Attch1_A04_SOW_WarmSpringsPaint-Flooring_261103_5pp_Redacted.pdf
PDF 142 KB Posted
- Attached to
- OR WARM SPRINGS QTRS 4 PAINT/FLOORING
- Solicitation number
- 140FF027Q0038
- Issued by
- Not on record
About this file
RFQ 140FF027Q0038 – Interior Painting and Laminate Flooring Installation
This is a Request for Quotation (RFQ) issued by the U.S. Fish and Wildlife Service (FWS) for interior painting and laminate flooring installation at Quarters #4, Warm Springs National Fish Hatchery, located at 1 Fish Hatchery Road, Warm Springs, Oregon. The residence is approximately 2,500 square feet with three bedrooms, two bathrooms, kitchen, living room, dining room, closets, hallways, stairways, and basement. The performance period runs from January 19, 2027 through February 19, 2027, with normal working hours Monday through Friday, 8:00 a.m. to 3:30 p.m. A mandatory site visit is scheduled for November 10, 2026, at 12:00 p.m. (PST).
The interior painting scope includes preparation, priming, and application of Benjamin Moore low-VOC paint or approved equal to walls, ceilings, doors, trim, closets, hallways, stairwell, bathrooms, basement areas, and cold air returns. Walls and ceilings require eggshell finish, while doors and trim require semi-gloss finish. Bathroom areas require mold- and mildew-resistant primer. The laminate flooring installation scope requires removal of existing carpet and installation of Pergo waterproof and pet scratch-resistant laminate flooring or approved equal in the living room, dining room, hallway, hallway closets, entryway, stairs, and downstairs landing area, including installation of stair nosing, transition strips, new baseboards where necessary, and trim accessories. The contractor must furnish all labor, materials, equipment, supervision, transportation, and disposal services; comply with applicable Federal, State, and local codes; maintain a safe work environment; and provide a one-year workmanship warranty from the date of Government acceptance. All paint colors and flooring finishes require approval by the Contracting Officer's Representative prior to application or installation.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 140FF027Q0038_TermsConditions_B-M_31pp.pdf | ||
| Attch2_Photos_8pp.docx | DOCX document | |
| Attch4_BidSchedule_1p.docx | DOCX document | |
| Sol_140FF027Q0038.pdf | ||
| Attch3_DBA_OR-20260009_5pp.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFQ
140FF027Q0038
FWS OR-Warm Springs National Fish Hatchery Quarters #4
Painting and Flooring Installation
STATEMENT OF WORK
1. Description of Work
The Contractor shall furnish all labor, materials, equipment, supervision, transportation, and disposal services necessary to complete interior painting and laminate flooring installation at Quarters #4, Warm Springs National Fish Hatchery, 1 Fish Hatchery Road, Warm Springs, Oregon.
All work shall be completed in a professional manner and in accordance with applicable Federal, State, and local codes and manufacturer recommendations.
The residence is approximately 2,500 square feet and consists of three bedrooms, two bathrooms, kitchen, living room, dining room, closets, hallways, stairways, and basement.
Offerors are responsible for verifying dimensions, quantities, and site conditions necessary to prepare their quotation.
2. Interior Painting
The Contractor shall furnish all labor, materials, and supplies necessary to prepare and paint the interior of Quarters #4.
The work includes painting of:
• Walls
• Ceilings
• Doors
• Trim
• Closets
• Hallways
• Stairwell
• Bathrooms
• Basement areas
• Cold air returns
The Contractor shall:
1. Prepare surfaces as necessary to achieve a professional finish, including patching holes and cracks, sanding, caulking, and cleaning.
2. Remove nails, hooks, and similar hardware not required to remain.
3. Protect flooring, fixtures, appliances, windows, smoke detectors, HVAC vents, and other adjacent surfaces from damage or paint overspray.
4. Prime repaired or stained surfaces as necessary to achieve a uniform finish.
5. Apply Benjamin Moore low-VOC paint or approved equal.
6. Paint walls and ceilings with eggshell finish.
7. Paint doors and trim with semi-gloss finish.
8. Apply mold- and mildew-resistant primer in bathroom areas.
9. Remove debris daily and maintain a clean work area throughout the project.
10. Perform final cleanup upon completion of all work.
All paint colors shall be approved by the Contracting Officer's Representative (COR) prior to application.
3. Laminate Flooring Installation
The Contractor shall furnish all labor, materials, equipment, supervision, and disposal services necessary to remove existing carpet and install laminate flooring in the following areas:
• Living room
• Dining room
• Hallway
• Hallway closets
• Entryway
• Stairs
• Downstairs landing area
The flooring shall be Pergo waterproof and pet scratch resistant laminate flooring or approved equal.
1. Remove and dispose of existing carpet, carpet padding, tack strips, and related materials.
2. Prepare the subfloor as necessary for installation, including removal of nails, staples, and minor surface irregularities.
3. Install laminate flooring in accordance with the manufacturer's recommendations.
4. Install required stair nosing, transition strips, and trim accessories.
5. Install new baseboards where necessary to provide a finished appearance.
6. Remove debris daily and maintain a clean work area throughout the project.
7. Perform final cleanup upon completion of all work.
Flooring color and finish shall be approved by the COR prior to installation.
4. Place of Performance
Work shall be performed at:
Warm Springs National Fish Hatchery 1 Fish Hatchery Road Warm Springs, OR 97761 Quarters #4
5. Period of Performance
The period of performance shall be:
January 19, 2027 through February 19, 2027
Normal working hours are Monday through Friday, 8:00 a.m. to 3:30 p.m.
Alternative work hours may be approved by the Hatchery Manager.
6. Site Visit
A site visit will be held on:
November 10, 2026, at 12:00 p.m. (PST)
Offerors are encouraged to inspect the site and verify existing conditions before submitting a quotation.
7. Contractor Responsibilities
• Furnish all labor, materials, equipment, and supplies necessary to complete the work.
• Comply with all applicable Federal, State, and local laws and regulations.
• Obtain and pay for any required permits.
• Maintain a safe work environment.
• Remove all debris and excess materials generated by the work.
• Notify the COR of any unforeseen conditions that may affect project completion.
8. Inspection and Acceptance
The Government will inspect all work for completeness and quality.
Work will be considered acceptable when:
• Painting is complete and provides a uniform, professional appearance.
• Flooring is properly installed and free of visible defects.
• All required trim, transitions, and stair components are installed.
• All debris, materials, and equipment have been removed from the site.
• Final cleanup has been completed.
The Contractor shall correct deficiencies identified during inspection at no additional cost to the Government.
9. Safety
The Contractor shall comply with applicable OSHA safety requirements and provide necessary safety measures for employees and visitors.
Fall protection shall be used when required by applicable safety regulations.
10. Warranty
The Contractor shall provide a one-year workmanship warranty from the date of Government acceptance.
11. Government Points of Contact
Technical Representative / Site Contact
File details come from the government source that posted it. Updated .