H52-32-85_FCA_REPORT_0002.pdf
PDF 4 MB Posted
- Attached to
- WHITE MOUNTAIN APACHE ADULT DETENTION - WALL REPAI Federal contract opportunity
- Solicitation number
- 140A1125B0001
About this file
This document is a Facility Condition Assessment (FCA) report for Structure 85 at the White Mountain Apache Department of Corrections, conducted by Keres | Faithful+Gould for the Bureau of Indian Affairs. The assessment, performed on August 20, 2018, evaluated the facility's physical condition and identified capital expenditure needs over a 10-year period.
The report reveals a total anticipated capital expenditure of $754,772, with $564,443 in immediate (Year 0) needs and $190,329 in future (Years 1-10) needs. Key immediate priorities include replacing the built-up roof ($308,423), addressing security surveillance systems ($93,810), and replacing commercial kitchen equipment ($147,210). The facility's Facility Condition Needs Index (FCNI) is 9.58%, indicating the building is in fair condition with some systems nearing the end of their useful life. Recommended repairs span multiple building systems, including exterior walls, interior finishes, plumbing, electrical systems, and detention equipment, with most critical replacements scheduled for 2019 and 2024.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140A1125B0001_Amd_0003.pdf | ||
| Sol_140A1125B0001_Amd_0002.pdf | ||
| Photo_of_Door_0002.pdf | ||
| WMAT_Detention_Adult___Juvenile_1_15_08_0002.pdf | ||
| White_Mountain_ApacheDetention_Facility_Exterior_Repairs_-SOW_5_19_25_0001.pdf | ||
| Sol_140A1125B0001_Amd_0001.pdf | ||
| Wage_Determination_AZ20250027_02142025.pdf | ||
| Questions_and_Answers_Log.xlsx | XLSX spreadsheet | |
| SOW.pdf | ||
| Sol_140A1125B0001.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Facility Condition Assessment Services
Tier 2 Report of
Facility Condition Assessment
For
Structure - 85 White Mountain Apache Department of Corrections Location #: H52-32
Date of Report:
Date of Assessment:
Provided By:
Keres | Faithful+Gould
Provided For:
Bureau of Indian Affairs
DFMC
Albuquerque, NM 87104
October 10, 2019
August 20, 2018
85 October 10, 2019
Executive Summary Introduction Limiting Conditions Project Details Assessor/Participant Names Building Details Facility Condition Needs Index Summary of Findings Building Expenditure Summary Distribution of Immediate (Year 0) Needs by Building System Distribution of Future (Year 1-Year 10) Needs by Building System Needs Sorted by Prioritization of Work Needs Sorted by Plan Type
Introduction
In accordance with the purchase order contract held between the Bureau of Indian Affairs and Keres | Faithful+Gould, this completed report provides a comprehensive Facility Condition Assessment of Structure - 85 located at White Mountain Apache Department of Corrections, H52-32 (The Property). This report has been prepared for the exclusive and sole use of the Bureau of Indian Affairs.
This report provides a summary of the facility information known to us at the time of the study, the scope of work performed, an equipment inventory, evaluation of the visually apparent condition of the Property together with a forecast of capital expenditures anticipated over the next 10 years. The expenditure forecast does not account for typical preventative maintenance items such as changing filters to fan coil units.
Our cost rates to produce life cycle and replacement cost estimates are based on our knowledge of the local regional market rates. The data in this report represent an opinion of probable cost of construction and is made on the basis of the experience, qualifications, and best judgment of the professional consultant familiar with the construction industry.
The report provides a summary of the anticipated primary expenditures over the 10-year study period. Further details of these expenditures are included within each respective report section and within the deficiency report, in Appendix A.
In this report we have calculated the Facility Condition Needs Index (FCNI) which is used in Facilities Management to provide a benchmark to compare the relative condition of a group of facilities. The FCNI is primarily used to support asset management initiatives of federal, state, and local government facilities organizations.
Executive Summary
Limiting Conditions
Project Details
On August 20, 2018, Keres | Faithful+Gould visited the Property to observe and document the condition of the building and site components.
Assessor/Participant Names
Participant Names
Assessor(s) Jake Stauffer
Building Details
Items Description
Site Description White Mountain Apache Department of Corrections
Structure Number 85
Property Type Building
Year Built 2010
Gross Building Area (GSF) 29,490
Floor(s) 2
Current Replacement Value (CRV) $5,892,415
CRV/GSF ($/Sq Ft) $200
Facility Condition Needs Index
FCNI =
Deferred Maintenance + Capital Renewal + Plant Adaptation (TC)
Current Replacement Value of the Facility(s) (CRV)
If the FCNI rating is 60% or greater then replacement of the asset/building should be considered instead of renewal.
Condition Definition Percentage Value
GOOD In a new or well-maintained condition, with no visual evidence of wear, soiling or other deficiencies. 0% to 5%
FAIR Subject to wear and soiling but is still in a serviceable and functioning condition. 5% to 10%
POOR Subjected to hard or long-term wear. Nearing the end of its useful or serviceable life. Greater than 10%
V-POOR Subjected to hard or long-term wear. Has reached the end of its useful or serviceable life. Renewal now necessary. Greater than 60%
Current FCI
85, FCNI: 9.58%
The Chart below indicates the cumulative effects of the FCNI ratio over the study period assuming the required funds and expenditures are NOT provided to address the identified works and deferred maintenance each year.
Year by Year Effects of FCNI Over the Study Period
0.00 %
1.00 %
2.00 %
3.00 %
4.00 %
5.00 %
6.00 %
7.00 %
8.00 %
9.00 %
10.00 %
11.00 %
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028
9.58 % 0.00 % 0.00 % 0.00 % 0.00 % 1.55 % 0.00 % 0.08 % 1.60 % 0.00 %
The chart below indicates the effects of the FCNI ratio per year, assuming the required funds and expenditures ARE made to address the identified actions each year.
Cumulative Effects of FCNI Over the Study Period
9.00 %
10.00 %
11.00 %
12.00 %
13.00 %
14.00 %
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028
9.58 % 9.58 % 9.58 % 9.58 % 9.58 % 11.13 % 11.13 % 11.21 % 12.81 % 12.81 %
Summary of Findings
This report represents summary-level findings for the Property Condition Assessment. The deficiencies identified in this assessment can be combined with potential new construction requirements to develop an overall Long-Term Capital Needs Plan that can be the basis for a facility wide capital improvement funding strategy. Key findings from the Assessment include:
Key Findings Metric
Current Year Facility Condition Needs Index 9.58 %
Immediate Capital Needs (Year 1) (included in FCNI) $564,443
Future Capital Needs (Year 2 to Year 10) $190,329
Total Capital Needs $754,772
1. All costs presented in present day values
2. Expenditures in excess of $5000 are included in the Key Findings list
3. Costs represent total anticipated values over the 10 year study period
4. Budget for additional project costs of between 25% - 30% to allow for professional fees and general contractor overhead/profit and management costs
Key Findings
B Shell: Replace B3011 Built-up Roof at an estimated cost of $308,423 in year 2019
B Shell: Engineering study to address severe settling and cracking throughout exterior masonry wall system. at an estimated cost of $15,000 in year 2019
C Interiors: Replace C3032 Ceiling Finish, ACT, Standard at an estimated cost of $86,673 in year 2027
D Services: Replace D5038 Security, Surveillance, Extensive at an estimated cost of $93,810 in year 2019
D Services: Replace D2018 Drinking Fountains, Refrigerated at an estimated cost of $14,835 in year 2024
D Services: Replace D2023 Water Heater, Gas, Non-condensing, 120 Gal at an estimated cost of $13,211 in year
D Services: Replace D2023 Water Heater, Gas, Non-condensing, 120 Gal at an estimated cost of $13,211 in year
D Services: Replace D2023 Water Heater, Gas, Non-condensing, 120 Gal at an estimated cost of $13,211 in year
D Services: Replace D2023 Water Heater, Gas, Non-condensing, 120 Gal at an estimated cost of $13,211 in year
D Services: Replace D5092 Emergency Power, Uninterruptible Power Supply (UPS) at an estimated cost of $12,095 in year 2024
D Services: Replace D3042 Kitchen Exhaust Hood, Commercial at an estimated cost of $7,630 in year 2027
E Equipment & Furnishing: Replace E1093 Commercial Kitchen, Equipment, Large, >500SF, (SF - Kitchen incl.
Dishwasher, Walk-in Freezer/Cooler Area) at an estimated cost of $147,210 in year 2019
E Equipment & Furnishing: Replace E1026 Shower, Institutional Grade, Package for Built-in, Detention Center, Replace at an estimated cost of $11,691 in year 2024
Building Expenditure Summary
The building expenditure summary section provides an executive overview of the findings from the assessment. The chart below provides a summary of yearly anticipated expenditures over the study period for the 85 building. Further details of these expenditures are included within each respective report section and within the expenditure forecast, in Appendix A of this report. The results illustrate a total anticipated expenditure over the study period of approximately $754,772.
Expenditure Forecast Over Study Period
$0.00K
$100.00K
$200.00K
$300.00K
$400.00K
$500.00K
$600.00K
$700.00K
EX
PE
N D
IT
U
R E
2019 2020 2021 2022 2023 2024 2025 2026 2027 2028
$564.44K $0.00K $0.00K $0.00K $0.00K $91.47K $0.00K $4.56K $94.30K $0.00K
Distribution of Immediate (Year 0) Needs by Building System
Building System Estimated Cost Percentage of Total Cost
Exterior Wall Construction $15,000 2.66 %
Food Service Equipment $147,210 26.08 %
Roof Finishes $308,423 54.64 %
Security and Detection Systems $93,810 16.62 %
Total $564,443 100 %
Distribution of Immediate Needs by Building System
Exterior Wall Construction Roof Finishes
Food Service Equipment Security and Detection Systems
Distribution of Future (Year 1-Year 10) Needs by Building System
Distribution of Capital Needs by Building System
C30 Interior Finishes D50 Electrical Systems
D20 Plumbing E10 Equipment
D30 HVAC
Building System Estimated Cost Percentage of Total Cost
C30 Interior Finishes $91,233 47.93 %
D20 Plumbing $67,681 35.56 %
D30 HVAC $7,630 4.01 %
D50 Electrical Systems $12,095 6.35 %
E10 Equipment $11,691 6.14 %
Total $190,329 100 %
Needs Sorted by Prioritization of Work
Keres | Faithful+Gould has prioritized the identified work in order to assist with analyzing the deficiencies found during the assessment. The baseline prioritization model is not just based on replacement year or criticality but uses four key data attributes to build an overall importance metric for every recommendation: System type, the cause or nature of the issue, timing and building mission incorporated into the model with relative weighting to provide an overall priority score. Priority categories are shown below:
Priority 1 Currently Critical
Systems requiring immediate action that have failed, compromises staff or public safety or requires to be upgraded to comply with current codes and accessibility
Priority 2 Potentially Critical
A system or component is nearing end of useful life, if not addressed will cause additional deterioration and added repair costs
Priority 3 Necessary / Not Critical
Lifecycle replacements necessary but not critical or mid-term future replacements to maintain the integrity of the facility or component
Planning Horizon Needs by System and Priority
B Shell C Interiors
D Services E Equipment & Furnishing
Priority
$0
$100,000
$200,000
$300,000
$400,000
Ex pe nd itu re in
D ol la rs
Priority 1
Priority 2
Priority 3
Building System Priority 1 Priority 2 Priority 3 Total
B Shell $15,000 $308,423 $0 $323,423
C Interiors $0 $0 $91,233 $91,233
D Services $105,905 $0 $75,310 $181,215
E Equipment & Furnishing $0 $147,210 $11,691 $158,901
Total $120,905 $455,633 $178,234 $754,772
The chart below illustrates the breakdown of expenditure according the priority coding providing an opportunity to strategically plan and effectively direct funding to the highest priority.
Needs Sorted by Plan Type
Keres | Faithful+Gould has prioritized the identified work according to the Plan Type or deficiency categories in order to assist with analyzing the deficiencies found during the assessment. The following Plan Types are shown below:
The chart below illustrates the breakdown of expenditure according to the Plan Type or deficiency categories providing an opportunity to strategically plan and effectively direct funding.
Plan Type 1 Capital Renewal
Indicates the need for replacement or major refurbishment of an asset, typically based on age and use but required in the future within a reasonable planning horizon.
Plan Type 2 Deferred Maintenance
Indicates a deficiency or a conditional, performance, or failure related issue with an elemental component that has persisted past a reasonable time frame and should have been remedied prior to the time of assessment.
Plan Type 3 Routine Maintenance
Indicates the need for normal or ongoing minor component renewal or repair, generally required to sustain the anticipated lifecycle of the asset.
Plan Type 4 Plant Adaptation
Indicates the need for alterations to the property for improvement in safety and security, ADA, hazardous materials abatement, green roof and LEED requirements.
Building System Total Cost
Capital Renewal $190,329
Work Order $564,443
Total $754,772
Planning Horizon Needs by Category
Capital Renewal Work Order
Plan Type
$100,000
$200,000
$300,000
$400,000
$500,000
$600,000
$700,000
Ex pe nd itu re in
D ol la rs
A - SubStructure A10 - Foundations A20 - Basement Construction
B - Shell B10 - SuperStructure B20 - Exterior Enclosure B30 - Roofing
C - Interiors C10 - Interior Construction C20 - Stairs C30 - Interior Finishes
D - Services D10 - Conveying Systems D20 - Plumbing
D30 - HVAC
D40 - Fire Protection Systems D50 - Electrical Systems
E - Equipment & Furnishing E10 - Equipment E20 - Furnishings
F - Special Construction And Demolition F10 - Special Construction F20 - Selective Demolition
G - Building Sitework G10 - Site Preparation G20 - Site Improvements G30 - Site Civil/Mechanical Utilities G40 - Site Electrical Utilities G90 - Other Site Construction
Z - General Z10 - General Requirements Z20 - Bidding Requirements, Contract Forms, Conditions Z90 - Project Cost Estimate
All assets observed are provided in this Section sorted by the Uniformat II coding, indexed is as follows:
AAsset Observed
Item Description
A1031 Concrete Slab-on-grade, Structural w/ integral Perimeter Footings
A1031 Concrete Slab-on-grade, Structural w/ integral Perimeter Footings
Condition Worse than age
Quantity 29,500 SF
Unit Cost $14.85
Remaining Useful Life (RUL) 42 Year(s)
A1031 Standard Slab on Grade
Item Description
B2011 Exterior Wall Construction, Masonry Cavity Wall, Architectural Block / CMU
B2011 Exterior Wall Construction, Masonry Cavity Wall, Architectural Block / CMU
Condition Worse than age
Quantity 23,500 SF
Unit Cost $32.77
Remaining Useful Life (RUL) 68 Year(s)
Uniformat Component Description Plan Type Year Expenditures
B2011 Engineering study to address severe settling and cracking throughout exterior masonry wall system. WO 2019 $15,000
Cost Recommendations:
B2011 Exterior Wall Construction
B2021 Steel Fixed Window, 2 Stories, 12 Sq Ft B2021 Steel Fixed Window, 2 Stories, 12 Sq Ft
Condition Typical for age
Quantity 73 EA
Unit Cost $718.10
Remaining Useful Life (RUL) 23 Year(s)
B20211 Windows
B3011 Built-up Roof B3011 Built-up Roof
Condition Worse than age
Quantity 29,500 SF
Unit Cost $10.46
Remaining Useful Life (RUL) 0 Year(s)
Uniformat Component Description Plan Type Year Expenditures
B3011 Replace B3011 Built-up Roof WO 2019 $308,423
B30111 Rooff Finishes
C1011 Interior Partitions, GWB on Studs C1011 Interior Partitions, GWB on Studs
Condition Typical for age
Quantity 16,750 SF
Unit Cost $4.69
Remaining Useful Life (RUL) 43 Year(s)
C10111 Fixedd Partitions
C2011 Metal, Painted, Interior Stairs C2011 Metal, Painted, Interior Stairs
Condition Typical for age
Quantity 600 SF
Unit Cost $35.88
Remaining Useful Life (RUL) 68 Year(s)
C20111 Regularr Stairs
Item Description
C3024 Floor Finish, Vinyl Composition Tile (VCT), Average C3024 Floor Finish, Vinyl Composition Tile (VCT), Average
Condition Typical for age
Quantity 1,500 SF
Unit Cost $3.04
Remaining Useful Life (RUL) 7 Year(s)
Uniformat Component Description Plan Type Year Expenditures
C3024 Replace C3024 Floor Finish, Vinyl Composition Tile (VCT), Average CR 2026 $4,560
C30244 Flooring
C3032 Ceiling Finish, ACT, Standard C3032 Ceiling Finish, ACT, Standard
Condition Typical for age
Quantity 16,700 SF
Unit Cost $5.19
Remaining Useful Life (RUL) 8 Year(s)
Uniformat Component Description Plan Type Year Expenditures
C3032 Replace C3032 Ceiling Finish, ACT, Standard CR 2027 $86,673
C30322 Suspendedd Ceilings
D2011 Tankless Water Closet D2011 Tankless Water Closet
Condition Typical for age
Quantity 8 EA
Unit Cost $643.39
Remaining Useful Life (RUL) 27 Year(s)
D20111 Waterr Closets
D2012 Urinal, Vitreous China D2012 Urinal, Vitreous China
Condition Typical for age
Quantity 1 EA
Unit Cost $888.54
Remaining Useful Life (RUL) 27 Year(s)
D20122 Urinals
D2013 Lavatory, Vitreous China D2013 Lavatory, Vitreous China
Condition Typical for age
Quantity 6 EA
Unit Cost $468.21
Remaining Useful Life (RUL) 27 Year(s)
D20133 Lavatories
Item Description
D2014 Sinks, Utility, Plastic D2014 Sinks, Utility, Plastic
Condition Typical for age
Quantity 3 EA
Unit Cost $1,709.73
Remaining Useful Life (RUL) 23 Year(s)
D20144 Sinks
D2018 Drinking Fountains, Refrigerated D2018 Drinking Fountains, Refrigerated
Condition Typical for age
Quantity 15 EA
Unit Cost $988.98
Remaining Useful Life (RUL) 5 Year(s)
Uniformat Component Description Plan Type Year Expenditures
D2018 Replace D2018 Drinking Fountains, Refrigerated CR 2024 $14,835
D20188 Drinkingg Fountainss andd Coolers
D2023 Water Heater, Gas, Non-condensing, 120 Gal D2023 Water Heater, Gas, Non-condensing, 120 Gal
Condition Typical for age
Quantity 1 EA
Unit Cost $13,211.47
Remaining Useful Life (RUL) 5 Year(s)
Asset Tag N/A
Manufacturer AO Smith
Model BTR200119
Serial Number 0842M000828
Uniformat Component Description Plan Type Year Expenditures
D2023 Replace D2023 Water Heater, Gas, Non-condensing, 120 Gal CR 2024 $13,211
D2023 Domestic Water Supply Equipment
D2023 Water Heater, Gas, Non-condensing, 120 Gal D2023 Water Heater, Gas, Non-condensing, 120 Gal
Condition Typical for age
Quantity 1 EA
Unit Cost $13,211.47
Remaining Useful Life (RUL) 5 Year(s)
Asset Tag N/A
Manufacturer AO Smith
Model BTR200119
Serial Number 0842M000830
Uniformat Component Description Plan Type Year Expenditures
D2023 Replace D2023 Water Heater, Gas, Non-condensing, 120 Gal CR 2024 $13,211
D20233 Domesticc Waterr Supplyy Equipment
D2023 Water Heater, Gas, Non-condensing, 120 Gal D2023 Water Heater, Gas, Non-condensing, 120 Gal
Condition Typical for age
Quantity 1 EA
Unit Cost $13,211.47
Remaining Useful Life (RUL) 5 Year(s)
Asset Tag N/A
Manufacturer AO Smith
Model BTR200119
Serial Number 0842M000829
Uniformat Component Description Plan Type Year Expenditures
D2023 Replace D2023 Water Heater, Gas, Non-condensing, 120 Gal CR 2024 $13,211
Cost Recommendations:
D2023 Domestic Water Supply Equipment
Item Description
D2023 Water Heater, Gas, Non-condensing, 120 Gal D2023 Water Heater, Gas, Non-condensing, 120 Gal
Condition Typical for age
Quantity 1 EA
Unit Cost $13,211.47
Remaining Useful Life (RUL) 5 Year(s)
Asset Tag N/A
Manufacturer AO Smith
Model BTR200119
Serial Number 0842M000827
Uniformat Component Description Plan Type Year Expenditures
D2023 Replace D2023 Water Heater, Gas, Non-condensing, 120 Gal CR 2024 $13,211
D2023 Domestic Water Supply Equipment
D3032 Condenser, Split System, Air Cooled, XX Tons D3032 Condenser, Split System, Air Cooled, XX Tons
Condition Typical for age
Quantity 1 EA
Unit Cost $3,133
Remaining Useful Life (RUL) 10 Year(s)
Asset Tag NA
Manufacturer Carrier
Model 38MVC0123
Serial Number 0308V03333
D30322 Directt Expansionn Systems
Item Description
D3042 Exhaust Fan, Ceiling, 1,000 Cfm D3042 Exhaust Fan, Ceiling, 1,000 Cfm
Condition Typical for age
Quantity 1 EA
Unit Cost $1,095.52
Remaining Useful Life (RUL) 15 Year(s)
Asset Tag NA
Manufacturer Greenheck
Model 6B1014X
D3042 Exhaust Ventilation Systems
D3042 Exhaust Fan, Ceiling, 1,000 Cfm D3042 Exhaust Fan, Ceiling, 1,000 Cfm
Condition Typical for age
Quantity 1 EA
Unit Cost $1,095.52
Remaining Useful Life (RUL) 15 Year(s)
Asset Tag NA
Manufacturer Greenheck
Model 6B1014X
D3042 Exhaust Ventilation Systems
Item Description
D3042 Exhaust Fan, Ceiling, 1,000 Cfm D3042 Exhaust Fan, Ceiling, 1,000 Cfm
Condition Typical for age
Quantity 1 EA
Unit Cost $1,095.52
Remaining Useful Life (RUL) 15 Year(s)
Asset Tag NA
Manufacturer Greenheck
Model 6B1014X
Serial Number 114260690808
D3042 Exhaust Ventilation Systems
D3042 Exhaust Fan, Ceiling, 1,000 Cfm D3042 Exhaust Fan, Ceiling, 1,000 Cfm
Condition Typical for age
Quantity 1 EA
Unit Cost $1,095.52
Remaining Useful Life (RUL) 15 Year(s)
Asset Tag NA
Manufacturer Greenheck
Model 6B0914X
Serial Number 13447261
D30422 Exhaustt Ventilationn Systems
D3042 Kitchen Exhaust Hood, Commercial D3042 Kitchen Exhaust Hood, Commercial
Condition Typical for age
Quantity 1 EA
Unit Cost $7,629.74
Remaining Useful Life (RUL) 8 Year(s)
Uniformat Component Description Plan Type Year Expenditures
D3042 Replace D3042 Kitchen Exhaust Hood, Commercial CR 2027 $7,630
Cost Recommendations:
D30422 Exhaustt Ventilationn Systems
Item Description
D3052 Air Conditioner, Rooftop, Multizone, 8 Ton D3052 Air Conditioner, Rooftop, Multizone, 8 Ton
Condition Typical for age
Quantity 1 EA
Unit Cost $13,037.72
Remaining Useful Life (RUL) 10 Year(s)
Asset Tag AC4
Manufacturer Carrier
Model 48HJE008
D30522 Packagee Units
D3052 Air Conditioner, Rooftop, Multizone, 8 Ton D3052 Air Conditioner, Rooftop, Multizone, 8 Ton
Condition Typical for age
Quantity 1 EA
Unit Cost $13,037.72
Remaining Useful Life (RUL) 10 Year(s)
Asset Tag AC4
Manufacturer Carrier
Model 48HJE008
Serial Number 3308G40571
D3052 Package Units
Item Description
D3052 Air Conditioner, Rooftop, Multizone, 8 Ton D3052 Air Conditioner, Rooftop, Multizone, 8 Ton
Condition Typical for age
Quantity 1 EA
Unit Cost $13,037.72
Remaining Useful Life (RUL) 10 Year(s)
Asset Tag AC3
Manufacturer Carrier
Model 48HJF009651
Serial Number 2608G11984
D3052 Package Units
D3052 Air Conditioner, Rooftop, Multizone, 8 Ton D3052 Air Conditioner, Rooftop, Multizone, 8 Ton
Condition Typical for age
Quantity 1 EA
Unit Cost $13,037.72
Remaining Useful Life (RUL) 10 Year(s)
Asset Tag AC4
Manufacturer Carrier
Model 48HJE008
D3052 Package Units
Item Description
D3052 Air Conditioner, Rooftop, Multizone, 8 Ton D3052 Air Conditioner, Rooftop, Multizone, 8 Ton
Condition Typical for age
Quantity 1 EA
Unit Cost $13,037.72
Remaining Useful Life (RUL) 10 Year(s)
Asset Tag AC2 Day Room
Manufacturer Carrier
Model 48HJF007
Serial Number 3408G40267
D3052 Air Conditioner, Rooftop, Multizone, 8 Ton D3052 Air Conditioner, Rooftop, Multizone, 8 Ton
Condition Typical for age
Quantity 1 EA
Unit Cost $13,037.72
Remaining Useful Life (RUL) 10 Year(s)
Asset Tag AC10
Manufacturer Carrier
Model 48SD024040311
Serial Number 1608G21160
D3052 Package Units
Item Description
D3052 Air Conditioner, Rooftop, Multizone, 8 Ton D3052 Air Conditioner, Rooftop, Multizone, 8 Ton
Condition Typical for age
Quantity 1 EA
Unit Cost $13,037.72
Remaining Useful Life (RUL) 10 Year(s)
Asset Tag AC5
Manufacturer Carrier
Model 48HJF008Y641HS
Serial Number 2704G40813
D3052 Air Conditioner, Rooftop, Multizone, 8 Ton D3052 Air Conditioner, Rooftop, Multizone, 8 Ton
Condition Typical for age
Quantity 1 EA
Unit Cost $13,037.72
Remaining Useful Life (RUL) 10 Year(s)
Asset Tag AC5
Manufacturer Carrier
Model 48HJF008Y641HS
D3052 Package Units
Item Description
D3052 Air Conditioner, Rooftop, Multizone, 8 Ton D3052 Air Conditioner, Rooftop, Multizone, 8 Ton
Condition Typical for age
Quantity 1 EA
Unit Cost $13,037.72
Remaining Useful Life (RUL) 10 Year(s)
Asset Tag AC4
Manufacturer Carrier
Model 48HJE008
D3052 Air Conditioner, Rooftop, Multizone, 8 Ton D3052 Air Conditioner, Rooftop, Multizone, 8 Ton
Condition Typical for age
Quantity 1 EA
Unit Cost $13,037.72
Remaining Useful Life (RUL) 10 Year(s)
Asset Tag AC9 Cells Over
Manufacturer Carrier
Model 48HJE008
Serial Number 3308G40570
D30522 Packagee Units
Item Description
D3052 Air Conditioner, Rooftop, Multizone, 8 Ton D3052 Air Conditioner, Rooftop, Multizone, 8 Ton
Condition Typical for age
Quantity 1 EA
Unit Cost $13,037.72
Remaining Useful Life (RUL) 10 Year(s)
Asset Tag AC5
Manufacturer Carrier
Model 48SD024040311
Serial Number 2108G42022
D3068 Building Controls, Automation - Average D3068 Building Controls, Automation - Average
Condition Typical for age
Quantity 29,500 SF
Unit Cost $2.52
Remaining Useful Life (RUL) 10 Year(s)
D30688 Buildingg Automationn Systems
Item Description
D4012 Sprinkler System, Light Hazard, Complete D4012 Sprinkler System, Light Hazard, Complete
Condition Typical for age
Quantity 29,500 SF
Unit Cost $5.47
Remaining Useful Life (RUL) 28 Year(s)
D40122 Sprinklerr Pumpingg Equipment
D5012 Power Panel Board, 208 Y, 120 V, 225 Amp D5012 Power Panel Board, 208 Y, 120 V, 225 Amp
Condition Typical for age
Quantity 2 EA
Unit Cost $6,379.30
Remaining Useful Life (RUL) 12 Year(s)
D50122 Loww Tensionn Servicee && Dist.
Item Description
D5012 Power Panel Board, 208 Y, 120 V, 400 Amp D5012 Power Panel Board, 208 Y, 120 V, 400 Amp
Condition Typical for age
Quantity 1 EA
Unit Cost $7,601.26
Remaining Useful Life (RUL) 12 Year(s)
D50122 Loww Tensionn Servicee && Dist.
D5012 Secondary Transformer, Dry, 113 kVA D5012 Secondary Transformer, Dry, 113 kVA
Condition Typical for age
Quantity 1 EA
Unit Cost $9,542.63
D50122 Loww Tensionn Servicee && Dist.
D5022 *Lighting, Interior, Fluorescent D5022 *Lighting, Interior, Fluorescent
Condition Typical for age
Quantity 29,500 SF
Unit Cost $6.12
Remaining Useful Life (RUL) 15 Year(s)
D50222 Lightingg Equipment
Item Description
D5037 Fire Alarm System Devices - Standard D5037 Fire Alarm System Devices - Standard
Condition Typical for age
Quantity 29,500 SF
Unit Cost $4.26
Remaining Useful Life (RUL) 15 Year(s)
D50377 Firee Alarmm Systems
D5038 Security, Surveillance, Extensive D5038 Security, Surveillance, Extensive
Condition Worse than age
Quantity 29,500 SF
Unit Cost $3.18
Remaining Useful Life (RUL) 0 Year(s)
Uniformat Component Description Plan Type Year Expenditures
D5038 Replace D5038 Security, Surveillance, Extensive WO 2019 $93,810
D50388 Securityy andd Detectionn Systems
D5092 Emergency Power, Uninterruptible Power Supply (UPS) D5092 Emergency Power, Uninterruptible Power Supply (UPS)
Condition Typical for age
Quantity 1 EA
Unit Cost $12,094.96
Remaining Useful Life (RUL) 5 Year(s)
Uniformat Component Description Plan Type Year Expenditures
D5092 Replace D5092 Emergency Power, Uninterruptible Power Supply (UPS) CR 2024 $12,095
D50922 Emergencyy Lightt && Powerr Systems
D5092 Generator, Diesel, 250 kW D5092 Generator, Diesel, 250 kW
Condition Typical for age
Quantity 1 EA
Unit Cost $123,293.72
Remaining Useful Life (RUL) 20 Year(s)
D50922 Emergencyy Lightt && Powerr Systems
Item Description
E1026 Shower, Institutional Grade, Package for Built-in, Detention Center, Replace
E1026 Shower, Institutional Grade, Package for Built-in, Detention Center, Replace
Condition Typical for age
Quantity 20 EA
Unit Cost $584.54
Remaining Useful Life (RUL) 5 Year(s)
Uniformat Component Description Plan Type Year Expenditures
E1026 Replace E1026 Shower, Institutional Grade, Package for Built-in, Detention Center, Replace CR 2024 $11,691
E10266 Detentionn Equipment
E1026 Toilet Water Closet/Lavatory Combination, Stainless, Detention Center, Replace
E1026 Toilet Water Closet/Lavatory Combination, Stainless, Detention Center, Replace
Condition Typical for age
Quantity 25 EA
Unit Cost $3,236.54
E10266 Detentionn Equipment
E1093 Commercial Kitchen, Equipment, Large, >500SF, (SF - Kitchen incl. Dishwasher, Walk-in Freezer/Cooler Area)
E1093 Commercial Kitchen, Equipment, Large, >500SF, (SF - Kitchen incl. Dishwasher, Walk-in Freezer/Cooler Area)
Condition Worse than age
Quantity 1,000 SF
Unit Cost $147.21
Remaining Useful Life (RUL) 0 Year(s)
Uniformat Component Description Plan Type Year Expenditures
E1093 Replace E1093 Commercial Kitchen, Equipment, Large, >500SF, (SF - Kitchen incl. Dishwasher, Walk-in Freezer/Cooler Area)
WO 2019 $147,210
E10933 Foodd Servicee Equipment
Appendices
APPENDIX A: Capital Expenditures
APPENDIX B: Photographic Record
APPENDIX A:
Capital Expenditures
APPENDIX A: Capital Expenditures
APPENDIX B:
Photographic Record
APPENDIX B: Photographic Record
B2011 Exterior Wall Construction:- View of B2011 Exterior Wall Construction, Masonry Cavity Wall, Architectural
Block / CMU
B2011 Exterior Wall Construction:- View of B2011 Exterior Wall Construction, Masonry Cavity Wall, Architectural
Block / CMU
W
E
S
N
B2021 Windows:- View of B2021 Steel Fixed Window, 2 Stories, 12 Sq Ft
C1011 Fixed Partitions:- View of C1011 Interior Partitions, GWB on Studs
C3032 Suspended Ceilings:- View of C3032 Ceiling Finish, ACT, Standard
B3011 Roof Finishes:- View of B3011 Built-up Roof
C2011 Regular Stairs:- View of C2011 Metal, Painted, Interior Stairs
D2011 Water Closets:- View of D2011 Tankless Water Closet
D2012 Urinals:- View of D2012 Urinal, Vitreous China
D2018 Drinking Fountains and Coolers:- View of D2018 Drinking Fountains, Refrigerated
D3032 Direct Expansion Systems:- View of D3032 Condenser, Split System, Air Cooled, XX Tons
D2013 Lavatories:- View of D2013 Lavatory, Vitreous China
D2023 Domestic Water Supply Equipment:- View of D2023 Water Heater, Gas, Non-condensing, 120 Gal
D3042 Exhaust Ventilation Systems:- View of D3042 Exhaust Fan, Ceiling, 1,000 Cfm
D3042 Exhaust Ventilation Systems:- View of D3042 Kitchen Exhaust Hood, Commercial
D3068 Building Automation Systems:- View of D3068 Building Controls, Automation - Average
D5012 Low Tension Service & Dist.:- View of D5012 Secondary Transformer, Dry, 113 kVA
D3052 Package Units:- View of D3052 Air Conditioner, Rooftop, Multizone, 8 Ton
D5012 Low Tension Service & Dist.:- View of D5012 Power Panel Board, 208 Y, 120 V, 225 Amp
D5022 Lighting Equipment:- View of D5022 *Lighting, Interior, Fluorescent
D5038 Security and Detection Systems:- View of D5038 Security, Surveillance, Extensive
D5092 Emergency Light & Power Systems:- View of D5092 Generator, Diesel, 250 kW
E1093 Food Service Equipment:- View of E1093 Commercial Kitchen, Equipment, Large, >500SF, (SF - Kitchen incl. Dishwasher, Walk-in Freezer/Cooler Area)
D5092 Emergency Light & Power Systems:- View of D5092 Emergency Power, Uninterruptible Power Supply (UPS)
E1026 Detention Equipment:- View of E1026 Toilet Water Closet/Lavatory Combination, Stainless, Detention Center, Replace
File details come from the government source that posted it. Updated .