Sol_140F0919Q0037_Amd_0002.pdf
PDF 89 KB Posted
- Attached to
- NCTC - BOUNDARY FENCE REPLACEMENT, PHASE Federal contract opportunity
- Solicitation number
- 140F0919Q0037
About this file
140F0919Q0037
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment_E_-_Site_Visit_Attendance_Sheet.pdf | ||
| Attachment_D_-_Site_Visit_Agenda.pdf | ||
| Sol_140F0919Q0037_Amd_0001.pdf | ||
| Attachment_F_-_NCTC_Fence_Option_SOW.pdf | ||
| Attachment_G_-_NCTC_Fence_Map_2019_Revised.pdf | ||
| Attachment_A_-_NCTC_Fence_SOW_2019.pdf | ||
| Attachment_C_-_Wage_Determination_2015-4285.pdf | ||
| Attachment_B_-_NCTC_Fence_Map_2019.pdf | ||
| Sol_140F0919Q0037.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
140F0919Q0037 x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
F09
Falls Church VA 22041-3803
MS: BMO
5275 Leesburg Pike
FWS, DIV OF CONTRACTING AND FA
09/04/20190002
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
08/13/2019
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of this amendment is to 1) provide a set of questions and answers, and 2) advise of the quote requirements. Accordingly:
1) The following questions and answers are provided:
Question: Does the additional 650 feet of fence get included in the original Bid?
Answer: The additional length of fence is a separate line item and is an option. The quote should include a price for the base/original line 10 and for the option line 20, and then both together are the total bid.
Question: Do you have to make the site visit to bid this project?
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
Alicia Weber
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
NSN 7540-01-152-8070
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 3
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140F0919Q0037/0002
Answer: No, attendance at the site visit is not a requirement to provide a quote.
Question: The wage determination scale does not have an ironworker or fence installer listing. As to bid this correctly what is the correct occupation code for fence replacement?
Answer: The correct wage determination has been provided, however, the Government is not specifying the labor category that needs to be used on this contract.
2) Potential offerors are advised to fully read the original synopsis that was posted on FBO.gov on August 13, 2019. Specific attention is called to the provision 52.212-2, Evaluation -
Commercial Items. This provision provides information on what is required to be submitted with a quote and how the Government will evaluate the quote. It is provided here again for emphasis:
52.212-2, Evaluation - Commercial Items (OCT
2014)
(a) The Government will award a contract resulting from this solicitation to the responsible offeror whose offer conforming to the solicitation will be most advantageous to the
Government, price and other factors considered.
The award will be made to the lowest priced, technically acceptable quote. The following factors shall be used to evaluate offerors:
1. Installation Method. The offeror shall provide a narrative describing the method that will be used in the performance of this contract.
2. Material List. The offeror shall provide a list of materials that meet the requirements of the Statement of Work and will be used in the performance of this contract
3. Past Performance. The offeror shall provide three (3) projects that reflect their past performance over the past three (3) years, and will give sufficient detail for the Government to perform an evaluation of the offeror's past performance.
(c) A written notice of award or acceptance of a quote, mailed or otherwise furnished to the successful offeror within the time for acceptance specified in the offer, shall result in a binding contract without further action by either party.
Before the offer's specified expiration time, the
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
3 3
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
140F0919Q0037/0002
Government may accept a quote (or part of an quote), whether or not there are negotiations after its receipt, unless a written notice of withdrawal is received before award.
(End of Provision)