Question 1. I read where the award was anticipated August 30, 2022 and the work completion date was
November 1, 2022 but I did not see where there was any indication of when the vessel may be available. Is that information available?
Answer: The vessel will be available after August 25, 2022. However, scheduling of this work must accommodate vessel underway time for research projects and reserve dates. Therefore, the Contractor shall coordinate with the Government Point of Contact Vessel Operations Coordinator or the Vessel
Captain to schedule the work upon receipt of contract award.