- Mold remediation, Merritt Island NWR
- Solicitation number
- 140FF027Q0053
- Issued by
- Not on record
About this file
This is Amendment 0002 to a federal solicitation for mold remediation services at Merritt Island National Wildlife Refuge (NWR), issued by the Fish and Wildlife Service (FWS), SAT Team 3, located in Falls Church, Virginia. The solicitation number is 140FF027Q0053, with an effective date of October 29, 2026. The amendment addresses industry concerns and includes a February 2012 Comprehensive Asbestos Survey as Attachment 6. A supplemental asbestos inspection report will be provided in a subsequent amendment before intrusive work begins. The offer closing date remains Monday, November 16, 2026, at 2:00 PM. The contract point of contact is Fred Riley (Fred_riley@ios.doi.gov), and the technical point of contact is Keith Ramos at (321) 861-2278.
The amendment includes a Questions and Answers section clarifying key requirements. Offerors must price work strictly according to the Performance Work Statement (PWS), including cleaning and remediation of retained attic roof decking and removal and disposal of contaminated conference-room flex-duct branch, while excluding roof-deck removal, replacement, and flex-duct replacement. The contractor must maintain insurance throughout performance, including Workers' Compensation at statutory limits, Employer's Liability of not less than $100,000, Commercial General Liability of not less than $500,000 per occurrence for bodily injury, Automobile Liability of not less than $200,000 per person and $500,000 per occurrence for bodily injury with $20,000 per occurrence for property damage, and Contractor's Pollution Liability including mold-related operations (required limit to be inserted by the Contracting Officer). Insurance evidence must be provided before commencing work, with required coverage extending to subcontractors consistent with FAR 52.228-5. All other terms and conditions of the original solicitation remain unchanged.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: is not is required copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7.ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PAGE
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
PAGESOF
Contractor
The hour and date specified for receipt of Offers to sign this document and return
Fred Riley
See continuation page
FWS, SAT Team 3 5275 Leesburg Pike Falls Church VA 22041
FSE
140FF027Q0053
10/29/2026
10/29/2026
1 4
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGES
NAME OF OFFEROR OR CONTRACTOR
SUPPLIES/SERVICES
(B)
UNIT
(D)
UNIT PRICE
(E)
AMOUNT
(F)
OPTIONAL FORM 336 (4-86)
Sponsored by GSA FAR (48 CFR) 53.110
ITEM NO.
(A)
QUANTITY
(C)
NSN 7540-01-152-8067
140FF027Q0053/0002
Amendment 0002 is necessary to address concerns posed from industry and include Attachment 6-
Asbestos test report from 2012. A supplemental asbestos test will be scheduled soon, and the results will be included in another Amendment to the solicitation.
Closing remains Monday, November 16, 2026, at
2:00pm.
All other terms and conditions remain unchanged.
Mold remediation, Merritt Island NWR
Tech POC Name/#: Keith Ramos (321) 861-2278
Contract POC: Fred Riley, Fred_riley@ios.doi.gov
Questions and Answers
Question 1: PWS Section 4.3 says an asbestos inspection report would be provided before the solicitation. It is not among the posted attachments. Can you provide it, or confirm none exists?
Answer 1: The Government has located a February 2012 Comprehensive Asbestos Survey that includes the project facility, identified as the Fire Cache/Administrative Building. The survey will be provided as an attachment to the solicitation amendment.
Because the 2012 survey does not address every material anticipated to be disturbed under the current mold-remediation scope, the Government will also obtain a supplemental, affected-area asbestos inspection. The supplemental report will be provided to the Contractor before intrusive work begins.
Offerors shall not include asbestos inspection, testing, or abatement in their proposed prices. If the supplemental inspection identifies asbestos-containing material that affects the scope, schedule, or performance requirements, the Government will address it through an appropriate solicitation amendment or contract modification before the affected material is disturbed.
Question 2: Insurance: PWS Section 10 states that insurance requirements will be established in the solicitation. Please provide the required coverages and minimum limits.
Answer 2: The Contractor shall maintain the following insurance throughout contract performance:
1. Workers’ Compensation: Statutory limits required by applicable Federal and Florida law.
2. Employer’s Liability: Not less than $100,000.
3. Commercial General Liability: Not less than $500,000 per occurrence for bodily injury.
4. Automobile Liability for vehicles used in contract performance: Not less than $200,000 per person and $500,000 per occurrence for bodily injury, and $20,000 per occurrence for property damage.
5. Contractor’s Pollution Liability, including mold-related operations: [CO INSERT
REQUIRED LIMIT].
The Contractor shall provide evidence of the required insurance before commencing work. Required coverage shall apply to subcontractors performing work on the Government installation, consistent with FAR 52.228-5.
Question 3: The Bio Pro assessment report recommends removal of affected attic roof decking and replacement of the conference-room flex duct. The PWS excludes both (cleaning of decking only; flex duct removal only). Please confirm that offerors should price strictly to the PWS.
Answer 3: Confirmed. Offerors shall price the work expressly defined by the PWS. The base scope includes cleaning and remediation of retained attic roof decking and removal and disposal of the identified contaminated conference-room flex-duct branch.
Roof-deck removal or replacement and flex-duct replacement are excluded.
The assessment report documents existing conditions and informs the remediation protocol, but it does not add reconstruction or replacement work expressly excluded by the PWS. If roof decking cannot be successfully remediated, or additional replacement work is determined necessary, the condition shall be documented and referred to the Government for separate action. No excluded work may be performed without written authorization from the Contracting Officer.
| Amendment of solicitation/modification of contract |
| Contract ID code |
| Amendment/modification number |
| Effective date |
| Requisition/purchase requisition number |
| Project number |
| Issued by |
| Code |
| Administered by |
| Code |
| Name and address of contractor |
| Code |
| Facility code |
| Amendment of solicitation number |
| Dated |
| Modification of contract/order number |
| Dated |
| This item only applies to amendments of solicitations |
| Accounting and appropriation data |
| This item applies only to modifications of contracts/orders. |
| This change order is issued pursuant to: |
| The above numbered contract/order is modified to reflect the administrative changes |
| This supplemental agreement is entered into pursuant to authority of: |
| Other |
| Important: |
| Description of amendment/modification |
| Name and title of signer |
| Contractor/offeror |
| Date signed |
| Name and title of contracting officer |
| Signature of Contracting Officer |
| Date signed |
| Previous edition unusable |
| Standard form 30 (rev. 11/2016) |
| Continuation sheet |