This is a Statement of Work for a construction project at the BIA Choctaw Agency in Philadelphia, Mississippi. The project involves constructing a new 40x80x14 metal equipment storage facility with 8-foot-tall sides on three sides (the fourth side remains open) to be positioned between existing Buildings 39 and 2 at 425 Hospital Street.
The contractor must provide all services, materials, labor, and installation to complete the following work: install 6-10 inches of compacted NO 57-slag material as the equipment base; grade and move material to ensure proper drainage away from the site; install 10-14 concrete pier footers (typically 26-inch diameter x 3-foot deep) with specified steel reinforcement and column specifications (W8x10 end wall columns, W12x14 intermediate columns, W6x9 breezeway columns); construct the prefabricated metal building; install a 60-amp electrical panel with one outlet per column on the west side (2 receptacles per column for battery maintenance) and eight LED high bay-lights total (2 per bay); install approximately 170 linear feet of 24-gauge prefinished commercial box gutters and four down spouts (approximately 15 feet each); and remove all debris from the site. The contractor is responsible for verifying site conditions, protecting existing utilities, providing disposal bins (approved by the Point of Contact), daily site cleanup, coordinating material staging with the POC, and working Monday-Friday 7:30 AM to 4:30 PM, with 48-hour advance approval required for weekend or after-hours work. The Point of Contact is Adam Rogers, BIA Fire Management Specialist, at Adam.Rogers@bia.gov or (706) 835-9640.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140A1626Q0084_Amd_0001.pdf | ||
| Sol_140A1626Q0084.pdf | ||
| A04_SOW02.pdf | ||
| A04_SOW01.pdf | ||
| Attachment_3_-_IEE_Reps.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Work
BIA Choctaw Agency
Fire Building 39 and 2
A. Project Information:
Project Location: Fire Building - 425 Hospital Street, building 39 and building 2, Philadelphia MS 39350. New 3 sided equipment storage facility will be set between existing building 39 and building 2.
Project Description: Project A: This project consists of constructing new large equipment storage building for Choctaw Agency Fire department. Project will consist of installing new 40x80x14 metal building with 8-foot-tall sides on three sides. Building will require pre-landscape installation of 6-10 inches of compacted NO 57-slag material for the ground coverage under the building. Installing 10-14 footers, depending on the manufacturing requirement. Install electrical panel and have electrical outlets available in each bay and install 2 shop LED lights for each bay.
B. Scope of Work:
The contractor shall provide all services, material, labor and installation required to perform the work described in this SOW, i.e. BIA Choctaw Fire building 39 and building 2 installing new 40x80x14 metal building with 8-foot-tall sides on three sides, and fourth side will remain open.
Work shall include but is not limited to the following for Appendix A:
Install 6-10 inches of compacted NO57 Slag material for equipment base of new building, material cover will tie into the existing drive.
Grade and move material to ensure proper drainage away from the project site.
Install 10-14 footers per the manufactures design, typically will be 26 inch diameter x 3-foot concrete dep piers with cold roll around re-enforcement (3/8 inch) with ½ inch uprights. The columns will weld to embeds with 2 (8” x 4”x ½” L shape) leg anchors. The end wall columns are w8 x 10 and the intermediate columns are w12 x 14. The breezeway columns are w6 x 9.
Construct a new Pre- fabricated metal building 40x80x14 with 8-foot sides on three sides
Install electrical panel 60 Amp to supply 1 outlet on each column located on west side of building with 2 receptacles per column, for battery maintenance, and install 2 LED high bay-lights per bay to make total of 8 LED lights. Power source will come either from Building 39 or building 2.
Install new rain gutters and down spouts. Install approximately 170 Linear feet of 24 gauge prefinished commercial box gutters for both sides of building. Install two down spouts approximately 15 feet long on each side of newly installed gutters.
Remove all debris from site
C. Contractor responsibilities:
Contractor shall verify all site conditions, quantities, measurements, and project requirements.
Contractors shall be responsible for damaging any existing utilities while digging/grading work areas. Contractor must make sure all utilities lines are marked before project begins.
Contractor shall cleanup work site daily and dispose of all construction debris to an appropriate dumpster provided by the contractor.
D. Disposal of Materials and Cleanup:
The contractor shall provide the appropriate disposal bins/trash receptacles. Approval for the location of the disposal bins shall be coordinated through the Point of Contact (POC).
The contractor shall clean up work site daily and dispose of all debris to an appropriate bin and /or receptacle provided by the contractor. Contractor may not use any Agency/Government disposal bins, dumpsters or trash receptacles for any reason at any time.
E. Project Material Storage:
The contractor shall coordinate and get approval prior to stage of any material on project site. Contractor must coordinate with POC for location of staging material for storage.
F. General Requirements:
Work hour: Monday-Friday 7:30AM – 4:30 pm. Coordinate work hours with POC, Mr.
Adam Rogers. If weekend work or after hours is required, the contractor shall coordinate with the POC and request approval 48 hours in advance.
G. Pont of Contact:
POC- Adam Rogers, BIA Fire Management Specialist
BIA Choctaw Agency
421 Powell Street
Philadelphia, MS 39350
Adam.Rogers@bia.gov
Cell (706) 835-9640 mailto:Adam.Rogers@bia.gov
PlAN NORTH l<tlt �•.,• $Q'.AAE; fW:>:m- Tfi'lCOl. l<H'l>«S P\leT Om:, IJ< !>Jl.CINO CO'iJAAC!�
+ J
MElAL STORAGE CONTAINER 8' >< 40' v V V J·
I
V -·- ' ✓
EXISTING BUILDING
24' X 30' I v ✓ /, ?
,y V v v
,, V ,,,_" ,f r
111"-0' 0.1< COOR v -v +
SITE PLAN
SCALE: 3/16",,,,1'-0"
METAL STORAGE" CONTAINER
a· x 40'
EXISTING WAREHOUSE
I
| A. Project Information: |
| B. Scope of Work: |
| C. Contractor responsibilities: |
| D. Disposal of Materials and Cleanup: |
| E. Project Material Storage: |
| F. General Requirements: |
| G. Pont of Contact: |