specified for receipt of Offers to sign this document and return
Sanford Carson
See continuation page
FWS GAOA
FWS, GAOA
5275 Leesburg Pike Falls Church VA 22041
FGA
140FGA26Q0041
07/16/2026
07/02/2026
1 5
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
140FGA26Q0041/0001
This amendment extends the due date for the submission of quotes under Solicitation No.
140FGA26Q0041 to July 22, 2026 at 12:00 p.m.
eastern. A compiled list of vendor questions and corresponding Government answers will be issued concurrently with this amendment and included as an official attachment. All other terms and conditions of the solicitation remain unchanged.
Period of Performance: 08/01/2026 to
10/15/2026
Solicitation Clarifications and Requirements Material Spreading and Manipulation The solicitation specifies that tailgate spreading to a depth of 4 inches must be applied along the entire road surface. This requirement implies that additional material manipulation is necessary after the material leaves the delivery trucks. Typically, tailgate spreading alone does not provide an even coverage, and further manipulation is needed to achieve uniformity. Refuge staff will be working behind the deliveries to ensure the material is properly worked and distributed across the road.
Contouring and Drainage If material manipulation is required, spreading the material to match the existing contour of the road is considered sufficient. For example, if the road currently has a center crown for drainage, this crown will be preserved only to the extent that an additional 4 inches of material allows. If there is no existing crown or drainage feature, none will be created during the spreading process. As a result, the graded road may not provide drainage improvements beyond what already exists. Refuge staff will work the material to achieve the desired grades and slopes.
Road Closure and Traffic Control The solicitation states that the government will be responsible for road closures as needed.
This indicates that no flagging or signage will be required from the contractor during the execution of the award. Roads will be closed to traffic to facilitate the work.
Bonding Requirements The solicitation appears to be issued as a construction project rather than an order for supplies. While no performance bond requirement was found, clarification is provided as follows:
• $0–$35,000: No payment or performance bond required.
• $35,000–$150,000: Payment bond required; performance bond is not required unless the Contracting Officer decides otherwise.
• Above $150,000: Both performance and payment bonds are required, typically at 100% of the contract price.
Labor Rate Reporting Labor rates have been included. Assuming the award does not exceed the minimum threshold for required labor rate reporting (believed to be approximately $350,000), no labor rates paid reporting will be required. If labor rate reporting is required, details will be provided by the government regarding the type of reporting necessary for compliance verification.
• Service Contract Labor Standards (SCLS): No labor rate reporting is required unless specifically requested by the government. Contractors must follow the wage determination and maintain payroll records.
• Davis-Bacon Act (Construction): If applicable, certified payrolls (Form WH-347) and weekly statements of compliance are required.
• For this solicitation, no labor rate reporting is expected beyond standard compliance with the applicable wage determination. If reporting becomes necessary, the government will notify the contractor and provide the required forms and instructions.
Tax Status This project is not tax exempt.
Material Quantities and Compaction The estimated tons per mile provided in the solicitation are insufficient. For a 4-inch uncompacted layer, approximately 1,370 tons per mile are needed. If compacted, the requirement increases to about 1,740 tons per mile. Contractors should estimate the quantity of aggregate based on 4 inches of compacted 1-inch minus material.
The material is expected to be delivered loose and will be compacted by station personnel.
Grading and rolling of the rock after tailgating will be completed by Refuge staff. Any grading to the existing roadway prior to placing the 4-inch layer will also be handled by Refuge staff.
Liquidated Damages There are no liquidated damages for this project.
Bid Due Date The bid due date has been extended to July 22nd at 12 PM Eastern time.
| Amendment of solicitation/modification of contract |
| Contract ID code |
| Amendment/modification number |
| Effective date |
| Requisition/purchase requisition number |
| Project number |
| Issued by |
| Code |
| Administered by |
| Code |
| Name and address of contractor |
| Code |
| Facility code |
| Amendment of solicitation number |
| Dated |
| Modification of contract/order number |
| Dated |
| This item only applies to amendments of solicitations |
| Accounting and appropriation data |
| This item applies only to modifications of contracts/orders. |
| This change order is issued pursuant to: |
| The above numbered contract/order is modified to reflect the administrative changes |
| This supplemental agreement is entered into pursuant to authority of: |
| Other |
| Important: |
| Description of amendment/modification |
| Name and title of signer |
| Contractor/offeror |
| Date signed |
| Name and title of contracting officer |
| Signature of Contracting Officer |
| Date signed |
| Previous edition unusable |
| Standard form 30 (rev. 11/2016) |
| Continuation sheet |
| Reference Number |
| Name of Offeror or Contractor |
| OPTIONAL FORM 336 (4-86)) |
Sponsored by GSA FAR (48 CFR) 53.110
| Material Spreading and Manipulation |
| Contouring and Drainage |
| Road Closure and Traffic Control |
| Bonding Requirements |
| Labor Rate Reporting |
| Tax Status |
| Material Quantities and Compaction |
| Liquidated Damages |
| Bid Due Date |
File details come from the government source that posted it. Updated .