Form IA-C713 is a Contract Progress Report template used by the Department of the Interior, Indian Affairs to document contractor work completion and progress toward contract fulfillment. The form serves as an official record for tracking work elements and their completion percentages, with columns for line number, work element description, percentage of total contract, percentage completed during the current reporting period, and cumulative percentage completed. The form includes space for contractor and address information, report number, period covered, project number, contract number, and completion date.
The form requires contractors or project managers to submit detailed progress information that may be used by the Contracting Officer to calculate progress payments according to the contract's payment clause. A designated submitter must certify that the contractor has satisfactorily completed the indicated percentage of work per contract specifications, with signature and date required. The Contracting Officer or designee must review and approve the submission with their own signature and date. The form also includes a mandatory question regarding whether payrolls have been submitted for the reporting period, with yes/no response options. This template is designed to facilitate ongoing contract administration and payment processing for Interior Department Indian Affairs contracts.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A3_-__-_DIAR_1452_280-2_Supplement.docx | DOCX document | |
| A6_SF1413_Statement_and_Acknowledgement.pdf | ||
| A7_IA_Form_C113_Progress_Schedule.pdf | ||
| A5_SF24_Bid_Bond.pdf | ||
| Sol_140A2327Q0319.pdf | ||
| A4_-_IA_-_IEE_Representation_Form.pdf | ||
| A1_-_SOW_Tohaali_Gym_Repainting.docx | DOCX document | |
| A02_-_Wage_Rates.pdf | ||
| A9_-__RFQ_Questions_and_Answers_Log.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Department of the Interior, Indian Affairs
CONTRACT PROGRESS REPORT
CONTRACTOR ADDRESS
REPORT NO. PERIOD COVERED
FROM: TO:
PROJECT NO. CONTRACT NO. COMPLETION DATE
LINE
NO.
WORK ELEMENT % OF
TOTAL
% COMPLETED
THIS PERIOD
% COMPLETED
CUMULATIVE
TOTAL
REMARKS
At the Contracting Officer's discretion and according to the payments clause of the contract, the information provided on this form may be used for computing progress payments.
PROGRESS OR COMPLETION CERTIFICATE
I hereby certify that the contractor has satisfactorily completed the indicated percentage of the contract per contract specifications.
SUBMITTED BY: _________________________
TYPE OR PRINT NAME AND TITLE SIGNATURE DATE
REVIEWED BY OR FOR CONTRACTING OFFICER
TYPE OR PRINT NAME AND TITLE SIGNATURE DATE
FORM IA-C713
Have payrolls been submitted for this time period? YES / NO