This document contains a past performance questionnaire for the NASA Academic Mission Services 2 (NAMS-2) solicitation. The NAMS-2 performance work statement requires support of scientific research associated with air traffic management, advanced technology, quantum computing, nanoelectronics, and prototype software at NASA Ames Research Center. Core requirements include contract management, air traffic management research, academic methods, safety and mission assurance for air traffic management, advanced technological systems, nanoelectronics and devices, advanced software for digital twin systems, quantum computing technology, secure airspace architectures, machine learning and data mining, and advanced air mobility national campaign. Offerors are required to provide past performance questionnaires to NASA for contracts demonstrating experience in these research areas. The questionnaire requests ratings and supporting information on management, staffing, problem resolution, quality assurance and technical performance across the scope of work.
View the file
Other files for this federal contract opportunity
Show all 19
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CLIENT AUTHORIZATION LETTER
, 2023
Dear Client:
We are currently responding to a Request for Proposal (RFP) for the NASA Ames Research Center (ARC) NASA Academic Mission Services (NAMS-2) procurement. The purpose of the NAMS-2 procurement is to support scientific research associated with air traffic management, advanced technology, quantum computing, nanoelectronics, and prototype software. Performance of these services will primarily be at NASA ARC.
Past performance is a factor for source selection under this solicitation. As such, a requirement of NASA’s solicitation is that past clients of ours are asked to provide an impartial assessment of our performance and the scope of work performed on the contract reference performed for your organization.
We have identified of your organization as the point of contact based on his/her knowledge concerning our work.
Please complete the enclosed Past Performance Questionnaire and forward it directly to NASA Contracting Officer, Rosalinda R. De Leon at the following email address, rosalinda.r.deleon@nasa.gov, with a copy to the Contract Specialist, Noor Khazendar at noor.khazendar@nasa.gov.
A response to this questionnaire is requested to the above email address no later than . (Offeror to complete)
Thank you for completing this questionnaire. Any questions may be directed to the undersigned.
Sincerely, Enclosure
Summary of the scope of work under the NAMS-2 procurement
The NAMS-2 Performance Work Statement (PWS) includes Core Contract Management Requirements, Core Technology Area Requirements: Air Traffic Management Research, and an Indefinite-Delivery Indefinite Quantity (IDIQ) component. The requirements include support of scientific research associated with air traffic management, advanced technology, quantum computing, nanoelectronics, and prototype software.
Core requirements include:
(1) Core Contract Management - ensures that the contract requirements are effectively managed and implemented to support all activities covered in the PWS. The required services include: Contract Reporting, Quality Management, Negotiating Task Orders, Safety and Health Adherence, IT Security Adherence, and Records Management.
(2) Core Technology Area: Air Traffic Management (ATM) Research - consists of research and software development, and supports the objectives and missions of the Aeronautics Research Mission Directorate (ARMD) project technology area, primarily supporting NASA researchers and engineers performing R&D. Areas of expertise relevant to this work include aeronautical engineering, modeling and simulation, artificial intelligence, operations research, software engineering, system engineering, electrical engineering, machine learning, and discrete and continuous control.
The IDIQ component includes the following disciplines:
(1) Academic methods – scope includes technical inputs, key findings, trends, and approaches from academia and industry. The required services included: incorporation of academic resources with the goal of enhancing any of the technology areas of the PWS, and support of R&D efforts through conducting laboratory and field-based experiments, performing data analysis, and reporting results.
(2) ATM research for safety and mission assurance - provide technical leadership and expertise to support Safety and Mission Assurance (S&MA) work for ATM research which includes development of software development management plan, software assurance compliance Matrix, and software development matrix.
(3) Advanced Technological Systems (ATS) – development of Data & Reasoning Fabric (DRF) with the goal of enabling the data exchange and management of the volumes of data that will be required for Advanced Air Mobility (AAM) operations including integration with simulated vehicles, integration with external data services, integration analyses, and maintenance of data models.
(4) Nanoelectronics and Devices - development of flexible hybrid electronics for in-space manufacturing of electronics and integration with associated hardware.
(5) Advanced Software for Digital Twin Systems - research on digital twin operations, machine learning (ML), predictive analytics, data analytics, and artificial intelligence (AI) to improve NextGen capabilities including use cases, algorithms and models, software development and testing, technical training, and prototype design.
(6) Quantum computing technology - devise quantum and quantum-classical hybrid algorithms for challenging combinatorial optimization problems in NASA applications including performance metrics, theoretical models, testing results, and circuit formulations.
(7) Secure Airspace Architectures - develop cybersecurity architectures and conceptual research solutions for securing future national airspace environments including security solutions for UAM, modeling and simulation support, and hardware evaluations.
(8) Machine Learning and Data Mining - organize, extract, and present relevant information contained in a variety of real-world data sets including assessment of existing methods, development of new methods and development of software and visualization modes.
(9) Advanced Air Mobility (AAM) National Campaign - National Campaign (NC) Airspace Test Infrastructure (ATI) is the integrator of airspace components from NASA research projects, industry providers, and the data repository for all flight test and simulation test related data for the advanced air mobility operations. Support includes testing for flight test, support partner simulations, data services, governance and data sharing, data analysis and reporting.
PAST PERFORMANCE QUESTIONAIRE
Contract Information
Contractor Name:
Contract Name:
Contract Number:
Agency/Company / Organization Name:
Point of Contact Name and Title/Position:
Point of Contact Email:
Point of Contact Phone:
General Contract Information Please provide the following information about this contract and the contractor’s role:
1. Provide a brief description of services provided by the contractor under this contract. Of the eleven requirements areas listed in the summary on pages 2 and 3, please specifically list the requirement areas (i.e., areas 1-11) which were/are performed under your contract. Additional detail describing specific areas of performance within each of the 11 areas is encouraged.
2. Type of Contract
| Firm Fixed Price |
| ☐ |
| Cost Plus Fixed Fee |
| ☐ |
| Cost Plus Award Fee |
| ☐ |
| Other (Describe): |
| ☐ |
3. Method of Competition
| Non-Competitive |
| ☐ |
Competitive (provide description—e.g., Full and Open, Small Business Set-Aside, etc.)
| Follow-on |
| ☐ |
| New requirement |
| ☐ |
4. Period of Performance (including options/ extensions):
From:
To:
5. Was the contractor the Prime or Sub?
6. If the contract involved task orders, then provide the average number of task orders per year: __________
7. Total Contract Value (including all options): $
8. Briefly describe any change(s) from original contract value (including cost overruns):
9. Was there a cost overrun? ( ) Yes ( ) No
If yes, please explain (please address any overruns in direct and indirect costs, such as increases in overhead rates, and their impact on overall cost performance):
Please use the following adjectival ratings to respond to the questions on the following pages. Please select one rating per statement, using the following definitions and provide supporting information to further explain any rating, as well as in response to the more detailed questions.
Definition of Ratings
Excellent (E) Performance was/is of exceptional merit. It indicates exemplary performance in a timely, efficient, and economical manner and very minor (if any) problems with no adverse effect on overall performance.
| Very Good (VG) |
| Performance was/is very effective. The performance was/is timely, efficient and economical with only minor problems having no adverse effect on overall performance. |
| Good (G) |
| Performance was/is effective. The performance was fully responsive to contract requirements with reportable problems, but with little identifiable effect on overall performance. |
Fair (F) Performance met/meets or slightly exceeds minimum acceptable standards. Adequate results were achieved and there are/were reportable problems with identifiable, but not substantial effects on overall performance.
Poor (P) Performance did not/does not meet minimum acceptable standards in one or more areas. Remedial action is/was required in one or more areas. Performance problems occurred in one or more areas which adversely affected overall performance.
| Not Applicable (N/A) |
| The contractor did not perform this task/scope of work. |
CONTRACTOR’S PERFORMANCE
Please evaluate the contractor’s performance under this contract for the specific services, scope or functions listed below. Please ensure that the rating is consistent with the Definition of Ratings provided above. Please provide supporting information to further explain the selected rating.
PERFORMANCE RATING
(Please circle)
1. Evaluate the contractor’s management of multiple, concurrent, and complex tasks, including management and negotiation of task orders and the quality of task order proposals.
E
VG
G
F
P
N/A
Supporting information for the rating:
PERFORMANCE RATING
2. Evaluate the contractor’s record in recruitment, training and retention of employees with the appropriate skills and expertise for contract and task order performance.
E
VG
G
F
P
Supporting information for the rating:
PERFORMANCE RATING
3. Evaluate the contractor’s management and resolution of contract performance problems, as well as performance monitoring techniques used to track and report to the customer.
E
VG
G
F
P
Supporting information for the rating:
PERFORMANCE RATING
| 4. Evaluate the effectiveness of the contractor’s quality assurance process. |
| E |
| VG |
| G |
| F |
| P |
| N/A |
Supporting information for the rating:
PERFORMANCE RATING
| 5. Evaluate the contractor’s performance in the area of ATM Research |
| E |
| VG |
| G |
| F |
| P |
| N/A |
Supporting information for the rating:
PERFORMANCE RATING
| 6. Evaluate the contractor’s technical performance in the area of Academic Methods. |
| E |
| VG |
| G |
| F |
| P |
| N/A |
Supporting information for the rating:
PERFORMANCE RATING
| 7. Evaluate the contractor’s technical performance in the area of ATM Research Safety and Mission Assurance. |
| E |
| VG |
| G |
| F |
| P |
| N/A |
Supporting information for the rating:
PERFORMANCE RATING
| 8. Evaluate the contractor’s technical performance in the area of Advanced Technological Systems (ATS). |
| E |
| VG |
| G |
| F |
| P |
| N/A |
Supporting information for the rating:
PERFORMANCE RATING
| 9. Evaluate the contractor’s technical performance in the area of Nanoelectronics and Devices. |
| E |
| VG |
| G |
| F |
| P |
| N/A |
Supporting information for the rating:
PERFORMANCE RATING
| 10. Evaluate the contractor’s technical performance in the area of Advanced Software for Digital Twin Systems. |
| E |
| VG |
| G |
| F |
| P |
| N/A |
Supporting information for the rating:
PERFORMANCE RATING
| 11. Evaluate the contractor’s technical performance in the area of Quantum Computing Technology. |
| E |
| VG |
| G |
| F |
| P |
| N/A |
Supporting information for the rating:
PERFORMANCE RATING
| 12. Evaluate the contractor’s technical performance in the area of Secure Airspace Architectures. |
| E |
| VG |
| G |
| F |
| P |
| N/A |
Supporting information for the rating:
PERFORMANCE RATING
| 13. Evaluate the contractor’s technical performance in the area of Machine Learning and Data Mining |
| E |
| VG |
| G |
| F |
| P |
| N/A |
Supporting information for the rating:
PERFORMANCE RATING
| 14. Evaluate the contractor’s technical performance in the area of | Advanced Air Mobility (AAM) National Campaign. |
| E | |
| VG | |
| G | |
| F | |
| P | |
| N/A |
Supporting information for the rating:
PERFORMANCE RATING
| 15. Evaluate the contractor’s performance in identification of risks and successful mitigation of those risks, including accuracy of estimated schedule and cost impacts. |
| E |
| VG |
| G |
| F |
| P |
| N/A |
Supporting information for the rating:
16. Describe any serious contract performance problems (e.g., termination for default, regulatory violations) resulting from contractor’s performance.
Submitted By (Signature) Date
File details come from the government source that posted it. Updated .